Deciding how much work counts as done
This chapter assumes you know how a work breakdown structure (WBS) divides a project into work packages, and that you can compute planned value (PV) and budget at completion (BAC) from a time-phased budget. Here you will learn how to turn "how far along are we?" into a number that earned value can use.
Why the rule matters
Earned value (EV) is the budget for the work actually finished. It is BAC for the package multiplied by the fraction of that work considered complete. PV and actual cost (AC) come from the plan and the ledger. The completion fraction is the only part someone has to judge. A different rule on the same package produces a different EV, and therefore a different schedule variance (SV), cost variance (CV), SPI, and CPI.
For that reason, the rule is chosen when the baseline is built, not when the status report is due. The rule is written down for each work package or control account before work starts. If you pick it afterward, you can choose whichever rule makes the project look better.
The common crediting rules
Fixed formula
A fixed formula gives set credit at the start and the rest at finish. The usual splits are 0/100, 50/50, and 25/75.
- 0/100 gives nothing until the work is done. It is the most conservative choice.
- 50/50 gives half the budget when work starts and half when it finishes.
- 25/75 gives a quarter at start and three quarters at finish.
Fixed formulas suit short packages, such as those lasting one or two reporting periods. They need no judgment about partial progress. Within a package, there is only a "started" fact and a "finished" fact to check.
Weighted milestones
A weighted milestone rule splits a longer package into checkpoints. Each checkpoint gets a weight, and the weights add up to 100%. The package earns a milestone's weight only when that milestone is complete.
Good milestones are objective. "Wiring inspected and signed off" is a good one. "Wiring mostly done" is not. Weights usually follow the budget for the effort leading up to each milestone, so a milestone that takes 40% of the effort carries about 40% of the weight.
Percent complete
A percent-complete rule has someone estimate the fraction done, such as 60%. It is the easiest rule to apply and the easiest to distort. Use it only when no objective milestones exist, and anchor the estimate to evidence: units produced, tests passed, or an estimate of remaining effort.
Other rules you will meet
- Units completed counts finished items against a planned quantity, such as 300 of 1,000 meters of cable laid. It works when units are alike in size.
- Level of effort (LOE) covers work that has no finished product, such as project management or support. Its EV is set equal to PV, so it never shows a schedule variance. Keep LOE small, because it makes SPI look better than the real work justifies.
Choosing a rule
The choice depends on package length and on whether objective checkpoints exist.
A worked comparison
Take the Build package from the earlier examples, with a budget of 50,000. Assume this is where it stands at the status date:
- Work has started but is not finished.
- Of four milestones, foundation (weight 15%) and framing (25%) are complete. Wiring (40%) and inspection (20%) are not.
- The package manager believes the work is 60% complete.
The following code applies each rule to the same facts.
def fixed_formula(budget, started, finished, start_credit=0.5):
"""Credit start_credit at start, the full budget at finish."""
if finished:
return budget
if started:
return budget * start_credit
return 0.0
def weighted_milestones(budget, milestones):
"""milestones is a list of (weight, done) pairs; weights must sum to 1."""
total = sum(weight for weight, _ in milestones)
if abs(total - 1.0) > 1e-9:
raise ValueError(f"Milestone weights sum to {total}, expected 1.0")
earned_weight = sum(weight for weight, done in milestones if done)
return budget * earned_weight
def percent_complete(budget, fraction):
"""fraction is a number from 0 to 1."""
if not 0 <= fraction <= 1:
raise ValueError("fraction must be between 0 and 1")
return budget * fraction
budget = 50000
milestones = [(0.15, True), (0.25, True), (0.40, False), (0.20, False)]
results = {
"0/100": fixed_formula(budget, started=True, finished=False, start_credit=0.0),
"50/50": fixed_formula(budget, started=True, finished=False, start_credit=0.5),
"Weighted milestones": weighted_milestones(budget, milestones),
"Percent complete (60%)": percent_complete(budget, 0.60),
}
for rule, ev in results.items():
print(f"{rule}: EV = {ev:,.0f}")Running it prints:
0/100: EV = 0
50/50: EV = 25,000
Weighted milestones: EV = 20,000
Percent complete (60%): EV = 30,000The same package is worth anywhere from 0 to 30,000 depending on the rule. If PV for this package is 25,000, the SV is -25,000, 0, -5,000, or +5,000 under the four rules. The work did not change. Only the crediting rule did.
Edge cases
Partial milestones
Weighted milestones give no credit for a milestone that is 90% done. That is deliberate, because it keeps the number tied to something that can be verified. If this makes EV lag too much on long milestones, split the milestone into smaller ones. Do not switch to a vague percentage.
Rework
Rework should not earn credit twice. If framing was credited and then had to be redone, the redo cost goes into AC and EV stays the same. CPI drops, which is the correct signal. Do not reduce EV and then re-earn it, because that makes the cost problem harder to see.
Changing the rule mid-package
Do not change the rule once work has started unless the change is approved through baseline change control. Switching rules shifts EV and breaks trend comparisons between periods.
EV never exceeds the budget
A package's EV can reach its budget and no further. Overrunning the budget raises AC, not EV. A percent complete above 100% is always an error.
Packages not yet started
If a package has no started work, its EV is zero. This is true even when the team has spent money preparing, such as buying materials. That spending raises AC without raising EV, and CPI shows it.
Practical guidance
- Record the crediting rule beside each work package in the baseline.
- Keep packages short enough, ideally within one or two reporting periods, so that fixed formulas or a few milestones can do the job.
- Define each milestone's completion evidence, such as an approved deliverable, a passed test, or an inspection record.
- Cap percent-complete estimates by the evidence: if no test has passed, do not report more than the weights of the milestones that have been met.
- Keep LOE as a small share of BAC, and report it separately so its flat SPI does not mask problems elsewhere.
Exercise
A work package has a budget of 80,000 and four milestones weighted 10%, 30%, 40%, and 20%. The first two are complete, the third is about 75% done, and the fourth has not started. The package manager says "we are about 70% complete." Using weighted milestones, what is the package's EV, and how does it compare with the manager's estimate under percent complete? Which would you report, and why?
Show answer
Weighted milestones credit only completed milestones: 10% + 30% = 40%, so EV = 0.40 x 80,000 = 32,000. The manager's percent-complete estimate gives 0.70 x 80,000 = 56,000. The 24,000 difference comes from crediting 30 percentage points of unfinished work that the milestone rule does not count. Report the weighted-milestone figure, because it is tied to verifiable completions and the rule was set in the baseline. The 70% estimate is subjective and cannot be checked against evidence.