Work packages and control accounts: where the numbers live
This chapter assumes you know what a work breakdown structure (WBS) is and can read task-level estimates. The earlier chapters introduced the performance measurement baseline. This chapter looks at the level where its numbers are stored and collected. Later chapters define planned value, earned value, and actual cost precisely. Here you will see where each of those three values comes from.
Why the level of detail matters
A project-wide EVM report is a sum of many small pieces. If those pieces are badly defined, the totals are wrong, and nobody can tell where. Two structures carry the data:
- A work package is the lowest-level deliverable-based piece of work in the WBS. It has a defined scope, a budget, a schedule, and a single owner.
- A control account is a management point where scope, budget, actual cost, and schedule are brought together and compared. It holds one or more work packages.
Work packages are where work is planned and progress is measured. Control accounts are where variances are calculated, analyzed, and reported. Projects usually report EVM at the control account level and above, and drill down to work packages when something looks wrong.
How the structure fits together
The WBS breaks the project down by deliverable. You then choose control account points in the WBS, usually at the level where one person can answer for the cost and schedule. Each control account contains work packages. Budgets and schedules at the work package level add up to the control account, and control accounts add up to the project.
Each box carries a budget. The figures in the diagram match the three-phase example used throughout this tutorial, so the control accounts here are the same Design, Build, and Test packages with a finer split underneath.
What a work package must contain
A work package that can feed EVM needs these attributes:
| Attribute | Why EVM needs it |
|---|---|
| Unique identifier | Lets cost, schedule, and progress data be matched to the same item |
| Scope description | Defines what "done" means, so progress can be measured |
| Budget | Becomes the basis for planned value and earned value |
| Start and finish dates | Spread the budget over time to create the time-phased plan |
| Progress rule | Says how completion will be claimed (covered in a later chapter) |
| One responsible owner | Gives someone accountability for the variance |
If any of these is missing, a specific EVM number becomes unreliable. A missing date means planned value cannot be placed in time. A vague scope means earned value cannot be justified. A missing owner means nobody explains a variance.
Sizing work packages
Work package size is a trade-off, and there is no universal right answer. These are common rules of thumb:
- Duration. Many organizations aim for packages of about one reporting period up to a few periods. A package that lasts a year will show 0% done for months, then jump.
- Effort. A package should be small enough to estimate and measure with confidence, and large enough that tracking it does not cost more than the work.
- Ownership. Each package should be doable by one team or discipline, so one person is accountable.
- Measurability. If you cannot say whether the package is 40% or 60% complete, split it, or choose a rule that does not depend on guessing.
Packages that are too large hide problems inside them and push you toward subjective percent-complete claims. Packages that are too small create reporting overhead and noisy data. Splitting a long package into milestones, each with its own budget, is often the best fix.
Planning packages
Not all work is detailed at the start. A planning package is a placeholder for work in a control account that is known but not yet broken into work packages. It has a budget and a rough time frame. As the work gets closer, you convert the planning package into work packages. The budget stays inside the same control account.
Planning packages let you baseline the whole project early without inventing detail you do not have. They are part of the baseline, so they count towards the budget at completion. Converting them is a normal planning step. Moving budget into or out of a control account is a baseline change and needs approval.
Charge numbers and actual cost
Actual cost comes from accounting systems such as timesheets, purchase orders, and invoices. The link between those systems and EVM is a charge number, sometimes called a cost code or account code. Each work package gets one or more charge numbers, and people record time and expenses against them.
This link is where many EVM programs fail. If people book time to a general project code, the actual cost for a given work package cannot be separated. Then cost variance at the control account level is meaningless. Two rules help:
- Every charge number maps to exactly one work package, and every work package maps to exactly one control account.
- Work that is not in any work package should not have a charge number, because it is out of scope or an unapproved change.
Rolling up budgets in code
The structure is simple enough to check automatically. This script rolls work package budgets up to control accounts and rejects two common data errors: duplicate package identifiers and packages that point to an unknown control account.
from collections import defaultdict
control_accounts = {
"CA-1": {"name": "Design", "manager": "Rivera"},
"CA-2": {"name": "Build", "manager": "Okafor"},
"CA-3": {"name": "Test", "manager": "Lindqvist"},
}
work_packages = [
{"id": "1.1", "account": "CA-1", "name": "Requirements", "budget": 8000},
{"id": "1.2", "account": "CA-1", "name": "Architecture", "budget": 12000},
{"id": "2.1", "account": "CA-2", "name": "Backend", "budget": 30000},
{"id": "2.2", "account": "CA-2", "name": "Frontend", "budget": 20000},
{"id": "3.1", "account": "CA-3", "name": "Test plan", "budget": 10000},
{"id": "3.2", "account": "CA-3", "name": "Execution", "budget": 20000},
]
def roll_up(accounts, packages):
"""Return the budget of each control account, checking basic integrity."""
ids = [wp["id"] for wp in packages]
if len(ids) != len(set(ids)):
raise ValueError("duplicate work package id")
totals = defaultdict(float)
for wp in packages:
if wp["account"] not in accounts:
raise ValueError(f"{wp['id']} has no control account")
totals[wp["account"]] += wp["budget"]
return dict(totals)
totals = roll_up(control_accounts, work_packages)
for ca, total in totals.items():
print(ca, control_accounts[ca]["name"], f"{total:,.0f}")
print("BAC", f"{sum(totals.values()):,.0f}")The output is:
CA-1 Design 20,000
CA-2 Build 50,000
CA-3 Test 30,000
BAC 100,000The sum of the control accounts is the budget at completion, which the next chapters build on. Notice that the check is only about structure. It cannot tell you whether the budgets are realistic.
Common errors
- Work packages that overlap in scope. The same work is budgeted twice, or claimed as progress twice. The baseline is inflated, and earned value is overstated.
- Missing scope. Work that is not in any package has no budget, so its cost appears as an unexplained overrun.
- Control accounts with several owners. Nobody is accountable, and variance explanations become vague.
- Levels of effort mixed with discrete work. Project management and support activities have no deliverable. They are usually tracked in their own packages, with a progress rule that matches their nature.
- Changing budgets silently. Moving budget between packages to hide a variance destroys the baseline. Changes should go through change control.
Exercises
Exercise
A team books all its time to one project-wide charge number. Which EVM measure becomes unreliable at the control account level, and why?
Show answer
Actual cost, and therefore cost variance and CPI. Without a charge number per work package, actual cost cannot be assigned to a control account, so it cannot be compared with that account's earned value.
Exercise
A work package is budgeted at 60,000 and runs for ten months. It shows 0% complete for nine months and then 100%. What is the problem, and what is one fix?
Show answer
The package is too long to measure progress between its start and end, so status is hidden until the end. Split it into smaller packages, or into milestones with their own budgets, so progress is visible each period.