SPI and CPI: efficiency as a ratio
This chapter assumes you can already calculate planned value (PV), earned value (EV), and actual cost (AC) at a status date, and that you know the schedule variance (SV = EV − PV) and cost variance (CV = EV − AC). Here you turn those differences into ratios, read them correctly, and avoid the usual mistakes.
Why a ratio when you already have variances
A variance is an amount of money. A cost variance of −15,000 is a small problem on a 5,000,000 project and a disaster on a 100,000 project. The variance does not say which.
A ratio removes the scale. It answers a different question: for each unit of something, how much did we get back? Two ratios cover the two dimensions of performance.
- Schedule performance index (SPI) is EV divided by PV. It shows how much planned work was completed per unit of work that was scheduled.
- Cost performance index (CPI) is EV divided by AC. It shows how much budgeted value was earned per unit of money actually spent.
SPI = EV / PV
CPI = EV / ACEV is always the numerator. Both indices ask how much value was earned compared with some other measure. A frequent error is to put EV in the denominator, which flips every interpretation.
Reading the numbers
The break-even point for both indices is 1.0.
| Index value | Schedule meaning (SPI) | Cost meaning (CPI) |
|---|---|---|
| Greater than 1.0 | Ahead of schedule | Under budget for the work done |
| Equal to 1.0 | On schedule | On budget |
| Less than 1.0 | Behind schedule | Over budget for the work done |
You can also read an index as a percentage. A CPI of 0.67 means that each currency unit spent has earned about 0.67 units of budgeted value. An SPI of 0.75 means the team has completed 75% of the work that the baseline said should be finished by now.
The variances and indices always agree on sign. SV is negative exactly when SPI is below 1.0, and CV is negative exactly when CPI is below 1.0. If your numbers disagree, one of them has a calculation error.
Worked example
Use the status data from the earlier chapters: BAC 100,000, PV 40,000, EV 30,000, AC 45,000.
- SPI = 30,000 / 40,000 = 0.75
- CPI = 30,000 / 45,000 ≈ 0.67
The project has done three quarters of the work it planned to have finished, and it is paying about 1.50 for every 1.00 of value earned.
def indices(pv, ev, ac):
"""Return (SPI, CPI) for one status date. PV and AC must be positive."""
if pv <= 0 or ac <= 0:
raise ValueError("PV and AC must be positive to compute SPI and CPI")
return ev / pv, ev / ac
spi, cpi = indices(pv=40000, ev=30000, ac=45000)
print(f"SPI = {spi:.2f}") # SPI = 0.75
print(f"CPI = {cpi:.2f}") # CPI = 0.67The guard matters in practice. PV is zero before the first scheduled work starts, and AC is zero before any cost is booked. Report the index as "not yet available" rather than as zero or infinity.
Cumulative and period indices
Most reports show the cumulative index, calculated from the start of the project to the status date. A period index uses only the values earned and spent in the latest reporting period. You get period values by subtracting the previous cumulative value from the current one.
Cumulative values are stable, but they average away recent changes. Period values show the current trend but jump around. A good report shows both.
cumulative = [ # (PV, EV, AC) at the end of months 1, 2, 3
(10000, 8000, 9000),
(25000, 20000, 26000),
(40000, 30000, 45000),
]
prev = (0, 0, 0)
for month, (pv, ev, ac) in enumerate(cumulative, start=1):
p_pv, p_ev, p_ac = pv - prev[0], ev - prev[1], ac - prev[2]
print(
f"Month {month}: cumulative SPI {ev / pv:.2f}, CPI {ev / ac:.2f} | "
f"period SPI {p_ev / p_pv:.2f}, CPI {p_ev / p_ac:.2f}"
)
prev = (pv, ev, ac)The output is:
Month 1: cumulative SPI 0.80, CPI 0.89 | period SPI 0.80, CPI 0.89
Month 2: cumulative SPI 0.80, CPI 0.77 | period SPI 0.80, CPI 0.71
Month 3: cumulative SPI 0.75, CPI 0.67 | period SPI 0.67, CPI 0.53The cumulative CPI falls from 0.89 to 0.67, which looks like a steady slide. The period CPI shows that month 3 was the worst month so far, at 0.53. The cumulative figure hides how quickly the trend is worsening.
Thresholds and tolerances
Organizations rarely react to a value of 0.99. They set a control threshold and act when an index leaves it. A common band is 0.90 to 1.10, and some organizations use a narrower band for cost. Your project's performance baseline or governance plan should state the band. The idea is the same everywhere: small deviations are noise, and larger ones need a recovery plan or a documented decision.
Consider both directions. A CPI of 1.25 looks good, but it can also mean that costs are late in being recorded, that the estimate was padded, or that work is being reported as complete before it really is.
Why CPI is useful for forecasting
Research on completed projects, often cited in EVM guidance, finds that cumulative CPI tends to stay within a narrow range once a project is about 20% complete. It rarely improves much after that point. This is why many forecast formulas use CPI to project the final cost, for example EAC = BAC / CPI. Later chapters use the index this way. SPI does not have the same property, as the last section explains.
Common errors
- Inverting the ratio. Dividing PV by EV or AC by EV gives a number that gets larger as performance gets worse. Always put EV on top.
- Treating SPI as a time measure. SPI is measured in money. It does not say that the project is 25% late in calendar terms.
- Using it too early. In the first few percent of a project, small absolute differences give extreme ratios. Interpret early indices carefully.
- Averaging indices. Do not average work package CPIs to get a project CPI. Add EV and AC across packages first, then divide.
- Ignoring weights. A CPI of 0.5 on a small package matters less than a CPI of 0.9 on a package that is half of the budget.
- Comparing indices across projects. The same index can reflect different baselines, estimating cultures, and progress-measurement rules.
Aggregating correctly
Suppose two work packages report the following at the status date.
| Package | PV | EV | AC | CPI |
|---|---|---|---|---|
| Alpha | 10,000 | 9,000 | 9,000 | 1.00 |
| Beta | 50,000 | 25,000 | 40,000 | 0.63 |
The project CPI is (9,000 + 25,000) / (9,000 + 40,000) = 34,000 / 49,000 ≈ 0.69. The simple average of 1.00 and 0.63 is 0.81. That average hides that the large package, Beta, is where the cost problem lies.
Exercise
At a status date, PV is 80,000, EV is 72,000, and AC is 60,000. Calculate SPI and CPI, then describe the project in one sentence.
Show answer
SPI = 72,000 / 80,000 = 0.90 and CPI = 72,000 / 60,000 = 1.20. The project is slightly behind schedule (it has completed 90% of the planned work) but is under budget for the work done (each currency unit spent has earned 1.20 of budgeted value).
Exercise
Package A has EV 20,000 and AC 10,000. Package B has EV 30,000 and AC 60,000. A colleague says the project CPI is the average of the two package CPIs. What is the correct project CPI, and why does the average give a different answer?
Show answer
Package A has CPI 2.00 and package B has CPI 0.50, so the average is 1.25. The correct project CPI is (20,000 + 30,000) / (10,000 + 60,000) = 50,000 / 70,000 ≈ 0.71. The average treats both packages equally, but package B has much more cost. Summing EV and AC first weights each package by its actual spending.