Sub topic 7
Earned value: the budgeted cost of work performed
Earned value (EV) is the budgeted cost of the work you have actually completed at a status date. It answers one question: how much of the plan is done, expressed in the same money units as the budget?
This chapter assumes you know what a work breakdown structure (WBS), a work package, and a budget at completion (BAC) are. It also assumes you have read the chapters on planned value and on rules for measuring work completed. The chapter builds EV from those pieces, shows how to compute it, and covers the errors that most often distort it.
What EV measures
EV is the value of the work done, priced at the original budget. It does not depend on what the work cost or on when it was scheduled. Two other measures cover those questions:
| Measure | Question it answers | Priced at |
|---|---|---|
| Planned value (PV) | How much work was scheduled to be done by now? | Budget |
| Earned value (EV) | How much work is actually done? | Budget |
| Actual cost (AC) | What did the work done cost? | Real spend |
PV and EV use the same prices, so comparing them isolates schedule performance. EV and AC use the same work but different prices, so comparing them isolates cost performance. This is why EV is the pivot of the method. Both the schedule and the cost comparison need it.
The basic formula
For each work package, the formula is:
EV = budget of the work package × fraction of the work package completed
For the whole project, EV is the sum over all work packages. A package that is 100% complete earns its full budget. A package that has not started earns nothing. A package in between earns a proportional share, according to the measurement rule you chose for it.
# Earned value for work packages: EV = budget * fraction complete
work_packages = [
{"name": "Design", "budget": 20000, "percent_complete": 1.00},
{"name": "Build", "budget": 50000, "percent_complete": 0.40},
{"name": "Test", "budget": 30000, "percent_complete": 0.00},
]
bac = sum(wp["budget"] for wp in work_packages)
ev = sum(wp["budget"] * wp["percent_complete"] for wp in work_packages)
print(bac) # 100000
print(ev) # 40000.0Design earns 20,000 because it is finished. Build earns 0.40 × 50,000 = 20,000. Test earns nothing. The total is 40,000 against a BAC of 100,000, so the project has earned 40% of its budget.
Where the fraction comes from
The fraction complete is the weak point of the calculation. It should come from a rule fixed in the plan, before the work starts, and not from a judgment made at the status date. Common rules are:
- Fixed formula (for example 0/100 or 50/50). Under 0/100, a package earns nothing until it is finished and then earns everything. Under 50/50, it earns half when it starts and the rest when it finishes. These suit short packages, where there is little progress to report between start and finish.
- Weighted milestones. The package is divided into milestones, each with a share of the budget. EV is the sum of the shares of milestones reached. This suits longer packages that have clear, verifiable checkpoints.
- Percent complete. Someone estimates the fraction done. This is the easiest to apply and the easiest to inflate, so use it only for work that can be measured, such as units installed or meters laid.
Choose the rule per work package and record it in the plan. Changing the rule mid-project, particularly after progress looks poor, makes EV values incomparable over time.
A weighted-milestone example
Suppose Build (budget 50,000) has four milestones:
| Milestone | Share of budget | Value | Reached? |
|---|---|---|---|
| Environment ready | 10% | 5,000 | Yes |
| Core modules coded | 40% | 20,000 | Yes |
| Integration done | 30% | 15,000 | No |
| Code review passed | 20% | 10,000 | No |
EV for Build is 5,000 + 20,000 = 25,000, or 50% of the package. A percent-complete estimate for the same package might have said 40% or 70%, depending on who was asked. The milestone rule removes that argument, because a milestone is either reached or it is not.
From EV to the other measures
Once you have EV, PV, and AC at the same status date, the core measures follow. The next chapters explain each one. This code shows how EV feeds them:
def evm_metrics(bac, pv, ev, ac):
"""Core EVM measures at one status date. All inputs are in the same currency."""
if pv <= 0 or ac <= 0:
raise ValueError("PV and AC must be positive to compute SPI and CPI")
sv = ev - pv # schedule variance
cv = ev - ac # cost variance
spi = ev / pv # schedule performance index
cpi = ev / ac # cost performance index
eac = bac / cpi # forecast if current cost efficiency continues
etc = eac - ac # estimate to complete
vac = bac - eac # variance at completion
tcpi = (bac - ev) / (bac - ac) # efficiency needed to finish within BAC
return {"SV": sv, "CV": cv, "SPI": spi, "CPI": cpi,
"EAC": eac, "ETC": etc, "VAC": vac, "TCPI": tcpi}
m = evm_metrics(bac=100000, pv=40000, ev=30000, ac=45000)
for name, value in m.items():
print(f"{name}: {value:,.2f}")With EV at 30,000, the project is behind schedule (SV = −10,000, SPI = 0.75) and over budget (CV = −15,000, CPI ≈ 0.67). Every one of those figures depends on EV. An EV that is too high hides both problems.
Edge cases
- EV cannot exceed the package budget. A package at 100% earns exactly its budget, even if it cost far more or finished early. Overspending shows up in AC, not in EV.
- EV does not go down when work is rejected, unless you reverse it. If a completed package fails inspection, reduce its credited fraction to what the rule supports. Leaving it at 100% overstates progress.
- Scope changes alter BAC and EV together. An approved change adds budget to the baseline. Do not count new work as earned until it is done. Unapproved extra work earns nothing and only raises AC.
- Level of effort (LOE) work. Activities such as project management have no measurable output. Their EV is usually set equal to PV, so they never produce a schedule variance. Keep them separate from measurable work, or they will mask real slippage in the project totals.
- Cumulative versus period values. EV is normally tracked cumulatively. Report the period value as the difference between two status dates, and do not mix the two in one calculation.
- Materials and partial deliveries. Decide in advance whether purchased material earns value on receipt or on installation. Pick one rule per package.
Common errors
- Using AC as a stand-in for progress. Spending 45,000 does not mean 45,000 of work is done. EV is measured from completed work and AC is measured from cost records. They are independent.
- Mixing price bases. EV must use the baseline budget, not current prices or revised estimates. Otherwise CPI and SPI compare unlike things.
- Crediting work that was not scheduled. Early work does earn EV, but only against the package it belongs to. EV is compared with PV at the status date, so early work shows as positive schedule variance.
- Changing rules after the fact. Switching a package from 0/100 to percent complete once it looks late distorts the history.
- Reading EV without PV and AC. EV alone says only how much is done. It says nothing about whether that is good or bad.
Exercise
A work package has a budget of 80,000 and uses weighted milestones: specification approved (15%), prototype built (35%), testing complete (30%), handover accepted (20%). At the status date the first two milestones are reached, testing is 80% done by the team's estimate, and handover has not happened. The project's AC for this package is 62,000 and its PV is 60,000. What is the package's EV, SV, and CV?
Show answer
Only milestones that are reached earn value, so the testing estimate is ignored. EV = (15% + 35%) × 80,000 = 40,000. SV = EV − PV = 40,000 − 60,000 = −20,000, so the package is behind schedule. CV = EV − AC = 40,000 − 62,000 = −22,000, so it is over budget for the work done.
Exercise
A report says a package with a 50,000 budget is "90% complete", and shows EV of 45,000. The team has not passed its acceptance test, and the test has failed twice. Which measurement rule would have given a more defensible EV, and what would EV be under a 50/50 rule if the package has started but not finished?
Show answer
A weighted-milestone rule that credits the acceptance test only when it passes would be more defensible, because the 90% figure hides the unfinished and failing work. Under a 50/50 rule, a started but unfinished package earns 50% of its budget, so EV = 25,000.