Sub topic 1
Why earned value: measuring progress in money terms
Prerequisites
This chapter assumes you already know the following:
- Basic project management vocabulary: scope, schedule, budget, and milestone.
- What a work breakdown structure (WBS) is, and how task-level estimates roll up into a total.
- How to work with percentages, ratios, and simple spreadsheet arithmetic.
You do not need to know any earned value formulas yet. This chapter explains the idea behind them. Later chapters build each value in detail.
The problem with spent money and elapsed time
Most status reports answer two questions: how much money have we spent, and how much time has passed? Both answers are easy to get. Neither one tells you how much was achieved.
Suppose a project has a budget of 100,000 and has spent 45,000. Is that good or bad? It depends on how much work is finished.
- If 60% of the work is done, the project is spending less than planned for the progress it has made.
- If 30% of the work is done, the project is spending too much for the progress it has made.
The spending figure is identical in both cases, and the conclusions are opposite. Comparing actual spending to the budget alone cannot separate "we are under budget" from "we are behind schedule and have not yet spent the money." Schedule status has the same weakness. Counting tasks started or days elapsed says nothing about how much of the work has been completed.
Earned value management (EVM) fixes this by adding a third measurement: the value of the work actually completed, expressed in the same currency as the budget and the costs.
The core idea: three values in one currency
EVM compares three numbers at a chosen status date. Each answers a different question.
| Value | Common name | Question it answers |
|---|---|---|
| Planned value (PV) | Budgeted cost of work scheduled | How much work did the plan say would be done by now? |
| Earned value (EV) | Budgeted cost of work performed | How much work has actually been done? |
| Actual cost (AC) | Actual cost of work performed | What did the work done so far actually cost? |
All three use money as the unit. That is the central trick. Work finished, work planned, and money spent are normally measured in different units (tasks, hours, dollars). Converting the work to its budgeted price puts everything on one scale, so the values can be subtracted and divided.
Two points are easy to miss:
- EV is priced at the budget, not at what was spent. If a task was budgeted at 10,000 and is finished, it has earned 10,000 whether it cost 7,000 or 14,000 to do. The difference shows up when you compare EV with AC.
- PV and EV measure the same thing against different references. PV is the budgeted value of the work that was scheduled. EV is the budgeted value of the work that was done. Because both use the same budget prices, comparing them isolates schedule progress from cost effects.
How the three values combine
Once you have PV, EV, and AC, two comparisons answer the questions most sponsors ask.
- Are we ahead or behind the plan? Compare EV with PV. If EV is lower, less work is done than scheduled.
- Are we over or under budget for the work done? Compare EV with AC. If AC is higher, the work done cost more than its budget.
Notice that cost is never compared with PV. Comparing spending with the planned value mixes two things: whether the project is slow and whether it is expensive. Comparing AC with EV removes the progress question, because both cover the same completed work.
The formal measures that come from these comparisons (variances, indices, and forecasts) are the subject of later chapters. At this point, remember the structure: EV sits in the middle, and the other two values are compared against it.
A small worked example
Consider a three-package project with a total budget of 100,000. This matches the example used throughout the tutorial.
| Work package | Budget | Fraction complete |
|---|---|---|
| Design | 20,000 | 100% |
| Build | 50,000 | 40% |
| Test | 30,000 | 0% |
The value earned is each package's budget multiplied by the fraction of it completed. The sum of all budgets is the total plan.
# Earned value for work packages: EV = budget * fraction complete
work_packages = [
{"name": "Design", "budget": 20000, "percent_complete": 1.00},
{"name": "Build", "budget": 50000, "percent_complete": 0.40},
{"name": "Test", "budget": 30000, "percent_complete": 0.00},
]
bac = sum(wp["budget"] for wp in work_packages)
ev = sum(wp["budget"] * wp["percent_complete"] for wp in work_packages)
print(bac) # 100000
print(ev) # 40000.0Here the budget at completion (BAC) is 100,000 and the earned value is 20,000 + 0.4 × 50,000 + 0 = 40,000. The project has earned 40% of its budget through completed work.
That 40,000 means little by itself. It becomes useful when you set it beside PV and AC. If the schedule called for 50,000 worth of work by this date, the project is behind. If the work cost 55,000 to produce, the project is over budget. The same EV supports either reading depending on the other two values, which is why EVM always uses all three.
Why the money scale matters
Using money as the common unit has practical consequences.
- Different kinds of work can be added together. Design hours, purchased equipment, and contractor invoices all become budgeted dollars, so a single project-level figure is possible.
- Weighting is automatic. A large work package contributes more to total progress than a small one. Counting finished tasks would treat a one-day task and a three-month task as equal.
- Progress and cost use one language. Executives can read a statement such as "we have earned 40,000 of a 100,000 plan" without translating between units.
What EVM needs before it works
EVM is not a calculation you can start on the last day. The three values depend on setup work done in advance:
- A time-phased budget, so PV can be read for any status date.
- Work defined at a level small enough to measure, so EV can be credited fairly.
- A way to collect actual costs against the same work, so AC matches what EV covers.
These requirements are the reason the next chapters cover the performance measurement baseline, work packages, and control accounts before returning to the three values. If the baseline is poor, every later number inherits the problem.
Common misreadings at this stage
- "EV is the money we have spent." It is not. Spending is AC. EV is the budgeted value of completed work.
- "Being under budget means we are doing well." Low spending may only mean little work is done. Compare AC with EV, not with the total budget.
- "EVM replaces the schedule." It does not. EVM summarises schedule performance in money terms and depends on a sound schedule to produce PV.
- "One number is enough." No single value gives a verdict. Status comes from reading PV, EV, and AC together.
Exercise
A project has a total budget of 200,000. At the status date, the plan called for 80,000 of work to be done. The team has finished work with a budgeted value of 60,000 and has spent 90,000. State PV, EV, and AC, then say in one sentence each what the comparison of EV with PV and of EV with AC suggests.
Show answer
PV is 80,000, EV is 60,000, and AC is 90,000. EV is below PV, so less work is done than was scheduled and the project is behind plan. EV is below AC, so the completed work cost 90,000 against a budget of 60,000, and the project is over budget for the work done.
Exercise
A manager says, "We have spent only 30% of the budget, so the project is in good shape." Why is this conclusion not supported, and which additional value would you need?
Show answer
Spending alone does not show how much work was completed. The project may have spent little because it has done little. You need earned value (the budgeted value of the work actually completed) to compare against actual cost, and planned value to judge whether progress matches the schedule.