Estimate to Complete and Variance at Completion
This chapter assumes you know the basic EVM quantities: BAC, PV, EV, AC, and the CPI and SPI ratios. It also assumes you have seen the EAC formulas from the previous chapter. Here you will use an EAC to answer two practical questions. How much money is still needed? How far will the project land from its budget?
From a forecast total to a forecast remainder
EAC is the forecast of the total cost at completion. Two further numbers come from it, and each answers a question a sponsor will ask.
- Estimate to complete (ETC) is the forecast cost of the work that remains. It answers "how much more money do we need from today?"
- Variance at completion (VAC) is the difference between the original budget and the forecast total. It answers "how far over or under budget will we finish?"
The relationships are:
- ETC = EAC − AC
- VAC = BAC − EAC
Both follow from a simple picture. EAC is what you have already spent (AC) plus what you expect to spend from here on (ETC). The sign convention matches the other variances in EVM: a negative VAC is bad news, because the forecast exceeds the budget.
Which ETC formula to use
You do not pick ETC in isolation. You pick an assumption about how the remaining work will perform, and the ETC follows from it. The assumption determines the EAC, and ETC is EAC − AC.
| Assumption | ETC | EAC |
|---|---|---|
| Past cost efficiency continues (typical variance) | (BAC − EV) / CPI | AC + (BAC − EV) / CPI = BAC / CPI |
| Past overrun was a one-off (atypical variance) | BAC − EV | AC + (BAC − EV) |
| Cost and schedule efficiency both drive the remaining cost | (BAC − EV) / (CPI × SPI) | AC + (BAC − EV) / (CPI × SPI) |
| The original plan is no longer valid (bottom-up) | A fresh estimate of the remaining work | AC + new ETC |
The term BAC − EV is the budgeted value of the work not yet done. Dividing it by CPI scales that remaining budget by how efficiently you have been spending. Dividing by CPI × SPI is a pessimistic variant, used when a late project must also pay for recovery effort such as overtime or extra staff.
The simplified form BAC / CPI only equals AC + (BAC − EV) / CPI because AC = EV / CPI. That identity holds at any status date, so the two expressions always agree.
A worked example
Use the same status data as the rest of this tutorial: BAC = 100,000, PV = 40,000, EV = 30,000, AC = 45,000. That gives CPI = 30,000 / 45,000 ≈ 0.67 and SPI = 30,000 / 40,000 = 0.75.
The project has completed 30% of its budgeted work (EV / BAC) and has spent 45% of its budget (AC / BAC). The remaining budgeted work is 100,000 − 30,000 = 70,000.
- Typical. ETC = 70,000 / 0.667 = 105,000. EAC = 45,000 + 105,000 = 150,000. VAC = 100,000 − 150,000 = −50,000.
- Atypical. ETC = 70,000. EAC = 45,000 + 70,000 = 115,000. VAC = −15,000.
- CPI × SPI. CPI × SPI = 0.667 × 0.75 = 0.5. ETC = 70,000 / 0.5 = 140,000. EAC = 185,000. VAC = −85,000.
The same data gives forecasts from 115,000 to 185,000. The data alone does not decide between them. Your judgment about the remaining work does.
def forecast_scenarios(bac, pv, ev, ac, bottom_up_etc=None):
"""Return ETC, EAC and VAC for each forecasting assumption."""
if pv <= 0 or ac <= 0 or ev <= 0:
raise ValueError("PV, EV and AC must be positive")
cpi = ev / ac
spi = ev / pv
remaining = bac - ev # budgeted value of the work not yet done
etcs = {
"typical (CPI continues)": remaining / cpi,
"atypical (one-off overrun)": remaining,
"CPI x SPI": remaining / (cpi * spi),
}
if bottom_up_etc is not None:
etcs["bottom-up re-estimate"] = bottom_up_etc
results = {}
for name, etc in etcs.items():
eac = ac + etc
vac = bac - eac
results[name] = {"ETC": etc, "EAC": eac, "VAC": vac}
return results
scenarios = forecast_scenarios(bac=100000, pv=40000, ev=30000, ac=45000,
bottom_up_etc=90000)
for name, r in scenarios.items():
print(f"{name:28s} ETC {r['ETC']:>9,.0f} EAC {r['EAC']:>9,.0f} VAC {r['VAC']:>9,.0f}")Running it prints:
typical (CPI continues) ETC 105,000 EAC 150,000 VAC -50,000
atypical (one-off overrun) ETC 70,000 EAC 115,000 VAC -15,000
CPI x SPI ETC 140,000 EAC 185,000 VAC -85,000
bottom-up re-estimate ETC 90,000 EAC 135,000 VAC -35,000The bottom-up row uses an assumed figure of 90,000 from the team's own estimate of the remaining tasks. That figure is an input to the code, not something EVM computes.
Reading VAC
VAC is easiest to interpret as a percentage of BAC. A VAC of −50,000 on a 100,000 budget means a 50% overrun. A VAC of −15,000 means 15%. Many organizations set a threshold, for example 10%, beyond which a forecast must be escalated or a baseline change requested.
A few interpretation rules help:
- A negative VAC forecasts an overrun. A positive VAC forecasts an underrun. A VAC of zero means you expect to finish on budget.
- VAC is only as good as the EAC behind it. Report which EAC method you used next to the VAC figure.
- VAC measures cost only. A project can have a VAC of zero and still finish late.
Edge cases and common errors
Early in the project. When EV is very small, CPI is volatile. A single invoice can swing the typical-variance EAC by a large amount. Treat early forecasts as ranges, and prefer a bottom-up estimate for the near-term work.
EV of zero. If no work has been earned, CPI is 0 and the typical formula divides by zero. The code above rejects that case. In practice, use a bottom-up estimate until some work is earned.
ETC that ignores contingency or known risks. The formulas extrapolate from the past. A known future cost, such as a vendor price increase or a risk you expect to occur, is not captured by CPI. Add it to the ETC explicitly, or use a bottom-up estimate.
Mixing up AC and EAC. AC is money already spent. EAC is the forecast total. Subtracting EAC from BAC gives VAC, but subtracting AC from BAC gives the unspent budget, which is a different number. The unspent budget is 55,000 here, but the forecast says you need 105,000 more.
Reusing an old CPI. If the team fixed the cause of an overrun months ago, a cumulative CPI still carries that history. Some teams use a recent-period CPI, such as the last three periods, for the typical method. State clearly which CPI you used.
Exercise
A project has BAC = 200,000, PV = 90,000, EV = 80,000 and AC = 100,000. The team finds that the overrun came from a one-time equipment failure that has been fixed. (a) Which EAC method fits, and what are ETC, EAC and VAC? (b) What would ETC and VAC be if the overrun were expected to continue at the current CPI?
Show answer
(a) Use the atypical method. The remaining budgeted work is BAC − EV = 200,000 − 80,000 = 120,000, so ETC = 120,000. EAC = AC + ETC = 100,000 + 120,000 = 220,000. VAC = BAC − EAC = 200,000 − 220,000 = −20,000, a 10% overrun. (b) CPI = 80,000 / 100,000 = 0.8. ETC = 120,000 / 0.8 = 150,000. EAC = 100,000 + 150,000 = 250,000, which also equals BAC / CPI. VAC = 200,000 − 250,000 = −50,000, a 25% overrun.