Sub topic 8
Actual Cost: What the Work Really Cost
This chapter assumes you know the basics of a work breakdown structure (WBS), control accounts, and the planned value (PV) and earned value (EV) definitions from the earlier chapters. You should also be comfortable with simple ratios and spreadsheet arithmetic.
What actual cost measures
Actual cost (AC) is the total cost actually incurred and recorded for the work performed during a given period. Some sources call it ACWP, the actual cost of work performed. It answers one question: how much have we spent to get the work that is done?
AC is the third leg of earned value management (EVM). PV is the budgeted cost of the work scheduled. EV is the budgeted cost of the work performed. AC is the real cost of the work performed. EV and AC describe the same work, so comparing them tells you whether that work cost more or less than planned.
| Value | Question it answers | Priced at |
|---|---|---|
| PV | What should be done by now? | Budget |
| EV | What is done, in budget terms? | Budget |
| AC | What did the done work cost? | Actual spend |
AC has no meaning on its own. Spending 45,000 is neither good nor bad until you know how much work that money bought. Only the comparison with EV gives it meaning.
The matching rule
AC must cover exactly the same scope as EV. If EV counts only the work packages that are finished or partly finished, AC must include only the cost of that work. Otherwise cost variance (CV = EV − AC) compares unlike things.
Three situations commonly break this rule:
- Spending on work not yet started. Buying materials early, or paying a deposit, is a real payment. It is not cost of work performed unless the budget treats it that way.
- Work done but not yet paid for. Labor hours that have been worked but not yet entered in the payroll or timesheet system.
- Scope outside the baseline. Time spent on unapproved extras is real cost, but it earns no EV because the work is not in the baseline.
Where AC comes from
AC is collected at the control account level, using the same WBS and cost codes that the budget uses. A typical project draws it from several sources:
- Timesheets and payroll, which supply labor cost. Hours are multiplied by a cost rate.
- Accounts payable, which supplies vendor and subcontractor invoices.
- Procurement and inventory records, which supply materials and equipment.
- Overhead and allocation rules, which spread shared costs across projects.
The key requirement is consistency. If the budget for labor includes benefits and overhead (a fully loaded rate), then AC for labor must be loaded the same way. Comparing a loaded budget to unloaded actuals makes the project look better than it is.
Incurred versus paid: timing
Cash leaving the bank and cost being incurred are different events. EVM uses incurred cost, recorded when the work is done or the goods are received, not when the invoice is paid.
Suppose a subcontractor finishes testing work in March and invoices you in April, and you pay in May. The cost belongs in March, next to the EV the testing earned. If you record it in May, March shows a low AC and a flattering CPI, and May looks worse than it was.
When accounting systems lag, teams record an accrual, an estimate of cost incurred but not yet invoiced. Accruals keep AC aligned with EV. They are replaced with the real figure when the invoice arrives.
Cumulative and period values
AC is usually reported two ways. Period AC is the cost in one reporting period, such as one month. Cumulative AC, or "to date" AC, is the sum of all period values from the project start to the status date. The EVM formulas use cumulative values for PV, EV, and AC, all taken at the same status date.
# Period actual cost by month, then the cumulative figure at each status date
period_ac = {"Jan": 12000, "Feb": 18000, "Mar": 15000}
cumulative = 0
for month, cost in period_ac.items():
cumulative += cost
print(f"{month}: period {cost:,} cumulative {cumulative:,}")The output ends with Mar: period 15,000 cumulative 45,000. This matches the 45,000 actual cost used in the running example in this tutorial.
What AC should and should not include
Include cost that the baseline budgets for and that was incurred on baseline work: direct labor, materials, subcontracts, equipment, and allocated indirect cost if the budget includes it.
Handle these items with care:
- Management reserve is not AC. It is an unallocated budget held back for unknown risks and is not part of the performance baseline. It enters the baseline only when it is released to a control account.
- Contingency reserve is part of the cost baseline for known risks. Spending it on a risk event is AC and should be charged to the affected work.
- Rework is AC. Redoing a defective deliverable adds cost and no new EV, which is exactly why CPI falls.
- Unapproved scope is real cost without EV. Track it, and push it through change control so that either the baseline is updated or the work stops.
Using AC in the metrics
Once you have AC, it feeds several measures from the Topic Spine:
- CV = EV − AC
- CPI = EV / AC
- EAC = BAC / CPI, when current cost efficiency is expected to continue
- ETC = EAC − AC
- TCPI = (BAC − EV) / (BAC − AC)
The following function takes the chapter's running numbers and shows how AC changes the result, holding EV fixed.
def cost_view(ev, ac):
"""Cost variance and CPI for a given earned value and actual cost."""
if ac <= 0:
raise ValueError("AC must be positive to compute CPI")
return {"CV": ev - ac, "CPI": ev / ac}
ev = 30000
for ac in (25000, 30000, 45000, 60000):
r = cost_view(ev, ac)
print(f"AC {ac:>6,}: CV {r['CV']:>8,} CPI {r['CPI']:.2f}")With EV fixed at 30,000, an AC of 25,000 gives CV +5,000 and CPI 1.20. An AC of 45,000 gives CV −15,000 and CPI 0.67. The work did not change, only what it cost.
Data quality failure modes
AC errors are quiet. The numbers still compute, and the dashboard still looks plausible. Watch for these patterns:
| Problem | Effect on AC | Effect on reported status |
|---|---|---|
| Late timesheets | AC too low | CPI looks better than reality |
| Missing accruals | AC too low in one period, too high in the next | CPI swings from period to period |
| Costs charged to the wrong control account | AC wrong in two accounts | One account looks overrun, another looks efficient |
| Unloaded labor rates against a loaded budget | AC too low | CPI is overstated |
| Shared overhead not allocated | AC too low | Project looks cheaper than it is |
| Rework charged to a general account | AC too low on the affected package | Quality problems stay hidden |
A common sign of incomplete AC is a CPI that sits close to 1.00 for months and then drops sharply when late invoices and timesheets are posted. A CPI that is too good for too long deserves a check of the cost feed before anyone celebrates.
How AC fits the whole picture
Practical habits
- Use the same WBS and cost codes for budget and actuals, so that every dollar of AC lands where its budget lives.
- Report AC and EV at the same status date, and cut off both at the same time.
- Record accruals for work performed but not invoiced.
- Reconcile EVM actuals to the accounting ledger every period.
- Chase down any large single-period change in CPI before treating it as a performance trend.
Exercise
At the end of June, a project has an earned value of 60,000. The team recorded 66,000 of labor and invoices. A subcontractor also completed 6,000 of testing work in June that is on the baseline, but the invoice has not arrived. No accrual was recorded. What are the reported CPI and the correct CPI, and which one should the project use?
Show answer
The reported CPI is 60,000 / 66,000 = 0.91. The subcontractor work was performed in June, so the incurred cost belongs in June. With a 6,000 accrual, AC becomes 72,000 and the correct CPI is 60,000 / 72,000 = 0.83. Use 0.83. The reported figure overstates cost efficiency because AC is missing incurred cost, and the same problem would appear as a cost spike in the month the invoice arrives.
Exercise
A team's labor budget uses a fully loaded rate of 100 per hour. Timesheets are costed at the base pay rate of 70 per hour. They have worked 400 hours on tasks whose earned value is 40,000. What CPI do they report, and what is the CPI if actuals use the loaded rate?
Show answer
Reported AC is 400 x 70 = 28,000, so CPI is 40,000 / 28,000 = 1.43. At the loaded rate, AC is 400 x 100 = 40,000, so CPI is 40,000 / 40,000 = 1.00. The budget and actuals must use the same rate basis. The mismatch makes the team look 43% more efficient than it is.