Sub topic 11
Reading the S-curve of PV, EV, and AC
This chapter assumes you can compute PV, EV, and AC at a status date, and that you know SV = EV − PV, CV = EV − AC, SPI = EV / PV, and CPI = EV / AC. Here you plot those values over time and read project status from the curves.
Why plot cumulative values
A table of variances describes one status date. A chart of cumulative values shows how the project got there and where it is heading. A single snapshot can hide a trend. A project with CPI 0.90 that was 0.98 three months ago is in a very different position from one that has held 0.90 since the start.
Each of PV, EV, and AC is plotted as a running total against time. Because costs accumulate, none of the curves can fall. Each curve rises from zero, and the PV curve ends at BAC.
Why it is called an S-curve
Most projects start slowly with planning and mobilization, spend fastest in the middle when many work packages run in parallel, then taper during testing, handover, and closeout. Cumulative spend therefore rises gently, steepens, and flattens near the end. That gives the S shape.
The shape of the PV curve comes from your schedule, not from any rule. A project that front-loads a large purchase will have a steep early section. A project with one big delivery at the end will have a late jump. If your PV curve looks odd, check the baseline before blaming the project.
The three curves and what each shows
| Curve | Question it answers | Ends at |
|---|---|---|
| PV | How much budgeted work was planned by each date? | BAC, at the planned finish |
| EV | How much budgeted work was actually completed by each date? | BAC, when all work is done |
| AC | How much have we actually spent by each date? | The final actual cost |
Only PV extends across the whole planned duration. EV and AC stop at the status date, because the future has not happened yet. A forecast line, if you draw one, is a separate estimate and should be styled differently.
A worked data set
The data below covers a 10-month project with BAC of 100 (in thousands). The status date is the end of month 5. At that date PV is 40, EV is 30, and AC is 45, which matches the figures used elsewhere in this tutorial.
In the chart, the EV and AC lines are drawn flat after month 5 only because the chart needs a value in every column. Those flat segments are not data. In a real tool you would stop the lines at the status date.
Reading the vertical gaps
At any date, the gaps between curves are the variances you already know.
- The vertical distance from PV to EV is the schedule variance. EV below PV means behind schedule. EV above PV means ahead.
- The vertical distance from EV to AC is the cost variance. AC above EV means over budget. AC below EV means under budget.
At month 5, EV is 10 below PV (SV = −10) and AC is 15 above EV (CV = −15). The order of the curves from top to bottom is AC, PV, EV. That order is the picture of a project that is both late and over budget.
The following script computes the variances and indices for each month with actuals, so you can see how the gaps developed.
months = list(range(1, 11))
pv = [5, 10, 18, 28, 40, 52, 64, 76, 88, 100] # full baseline
ev = [4, 8, 14, 22, 30] # actuals to month 5
ac = [6, 12, 21, 32, 45]
def status(spi, cpi):
if spi < 1 and cpi < 1:
return "behind schedule, over budget"
if spi < 1:
return "behind schedule, under budget"
if cpi < 1:
return "ahead of schedule, over budget"
return "ahead of schedule, under budget"
print("Month PV EV AC SV CV SPI CPI Status")
for m, e, a in zip(months, ev, ac):
p = pv[m - 1]
spi, cpi = e / p, e / a
print(f"{m:>5} {p:>4} {e:>4} {a:>4} {e - p:>5} {e - a:>5} "
f"{spi:>5.2f} {cpi:>5.2f} {status(spi, cpi)}")The output shows CPI staying near 0.67 to 0.70 in every month. That steadiness is the useful finding. The cost problem started in month 1 and has not improved, so it is a persistent condition rather than a recent event. This matters when you choose a forecast method, which a later chapter covers.
Reading the horizontal gaps
The vertical gap is in money. You can also read the gap horizontally, in time. At month 5, EV is 30. The PV curve reached 28 at month 4 and 40 at month 5, so the project has earned only what it planned to have by a point a little after month 4. In time terms the project is roughly 0.8 months behind. Horizontal reading is the intuition behind earned schedule, which a later chapter develops properly.
Reading the slope
The steepness of each curve at a given point is its rate. A few patterns are worth recognizing.
- EV slope shallower than PV slope: the gap is widening. The project is falling further behind each period.
- EV slope steeper than PV slope: the project is catching up.
- AC slope steeper than EV slope: each unit of progress costs more than budgeted. If AC and EV run parallel, the overrun is not growing.
- A flat EV with a rising AC: money is being spent but nothing is being completed. Look for rework or work packages that sit at "90% done".
A single month can be noisy because of invoice timing or milestone-based earning, so look at three or more periods before declaring a trend.
Two conditions the curves can hide
The first is that EV can only move when work is credited. If you use a 0/100 rule or weighted milestones for a long work package, EV stays flat and then jumps. A flat EV in that case does not prove that no work happened. Check which earning rule applies before interpreting the slope.
The second is the convergence of SV. When the project finishes, EV reaches BAC, and PV also equals BAC at the planned end date. So SV returns to zero and SPI to 1.0 even for a project that finished months late. Schedule variance in money terms is therefore unreliable late in a project. The curves still show the lateness horizontally, because EV reaches BAC at a later date than PV did.
A reading routine
When you open a new S-curve, work through the same steps each time.
- Check that PV ends at BAC and that its shape matches the known schedule.
- Confirm the status date and that EV and AC stop there.
- Find the vertical order of the curves at the status date.
- Compare the slopes over the last three or more periods.
- Check whether the gaps are widening, steady, or closing.
- Note any step changes in EV and ask which milestones caused them.
Common reading mistakes
- Treating EV and AC as comparable to PV directly. PV and EV measure budgeted value, while AC measures real spend. Compare AC only with EV.
- Reading AC below PV as good news. Low spending with low EV means work is late, not that costs are controlled.
- Mixing periodic and cumulative values. The S-curve always uses cumulative totals.
- Ignoring baseline changes. If the baseline was rebaselined, the PV curve before and after the change is not comparable without noting it.
Exercise
At the end of month 4 in the data set above, PV is 28, EV is 22, and AC is 32. Which curve is highest, which is lowest, and what are SV, CV, SPI, and CPI?
Show answer
AC (32) is highest, PV (28) is in the middle, and EV (22) is lowest. SV = 22 − 28 = −6 and CV = 22 − 32 = −10. SPI = 22 / 28 ≈ 0.79 and CPI = 22 / 32 ≈ 0.69. The project is behind schedule and over budget.
Exercise
A project finishes three months after its planned date. EV equals BAC at the end, and PV equals BAC at the planned date. Why is SV not a good measure of lateness at the end, and what should you look at on the chart instead?
Show answer
At the end EV equals BAC, and PV also equals BAC from the planned finish onward, so SV = 0 and SPI = 1.0 even though the work finished late. Compare the dates at which the EV curve and the PV curve reach BAC. The three-month horizontal gap shows the delay.