Sub topic 12
Interpreting status: the four common cases
This chapter assumes you can already compute PV, EV, and AC for a status date and derive SV, CV, SPI, and CPI from them. Here you learn to turn those numbers into a statement about the project and a decision about what to do next.
Two questions, two axes
EVM answers two separate questions, and each uses its own pair of values:
- Schedule: has the project earned as much value as it planned to by now? Compare EV with PV. SV = EV − PV and SPI = EV / PV.
- Cost: did the earned value cost what the budget allowed? Compare EV with AC. CV = EV − AC and CPI = EV / AC.
The two answers are independent. A project can be ahead on one axis and behind on the other. Crossing the two axes gives four cases, and each case points to different causes and different management responses.
| Case | Schedule (SPI) | Cost (CPI) | Typical reading |
|---|---|---|---|
| 1 | Above 1.0 (ahead) | Above 1.0 (under budget) | Healthy, but check the data |
| 2 | Above 1.0 (ahead) | Below 1.0 (over budget) | Speed bought with money, or rework |
| 3 | Below 1.0 (behind) | Above 1.0 (under budget) | Cost-efficient but slow, often a resourcing issue |
| 4 | Below 1.0 (behind) | Below 1.0 (over budget) | Most serious: late and expensive |
A value of exactly 1.0 means on plan. In practice, no project hits 1.0 exactly, so organizations set tolerance bands, for example treating an index between 0.95 and 1.10 as acceptable. The band is a policy choice, not part of EVM itself. The sign of the variance and the side of 1.0 for the index always agree: SV > 0 exactly when SPI > 1, and CV > 0 exactly when CPI > 1.
Classifying a status date in code
The function below computes both indices and names the case. It uses the status figures from earlier chapters for case 4 and three invented status dates for the other cases.
def classify(pv, ev, ac, tolerance=0.0):
"""Name the schedule/cost case for one status date.
tolerance widens the 'on plan' band around 1.0 (for example 0.05).
"""
if pv <= 0 or ac <= 0:
raise ValueError("PV and AC must be positive")
spi = ev / pv
cpi = ev / ac
def side(index, ahead, behind):
if index > 1 + tolerance:
return ahead
if index < 1 - tolerance:
return behind
return "on plan"
schedule = side(spi, "ahead of schedule", "behind schedule")
cost = side(cpi, "under budget", "over budget")
return spi, cpi, schedule, cost
status_dates = {
"Case 1": (40000, 46000, 42000),
"Case 2": (40000, 46000, 52000),
"Case 3": (40000, 32000, 30000),
"Case 4": (40000, 30000, 45000),
}
for name, (pv, ev, ac) in status_dates.items():
spi, cpi, schedule, cost = classify(pv, ev, ac)
print(f"{name}: SPI {spi:.2f}, CPI {cpi:.2f} -> {schedule}, {cost}")The output is:
Case 1: SPI 1.15, CPI 1.10 -> ahead of schedule, under budget
Case 2: SPI 1.15, CPI 0.88 -> ahead of schedule, over budget
Case 3: SPI 0.80, CPI 1.07 -> behind schedule, under budget
Case 4: SPI 0.75, CPI 0.67 -> behind schedule, over budgetSetting tolerance=0.05 would report any index between 0.95 and 1.05 as "on plan". That lets a report show green, amber, and red instead of a strict above or below.
The decision path
Reading each case
Case 1: ahead and under budget
The work is completing faster and cheaper than planned. This is the best outcome, but do not stop at the numbers. Ask whether the baseline was padded, whether progress is being claimed too generously, and whether costs are missing from AC. If the data holds up, the project may forecast a finish below BAC.
Case 2: ahead and over budget
More work is done than planned, but it cost more than the budget allowed. Common causes are overtime, extra staff added to compress the schedule, premium-priced materials, and rework. The schedule gain was paid for. Decide whether the earlier finish is worth the cost. If it is not, slow the spending rate. If the cost trend continues, CPI drives the final forecast, which a later chapter covers.
Case 3: behind and under budget
The work costs less than planned per unit of progress, but less of it is getting done. The low spending is partly an artifact: people who are not working are not billing. Look for unfilled positions, waiting on approvals or deliveries, or a blocked dependency. The underspend is not a saving if the missing work must still be done later at full price.
Case 4: behind and over budget
The project is late and each unit of progress costs more than planned. This case needs the earliest and firmest intervention. Look for a root cause that affects both axes, such as an underestimated scope, a skills gap, or a defect-heavy product that generates rework. Recovery is hard because the remaining work will probably be done at the same poor efficiency unless something changes.
With the status figures above (BAC 100,000, PV 40,000, EV 30,000, AC 45,000), SV is −10,000, CV is −15,000, SPI is 0.75, and CPI is about 0.67. That is case 4. Each currency unit spent has earned only about 0.67 units of planned value, and only 75% of the scheduled work is done.
Cross-checks before you trust a case
Any case can come from bad data. Run these checks before acting on the label.
- Cost lag. Invoices, timesheets, and accruals often post late. If AC is understated, CPI looks better than reality and a case 4 project can appear as case 3. Confirm that AC includes all committed costs through the status date.
- Progress rules. EV is only as honest as the rule that measures it. Percent-complete estimates tend to run optimistic, especially for work reported as "90% done" for weeks. Fixed-formula and weighted-milestone rules resist this better.
- Same scope on both sides. PV, EV, and AC must cover the same work packages and the same cumulative period. A mismatch, such as AC that includes a work package outside the baseline, produces a false cost signal.
- Trend over snapshot. One status date is a point. Compare the last several periods. A CPI that was 0.95 and is now 0.88 deserves more attention than one that has sat at 0.88 for months. Early-period indices are noisy because the amounts are small.
- Late-project SPI. As the project nears completion, EV converges to BAC and PV reaches BAC at the planned end date. SPI therefore drifts toward 1.0 even for a project that finishes late. A late project with SPI = 0.99 is not nearly on time. Earned schedule, covered in a later chapter, addresses this.
Choosing a response
The case suggests a first question, not a fixed action:
- Case 1: confirm the data, then protect the gain by not releasing resources prematurely.
- Case 2: find what is driving cost above plan, and decide whether the schedule gain justifies it.
- Case 3: find the cause of the slow progress, such as missing resources or blockers, and expect the cost to rise once they are removed.
- Case 4: find a shared root cause, and rebaseline or re-forecast only after approved scope and funding are confirmed.
Exercise
At a status date, PV is 60,000, EV is 66,000, and AC is 72,000. Which of the four cases is this? Give SPI and CPI, and name one plausible cause.
Show answer
SPI = 66,000 / 60,000 = 1.10 (ahead of schedule). CPI = 66,000 / 72,000 ≈ 0.92 (over budget). This is case 2: ahead and over budget. A plausible cause is overtime or added staff used to speed up the work, or rework that raised cost without slowing progress.
Exercise
A project shows SPI = 0.85 and CPI = 1.20. A manager says the project is doing well because it is far under budget. What is wrong with that conclusion, and what would you check?
Show answer
The project is in case 3: behind schedule and under budget. The low cost may be a result of less work being done, for example unfilled roles or blocked tasks, so the saving may disappear when that work is finally performed. Check for unstaffed positions, waiting dependencies, and unposted costs in AC, and look at whether the delayed work lies on the critical path.