Sub topic 13
Forecasting the Estimate at Completion
This chapter assumes you can already compute BAC, PV, EV, AC, CPI, and SPI from the earlier chapters. It covers how to turn a status snapshot into a forecast of the final cost.
What the estimate at completion answers
The estimate at completion (EAC) is a forecast of the total cost of the project when it finishes. It is the actual cost spent so far plus a forecast of what the remaining work will cost:
EAC = AC + ETC
The budget at completion (BAC) is the original plan. The EAC is your current best guess. If the two differ, the project expects to finish over or under budget.
There is no single correct EAC formula. Each formula encodes an assumption about how the remaining work will perform. Choosing the formula means choosing the assumption, so you should be able to defend it.
The three standard formulas
The examples use one status snapshot: BAC = 100,000, PV = 40,000, EV = 30,000, AC = 45,000. That gives CPI = 30,000 / 45,000 ≈ 0.67 and SPI = 30,000 / 40,000 = 0.75.
| Assumption about the remaining work | Formula | Result |
|---|---|---|
| Current cost efficiency continues (typical variance) | EAC = BAC / CPI | 150,000 |
| The overrun was a one-time event (atypical variance) | EAC = AC + (BAC - EV) | 115,000 |
| Cost and schedule efficiency both drive remaining cost | EAC = AC + (BAC - EV) / (CPI x SPI) | 185,000 |
| The original estimates are no longer valid | EAC = AC + a new bottom-up ETC | depends on the re-estimate |
Typical variance: BAC / CPI
This formula assumes the project will keep earning 0.67 of value for each unit of currency spent. It is mathematically the same as AC + (BAC - EV) / CPI. Use it when the cause of the overrun is likely to continue, such as an underestimated productivity rate or a vendor whose prices are higher than planned.
Atypical variance: AC + (BAC - EV)
This formula assumes the remaining work will be done at the planned rate. You keep the money already lost and add the unearned budget unchanged. Use it only when you can name a specific one-off cause, such as a rework event that has been fixed. It is the most optimistic formula, so it needs the strongest evidence.
Cost and schedule together: AC + (BAC - EV) / (CPI x SPI)
This formula penalizes the remaining work for both cost and schedule inefficiency. It fits projects where a late schedule drives extra cost, for example through overtime, expediting fees, or extended overhead. Here CPI x SPI = 0.5, so the remaining 70,000 of budgeted work is forecast to cost 140,000, and the EAC is 45,000 + 140,000 = 185,000.
Be careful with this one. SPI is a measure of schedule, not cost, and it drifts toward 1.0 as the project ends (a later chapter covers why). That drift makes the formula less reliable late in a project.
Bottom-up re-estimate
When the original estimates are clearly wrong, no index-based formula helps. Ask the work package owners to re-estimate the remaining work from scratch. The new estimate to complete (ETC) is added to AC. It takes the most effort but is the only option that does not depend on past ratios.
Choosing a formula
Computing the forecasts in code
The first script calculates the three index-based forecasts from the same status data.
bac, pv, ev, ac = 100000, 40000, 30000, 45000
cpi = ev / ac
spi = ev / pv
eac_typical = bac / cpi # current CPI continues
eac_atypical = ac + (bac - ev) # past overrun was a one-off
eac_cost_and_schedule = ac + (bac - ev) / (cpi * spi) # CPI and SPI both drive remaining cost
print(round(eac_typical)) # 150000
print(round(eac_atypical)) # 115000
print(round(eac_cost_and_schedule)) # 185000The second script wraps the choice in a function. It makes the assumption an explicit argument, so the report shows which one you used.
def forecast_eac(bac, ev, ac, pv, method, new_etc=None):
"""Return EAC for a named assumption. All inputs share one currency."""
if ev <= 0 or ac <= 0 or pv <= 0:
raise ValueError("EV, AC, and PV must be positive")
cpi = ev / ac
spi = ev / pv
if method == "typical":
return bac / cpi
if method == "atypical":
return ac + (bac - ev)
if method == "cost_schedule":
return ac + (bac - ev) / (cpi * spi)
if method == "bottom_up":
if new_etc is None:
raise ValueError("bottom_up requires new_etc")
return ac + new_etc
raise ValueError(f"unknown method: {method}")
for method in ("typical", "atypical", "cost_schedule"):
eac = forecast_eac(100000, 30000, 45000, 40000, method)
print(f"{method:14s} EAC={eac:>10,.0f} VAC={100000 - eac:>10,.0f}")
eac = forecast_eac(100000, 30000, 45000, 40000, "bottom_up", new_etc=90000)
print(f"{'bottom_up':14s} EAC={eac:>10,.0f} VAC={100000 - eac:>10,.0f}")The variance at completion (VAC = BAC - EAC) shows how far each forecast is from the budget. For the typical formula, VAC = -50,000, so the project is forecast to overrun by half its budget.
Edge cases and common errors
- EV of zero. CPI is 0, so BAC / CPI divides by zero. Early in a project, with no earned value yet, index-based forecasts are meaningless. Use the bottom-up method or keep the BAC until real progress exists.
- CPI above 1. BAC / CPI then gives an EAC below the BAC. That is valid arithmetic, but many organizations will not publish an underrun forecast until the work is largely complete, because early CPI often reflects delayed invoices rather than real efficiency.
- Cumulative versus period CPI. The standard formulas use cumulative CPI (total EV / total AC). Using the CPI of a single good month hides a long history of overruns. If recent performance clearly differs, say so and consider a bottom-up estimate.
- Mixing currencies or units. BAC, EV, and AC must all be in the same currency and base year. Mixing hours with currency produces a meaningless CPI.
- Treating the range as one number. The typical EAC (150,000) and cost-and-schedule EAC (185,000) differ by 35,000. Reporting a range makes the uncertainty visible, and a single figure hides it.
From EAC to the next steps
Once you have an EAC, two derived values follow directly. The estimate to complete is ETC = EAC - AC, and the variance at completion is VAC = BAC - EAC. The next chapter covers both. After that, TCPI tests whether the efficiency needed to hit a target is achievable.
Exercise
A project has BAC = 200,000, EV = 80,000, and AC = 100,000. The manager confirms that a one-time equipment failure caused the whole overrun and that it has been fixed. (a) Which EAC formula fits, and what is the EAC? (b) What would the EAC be if the overrun were instead expected to continue at the current CPI?
Show answer
(a) The overrun is atypical, so use EAC = AC + (BAC - EV) = 100,000 + (200,000 - 80,000) = 220,000. (b) CPI = 80,000 / 100,000 = 0.8, so EAC = BAC / CPI = 200,000 / 0.8 = 250,000. The assumption about the remaining work changes the forecast by 30,000.
Exercise
Using BAC = 100,000, PV = 40,000, EV = 30,000, and AC = 45,000, calculate the EAC with the cost-and-schedule formula and explain why it is higher than BAC / CPI.
Show answer
CPI = 30,000 / 45,000 = 0.667 and SPI = 30,000 / 40,000 = 0.75, so CPI x SPI = 0.5. EAC = 45,000 + (100,000 - 30,000) / 0.5 = 45,000 + 140,000 = 185,000. It is higher than BAC / CPI (150,000) because it also assumes the schedule delay raises the cost of the remaining work, so the remaining 70,000 of work costs twice its budget instead of 1.5 times.