Sub topic 2
The performance measurement baseline
What this chapter assumes
You should know basic project management vocabulary (scope, schedule, budget, milestone) and what a work breakdown structure (WBS) is. You should also be comfortable with percentages and simple spreadsheet arithmetic. This chapter does not compute variances or indices yet. It builds the reference plan that those later calculations depend on.
Why earned value needs a baseline
Earned value management compares what happened with what you planned. A comparison only works if the plan stays fixed while the project moves. The performance measurement baseline (PMB) is that fixed plan. It is the approved, time-phased budget against which you measure schedule and cost performance.
Without a baseline, "we are behind" has no meaning. Behind what? If the plan changes every week, a late task simply gets a new date and the project always looks on track. The baseline stops this by holding the original agreement steady until someone formally changes it.
What the baseline contains
The PMB combines three things that are already part of a project plan:
- Scope baseline. The approved scope statement, the WBS, and the WBS dictionary. This defines what work exists.
- Schedule baseline. The approved start and finish dates for that work, including its sequence and duration.
- Cost baseline. The approved budget for each piece of work, spread across the time periods in which you plan to spend it.
The word "time-phased" matters. A budget of 100,000 is not enough. The baseline says how much of it you expect to have earned in each week or month. That spread is what lets you compute planned value at any status date.
Many organizations also hold a management reserve. This is money set aside for unknown risks. It is part of the project budget but is not part of the PMB, because it is not assigned to any work. When a risk occurs, management releases some reserve into the baseline through a formal change.
| Item | In the PMB? | Reason |
|---|---|---|
| Work package budgets | Yes | Assigned to defined work |
| Contingency for identified risks | Yes (typically) | Tied to known, planned responses |
| Management reserve | No | Not assigned to any work yet |
| Profit or fee (contract projects) | No | Not part of the cost of the work |
Organizations differ on contingency. Some place it in control accounts and some hold it separately, so check your own standard.
How the baseline is built
You build the baseline from the bottom up and then add it up.
- Decompose the scope. Break the project into a WBS until you reach work packages, which are small enough to estimate, assign, and track.
- Group work packages into control accounts. A control account is a management point where scope, budget, schedule, and responsibility meet. The next chapter covers these in detail.
- Estimate the cost of each work package. This gives each package its budget.
- Schedule each work package. Place it on the timeline with a start and finish.
- Spread each budget over its duration. A package budgeted at 20,000 over four months might get 5,000 per month.
- Sum by period. Add every package's spread for each period to get the project's planned spend per period.
- Accumulate the totals. Add each period to the running total.
The final running total equals the budget at completion (BAC). The running totals by period form the curve that later chapters call the S-curve.
A worked example
Consider a three-package project with a four-month schedule. Each budget is spread evenly over the months in which the work is scheduled.
| Work package | Budget | Month 1 | Month 2 | Month 3 | Month 4 |
|---|---|---|---|---|---|
| Design | 20,000 | 10,000 | 10,000 | 0 | 0 |
| Build | 50,000 | 0 | 25,000 | 25,000 | 0 |
| Test | 30,000 | 0 | 0 | 10,000 | 20,000 |
| Period total | 100,000 | 10,000 | 35,000 | 35,000 | 20,000 |
| Cumulative | 10,000 | 45,000 | 80,000 | 100,000 |
The cumulative row is the baseline. At the end of month 2, the plan says 45,000 of work should be done. That figure will become planned value in a later chapter.
The following code builds the same baseline from the package data.
# Build a time-phased baseline from work packages
# Each package: total budget spread evenly across its scheduled months
packages = [
{"name": "Design", "budget": 20000, "months": [1, 2]},
{"name": "Build", "budget": 50000, "months": [2, 3]},
{"name": "Test", "budget": 30000, "months": [3, 4]},
]
# Test is not spread evenly in the table above, so override it explicitly
custom_spread = {"Test": {3: 10000, 4: 20000}}
horizon = 4
period_totals = {m: 0.0 for m in range(1, horizon + 1)}
for wp in packages:
if wp["name"] in custom_spread:
spread = custom_spread[wp["name"]]
else:
share = wp["budget"] / len(wp["months"])
spread = {m: share for m in wp["months"]}
assert abs(sum(spread.values()) - wp["budget"]) < 1e-9, wp["name"]
for month, amount in spread.items():
period_totals[month] += amount
cumulative = 0.0
for month in range(1, horizon + 1):
cumulative += period_totals[month]
print(f"Month {month}: period {period_totals[month]:,.0f}, cumulative {cumulative:,.0f}")
print(f"BAC: {cumulative:,.0f}")The assertion is worth keeping in real tools. If a package's spread does not add up to its budget, the baseline silently drifts away from the BAC, and every later metric inherits the error.
The baseline as a diagram
The baseline is assembled from three approved inputs and then locked behind change control.
Keeping the baseline stable
The baseline is only useful while it is stable, so you change it deliberately and only for approved reasons.
Changes that normally justify a rebaseline:
- An approved scope change, such as a customer adding a feature.
- A release of management reserve after a risk occurs.
- A contract modification that changes budget or delivery dates.
Changes that do not justify one:
- A task running late.
- A cost overrun on finished work.
- A wish to make the status report look better.
Each of the second group is the very thing earned value is built to reveal. If you rewrite the baseline to absorb it, the variance disappears from the report, but the problem remains in the project.
Common errors
- Budgets that do not sum to the BAC. Rounding, missed packages, or double-counted work produce a baseline that disagrees with the approved budget. Reconcile the period totals to the BAC every time you build or change the baseline.
- Schedule and budget out of sync. If a task moves on the schedule but its budget stays in the old months, planned value is wrong. Update both together.
- Packages too large. A work package that runs six months with one spread gives a coarse baseline. Progress is hard to measure, and planned value is a rough guess. Smaller packages produce a more useful baseline.
- Including management reserve in the PMB. This inflates the BAC and makes every efficiency measure look better or worse than it should.
- Spreading budget in a way that does not match the work. An even spread is a default. If a package's effort is front-loaded, spread it that way, because planned value follows the spread.
What the baseline gives the next chapters
Once the PMB exists, three values become defined. Each is read from the baseline or measured against it:
- Planned value (PV) is the cumulative baseline up to the status date.
- Budget at completion (BAC) is the final cumulative total.
- Earned value (EV) and actual cost (AC) are measured during execution and compared with PV.
The next chapter looks at how work packages and control accounts attach these numbers to named owners.
Exercise
A project has two work packages. Package A has a budget of 12,000 and is scheduled across months 1 to 3, with an even spread. Package B has a budget of 18,000 and is scheduled in months 3 and 4, with 6,000 in month 3 and 12,000 in month 4. What is the cumulative baseline at the end of month 3, and what is the BAC?
Show answer
Package A contributes 4,000 per month for months 1 to 3. Package B contributes 6,000 in month 3. Cumulative at the end of month 1 is 4,000, at the end of month 2 it is 8,000, and at the end of month 3 it is 8,000 + 4,000 + 6,000 = 18,000. Month 4 adds 12,000, so the BAC is 30,000, which equals 12,000 + 18,000.
Exercise
Midway through a project, a task on the critical path slips by three weeks, and the project manager proposes moving the baseline dates so the project shows no schedule variance. Should this be approved as a rebaseline? Give your reason.
Show answer
No. A slipped task is a performance problem, not an approved change to scope, contract, or budget. Moving the baseline would erase the schedule variance that earned value is meant to report. The slip should stay visible against the original baseline, and the team should respond with recovery actions or a formally approved change if one is justified.