Sub topic 9
Schedule Variance and Cost Variance
This chapter assumes you know what planned value (PV), earned value (EV), and actual cost (AC) mean, and that you can read a work package budget. If you need a refresher, review the three values first. Here you will combine them into two variances, and you will learn how to read them, where they mislead, and how to avoid common calculation mistakes.
What a variance tells you
A variance is a difference between two values measured in the same currency. In earned value management (EVM), there are two core variances. Each one compares EV, the budgeted worth of work actually done, against a different reference.
| Variance | Formula | Compares EV with | Question it answers |
|---|---|---|---|
| Schedule variance (SV) | SV = EV - PV | The work planned by the status date | How much budgeted work are we ahead of or behind plan? |
| Cost variance (CV) | CV = EV - AC | What the completed work actually cost | How much budget did we gain or lose on the work done? |
EV is always the first term. This is the convention that keeps the signs consistent:
- A positive variance is favorable (ahead of schedule or under budget).
- A negative variance is unfavorable (behind schedule or over budget).
- Zero means the project is exactly on plan for that measure.
Some older cost-accounting texts subtract in the other direction (AC - EV), which flips the sign. If you read a report from another source, check which convention it uses before you act on the sign.
Schedule variance
SV = EV - PV. PV is the budget for work that should be finished by the status date. EV is the budget for work that is finished. If you completed less budgeted work than planned, EV is smaller than PV and SV is negative.
Notice that SV is stated in money, not in days. An SV of -10,000 means you are behind by 10,000 of budgeted work. It does not mean you are 10 days late. To estimate time, you need the rate at which PV accrues around the status date, or you need the earned schedule method covered in a later chapter.
Cost variance
CV = EV - AC. EV is what the finished work was supposed to cost. AC is what it actually cost. If AC is larger, CV is negative and you have overspent for the progress you have made.
CV does not compare AC with PV. That comparison is a common mistake. Spending less than planned is not good news if the work is not done. Suppose you planned to spend 40,000 and have spent 30,000. That looks like an underspend. If only 20,000 worth of work is finished, the project is actually overspent by 10,000 for the work completed.
Worked example
Take a project with a budget at completion (BAC) of 100,000. At the status date:
- PV = 40,000
- EV = 30,000
- AC = 45,000
Then:
- SV = 30,000 - 40,000 = -10,000 (behind schedule)
- CV = 30,000 - 45,000 = -15,000 (over budget)
The following code computes both variances. It is the first part of the full metric function used elsewhere in this tutorial.
def variances(pv, ev, ac):
"""Return schedule variance and cost variance in the same currency."""
sv = ev - pv # schedule variance
cv = ev - ac # cost variance
return sv, cv
def describe(value, favorable, unfavorable):
"""Turn a variance into a plain-language statement."""
if value > 0:
return favorable
if value < 0:
return unfavorable
return "on plan"
sv, cv = variances(pv=40000, ev=30000, ac=45000)
print(f"SV: {sv:,.0f} -> {describe(sv, 'ahead of schedule', 'behind schedule')}")
print(f"CV: {cv:,.0f} -> {describe(cv, 'under budget', 'over budget')}")Running this prints:
SV: -10,000 -> behind schedule
CV: -15,000 -> over budgetHow the three values relate
The two variances share EV as their anchor. The diagram below shows which values feed each variance.
Because EV appears in both formulas, an error in how you measure progress changes both variances at once. If you overstate EV, SV and CV both look better than they should. This is why the rules for measuring work completed matter more than the arithmetic.
Variances as percentages
An absolute variance is hard to compare across projects or work packages. A 10,000 overrun is serious on a 50,000 project and minor on a 5,000,000 project. You can express variances as a percentage:
- SV% = SV / PV
- CV% = CV / EV
In the example, SV% = -10,000 / 40,000 = -25%, and CV% = -15,000 / 30,000 = -50%. Many organizations set thresholds on these percentages, for example a yellow flag at -10% and a red flag at -20%. The thresholds are a management choice. EVM itself does not define them, so use the ones your project's governance sets.
Divide by the right base. CV% uses EV in the denominator, not PV, because CV is measured against completed work.
Where you measure: control accounts and cumulative values
You can calculate variances at any level of the work breakdown structure: a work package, a control account, or the whole project. Two rules apply.
- Use the same status date for PV, EV, and AC. Mixing a PV from the end of the month with an AC from the middle of the month produces a variance with no meaning.
- Sum the values first or sum the variances. Both give the same answer, because subtraction distributes over addition. But do not sum the percentages. Recompute the percentage from the summed values.
You can also report variances for a period (this month) or cumulatively (since the start). Cumulative figures are the standard basis for forecasting, because they are less affected by one noisy month. Period figures help you see whether a trend is improving.
Edge cases and gotchas
- Schedule variance converges to zero. When a project finishes, all planned work is done, so EV equals PV (both equal BAC) and SV is 0, even if the project finished months late. SV therefore says little about lateness near the end of a project. A later chapter covers earned schedule, which fixes this.
- Work on the wrong tasks. SV counts only budgeted value earned. A team that completes 40,000 of low-priority work while the critical path stalls can show SV = 0. SV does not tell you whether the right work is being done. Check the critical path separately.
- Incomplete AC. If invoices, contractor charges, or overtime are not yet booked, AC is too low and CV looks better than reality. Confirm that AC includes accruals for work already performed.
- Early payments. Paying a supplier up front raises AC without any work being done, which makes CV look worse. Record cost when the work is performed, or the equivalent accrual basis your organization uses.
- Optimistic EV. Percent-complete estimates that drift upward ("90% done" for weeks) inflate EV and hide both variances. Prefer objective rules such as weighted milestones.
- Zero PV. SV% divides by PV, so it is undefined before any work is scheduled. Guard against division by zero in your code.
A reusable function with guards
This function adds percentages and handles the zero-denominator cases.
def variance_report(pv, ev, ac):
"""Variances and percentages for one status date."""
sv = ev - pv
cv = ev - ac
sv_pct = sv / pv if pv else None # undefined when nothing was scheduled
cv_pct = cv / ev if ev else None # undefined when nothing was earned
return {"SV": sv, "CV": cv, "SV%": sv_pct, "CV%": cv_pct}
def fmt(x):
return "n/a" if x is None else f"{x:,.2f}"
for label, pv, ev, ac in [
("Behind and over", 40000, 30000, 45000),
("Ahead and under", 40000, 48000, 42000),
("Nothing earned yet", 10000, 0, 2000),
]:
r = variance_report(pv, ev, ac)
print(label, {k: fmt(v) for k, v in r.items()})The third case shows why the guard matters. With EV = 0, CV is -2,000, but CV% cannot be computed, so the report shows "n/a" instead of failing.
Common errors checklist
- Using the wrong sign convention, so favorable and unfavorable are swapped.
- Subtracting AC from PV instead of from EV.
- Mixing status dates across PV, EV, and AC.
- Reading SV as a number of days.
- Trusting SV near project end without checking the actual finish date.
- Averaging percentages across work packages instead of recomputing from totals.
Exercise
At a status date, a project has PV = 80,000, EV = 72,000, and AC = 66,000. Calculate SV, CV, SV%, and CV%, and describe the project's status. Then explain why a manager who only compared AC (66,000) with PV (80,000) would reach a misleading conclusion.
Show answer
SV = 72,000 - 80,000 = -8,000. CV = 72,000 - 66,000 = +6,000. SV% = -8,000 / 80,000 = -10%. CV% = 6,000 / 72,000 = about +8.3%. The project is behind schedule (it finished 8,000 less budgeted work than planned) but under budget for the work it did complete (it spent 6,000 less than that work was budgeted to cost). A manager comparing AC with PV would see 14,000 of apparent underspend and might conclude the project is healthy. That figure mixes two effects: some of the underspend is simply work that has not been done yet. Only CV, which compares AC with EV, isolates cost efficiency.
Exercise
A project is complete: EV = BAC = 200,000 and PV (cumulative) = 200,000. The team finished four months after the planned date. What is SV, and what does the result tell you about SV as a late-project indicator?
Show answer
SV = 200,000 - 200,000 = 0. SV reports no schedule problem even though the project finished four months late. Once all planned value has been earned, SV always returns to zero, so it stops reflecting lateness. Use the actual dates or the earned schedule method to measure delay late in a project.