02Chapter 2: The performance measurement baselineYou should know basic project management vocabulary (scope, schedule, budget, milestone) and what a work breakdown structure (WBS) is. You should also be comfortable with percentages and simple spreadsheet arithmetic. This chapter does not compute variances or indices yet. It builds the reference pl6 min read
03Chapter 3: Work packages and control accounts: where the numbers liveThis chapter assumes you know what a work breakdown structure (WBS) is and can read task-level estimates. The earlier chapters introduced the performance measurement baseline. This chapter looks at the level where its numbers are stored and collected. Later chapters define planned value, earned valu5 min read
04Chapter 4: Planned value: the budgeted cost of work scheduledThis chapter assumes you know what a work breakdown structure (WBS) and a baseline schedule are. It also assumes you can do percentage and ratio arithmetic. By the end you should be able to build planned value (PV) from a schedule, read it at any status date, and avoid the usual mistakes when using 5 min read
05Chapter 5: Budget at completion: the total of the planBudget at completion (BAC) is the total budget for all the work in the performance measurement baseline. It is the number at the top of the plan, and nearly every forecast formula in earned value management uses it.4 min read
06Chapter 6: Deciding how much work counts as doneThis chapter assumes you know how a work breakdown structure (WBS) divides a project into work packages, and that you can compute planned value (PV) and budget at completion (BAC) from a time-phased budget. Here you will learn how to turn "how far along are we?" into a number that earned value can u5 min read
07Chapter 7: Earned value: the budgeted cost of work performedEarned value (EV) is the budgeted cost of the work you have actually completed at a status date. It answers one question: how much of the plan is done, expressed in the same money units as the budget?6 min read
08Chapter 8: Actual cost: what the work really costThis chapter assumes you know the basics of a work breakdown structure (WBS), control accounts, and the planned value (PV) and earned value (EV) definitions from the earlier chapters. You should also be comfortable with simple ratios and spreadsheet arithmetic.6 min read
09Chapter 9: Schedule variance and cost varianceThis chapter assumes you know what planned value (PV), earned value (EV), and actual cost (AC) mean, and that you can read a work package budget. If you need a refresher, review the three values first. Here you will combine them into two variances, and you will learn how to read them, where they mis6 min read
10Chapter 10: SPI and CPI: efficiency as a ratioThis chapter assumes you can already calculate planned value (PV), earned value (EV), and actual cost (AC) at a status date, and that you know the schedule variance (SV = EV − PV) and cost variance (CV = EV − AC). Here you turn those differences into ratios, read them correctly, and avoid the usual 5 min read
11Chapter 11: Reading the S-curve of PV, EV, and ACThis chapter assumes you can compute PV, EV, and AC at a status date, and that you know SV = EV − PV, CV = EV − AC, SPI = EV / PV, and CPI = EV / AC. Here you plot those values over time and read project status from the curves.6 min read
12Chapter 12: Interpreting status: the four common casesThis chapter assumes you can already compute PV, EV, and AC for a status date and derive SV, CV, SPI, and CPI from them. Here you learn to turn those numbers into a statement about the project and a decision about what to do next.5 min read
13Chapter 13: Forecasting the estimate at completionThis chapter assumes you can already compute BAC, PV, EV, AC, CPI, and SPI from the earlier chapters. It covers how to turn a status snapshot into a forecast of the final cost.5 min read
14Chapter 14: Estimate to complete and variance at completionThis chapter assumes you know the basic EVM quantities: BAC, PV, EV, AC, and the CPI and SPI ratios. It also assumes you have seen the EAC formulas from the previous chapter. Here you will use an EAC to answer two practical questions. How much money is still needed? How far will the project land fro5 min read
15Chapter 15: TCPI: the efficiency still requiredThis chapter assumes you can already compute EV, AC, CPI, and EAC, as covered in the earlier chapters. It adds one more index, the to-complete performance index (TCPI). Where CPI looks backward, TCPI looks forward.5 min read
16Chapter 16: Why SV and SPI mislead late in a project, and earned scheduleThis chapter assumes you can already compute SV and SPI, and that you can read a cumulative PV curve. It explains why the money-based schedule measures stop working near the end of a project, and how earned schedule fixes that.4 min read
17Chapter 17: Data quality and common pitfallsThis chapter assumes you can compute PV, EV, AC, the variances and the indices (SV, CV, SPI, CPI), and that you know the EAC formulas. It covers the ways good formulas produce bad answers. Every EVM measure is a ratio or difference of three numbers. If one of those numbers is wrong, the result looks6 min read