Why SV and SPI Mislead Late in a Project, and Earned Schedule
This chapter assumes you can already compute SV and SPI, and that you can read a cumulative PV curve. It explains why the money-based schedule measures stop working near the end of a project, and how earned schedule fixes that.
The problem: schedule measured in dollars
SV and SPI answer a schedule question with a cost unit:
- SV = EV − PV
- SPI = EV / PV
Both compare two currency amounts at the status date. That works while the PV curve is steep, because a shortfall in EV corresponds roughly to time lost. Near the end of the project the logic breaks down.
PV stops growing at the budget at completion (BAC). EV keeps climbing until the work is finished, and then it also equals BAC. At that moment SV is 0 and SPI is 1.0, whether the project finished on time or a year late. A late project therefore appears to recover its schedule as it approaches completion.
Three effects combine to cause this:
- PV is capped at BAC. After the planned finish date, PV stays flat, so any EV gain shrinks the gap even if the delay is unchanged.
- The unit is money, not time. A 5,000 gap means little if the plan earns 1,000 per month in one phase and 20,000 per month in another.
- Completion forces convergence. When all work is done, EV = BAC = PV, so SV must be 0.
Seeing the distortion
Take a 10-month project with a BAC of 100,000 and this cumulative PV at the end of each month:
| Month | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Cumulative PV | 0 | 5,000 | 10,000 | 20,000 | 35,000 | 50,000 | 65,000 | 80,000 | 90,000 | 97,000 | 100,000 |
The project is slow. At month 11 only 95,000 of work is earned. It finishes at month 12, two months late. The classic measures look like this:
| Status date | EV | PV | SV | SPI |
|---|---|---|---|---|
| Month 6 | 40,000 | 65,000 | −25,000 | 0.62 |
| Month 11 | 95,000 | 100,000 | −5,000 | 0.95 |
| Month 12 | 100,000 | 100,000 | 0 | 1.00 |
SPI rises from 0.62 to 1.00, which suggests the team caught up. In fact the project is two months late and stays two months late.
Earned schedule: moving the comparison onto the time axis
Earned schedule (ES) asks a different question. Instead of "how much value is missing at this date?", it asks "at what point in the baseline did the plan call for the amount of value we have now earned?"
The calculation has three steps:
- Find C, the last baseline period whose cumulative PV is less than or equal to the current EV.
- Interpolate within the next period: the fraction is (EV − PV at C) / (PV at C+1 − PV at C).
- ES = C + fraction.
The time-based measures follow from ES and actual time (AT), the elapsed time at the status date:
- SV(t) = ES − AT
- SPI(t) = ES / AT
- Forecast duration, IEAC(t) = planned duration / SPI(t)
Because ES is a time on the baseline, it keeps its meaning after PV is capped. At EV = 100,000, ES is 10 months. If AT is 12, SV(t) is −2 months, and it stays at −2 until you change the plan or recover time.
Implementing it
The following program computes both the classic and the time-based measures for the project above. It uses only the standard library.
cum_pv = [0, 5000, 10000, 20000, 35000, 50000,
65000, 80000, 90000, 97000, 100000] # index = month
planned_duration = len(cum_pv) - 1
def earned_schedule(cum_pv, ev):
"""Return ES in periods, interpolating inside the period that EV falls in."""
c = max(i for i, pv in enumerate(cum_pv) if pv <= ev)
if c == len(cum_pv) - 1:
return float(c)
return c + (ev - cum_pv[c]) / (cum_pv[c + 1] - cum_pv[c])
def report(at, ev):
pv = cum_pv[min(at, planned_duration)] # PV is capped at BAC
es = earned_schedule(cum_pv, ev)
spi_t = es / at
return {
"SV($)": ev - pv,
"SPI($)": ev / pv,
"ES": es,
"SV(t)": es - at,
"SPI(t)": spi_t,
"IEAC(t)": planned_duration / spi_t,
}
for at, ev in [(6, 40000), (11, 95000), (12, 100000)]:
print(f"Month {at}")
for name, value in report(at, ev).items():
print(f" {name}: {value:,.2f}")The key results are:
| Month | SPI (money) | ES | SV(t) | SPI(t) | Forecast duration |
|---|---|---|---|---|---|
| 6 | 0.62 | 4.33 | −1.67 | 0.72 | 13.8 months |
| 11 | 0.95 | 8.71 | −2.29 | 0.79 | 12.6 months |
| 12 | 1.00 | 10.00 | −2.00 | 0.83 | 12.0 months |
The month 11 row shows the difference. The money-based SPI says 0.95, which looks nearly on track. SPI(t) says 0.79, and the duration forecast of 12.6 months is close to the real finish at month 12. At month 12 the forecast equals the actual duration, as it should.
Gotchas and edge cases
- Flat sections of the baseline. If PV is flat for several periods, for example during a planned pause, the interpolation denominator could be zero. The code above takes the last period with PV ≤ EV, so the next period always has a higher PV and the division is safe.
- Period granularity. ES is interpolated linearly inside a period, which assumes PV accrues evenly within it. Use finer periods, such as weeks, if the plan has sharp steps.
- ES is not a critical path measure. It is computed from aggregate cost-weighted EV. Work done off the critical path still raises EV and ES, so a project can show a healthy SPI(t) while the critical path slips. Check the schedule network as well.
- Rebaselining. If the baseline changes, recompute ES against the new cumulative PV. Mixing old EV with a new baseline produces nonsense.
- Cost-weighted bias. Expensive activities dominate both PV and EV. Cheap but critical activities can be late without moving ES much.
- AT of zero. SPI(t) divides by AT, so compute it only after the first status period.
When to use which measure
| Situation | Better measure |
|---|---|
| Early or mid project, steep PV curve | SV and SPI are usually adequate |
| Past 70 to 80 percent of the plan | SV(t) and SPI(t) |
| Project past its planned finish date | SV(t) and SPI(t); the money-based measures are meaningless |
| Need a duration forecast | IEAC(t), cross-checked against the schedule network |
| Need to know if critical work is late | Schedule network analysis; EVM and ES cannot show this |
Exercise
A 10-month project uses the cumulative PV table in this chapter. At month 9 the team has earned 60,000. Compute ES, SV(t), and SPI(t). Compare SPI(t) with the money-based SPI, using PV at month 9 of 97,000.
Show answer
The last month with PV ≤ 60,000 is month 5 (PV 50,000); month 6 has PV 65,000. ES = 5 + (60,000 − 50,000) / (65,000 − 50,000) = 5.67 months. SV(t) = 5.67 − 9 = −3.33 months. SPI(t) = 5.67 / 9 = 0.63. The money-based SPI is 60,000 / 97,000 = 0.62, so here the two agree. They agree because the project is still mid-curve. The disagreement appears only when PV flattens near BAC.
Exercise
A project planned for 10 months finishes all its work at month 14. What are the money-based SV and SPI at month 14, and what are SV(t) and SPI(t)?
Show answer
At month 14, PV is capped at BAC and EV equals BAC, so SV = 0 and SPI = 1.0. ES = 10 months because EV equals the final cumulative PV. SV(t) = 10 − 14 = −4 months and SPI(t) = 10 / 14 = 0.71. Only the time-based measures show the four-month delay.