Budget at Completion: The Total of the Plan
Budget at completion (BAC) is the total budget for all the work in the performance measurement baseline. It is the number at the top of the plan, and nearly every forecast formula in earned value management uses it.
This chapter assumes you know what a work breakdown structure (WBS) and a control account are, and that you can read a time-phased budget. If not, review the previous two chapters first.
What BAC Is
BAC is the sum of the budgets of all the work packages and control accounts in the baseline. Planned value (PV) is the budget scheduled to be spent by a given date. BAC is the PV at the end of the project, when all the work has been scheduled.
BAC answers one question: how much money did we authorize to do all of the planned work?
BAC is not the following:
- The forecast. The forecast is the estimate at completion (EAC). BAC is what you planned and EAC is what you now expect.
- The price or contract value. A price includes profit, fees, and risk allowances that are not part of the cost budget.
- The total funds available. Management reserve may sit above BAC, as shown below.
How BAC Is Built
You build BAC from the bottom up. Each work package gets a budget, work packages roll up into control accounts, and control accounts roll up into BAC.
The reserve layers need care, because organizations treat them differently.
| Layer | Included in BAC? | Who controls it |
|---|---|---|
| Work package and control account budgets | Yes | Control account manager |
| Contingency reserve | Depends on the organization's convention | Project manager |
| Management reserve | No | Senior management |
Contingency reserve covers identified risks. The PMBOK Guide includes it in the cost baseline, but many organizations hold it at project level and leave it out of BAC. Management reserve covers unknown unknowns. It is never part of BAC, and spending it requires a formal change to the baseline.
BAC and the Time-Phased Budget
Because BAC is the final value of the PV curve, you can check your baseline with one test. The cumulative time-phased budget must end exactly at BAC. If it does not, some work package is under-phased or over-phased.
The following code builds BAC from control accounts, accumulates the PV curve, and verifies that the two agree.
from itertools import accumulate
# Monthly budget by control account (months 1 to 6)
phased = {
"Design": [10000, 10000, 0, 0, 0, 0],
"Build": [0, 0, 15000, 20000, 15000, 0],
"Test": [0, 0, 0, 0, 10000, 20000],
}
bac = sum(sum(months) for months in phased.values())
monthly_totals = [sum(col) for col in zip(*phased.values())]
cumulative_pv = list(accumulate(monthly_totals))
print("BAC:", bac)
print("Cumulative PV:", cumulative_pv)
assert cumulative_pv[-1] == bac, "PV curve must end at BAC"The output shows a BAC of 100000 and a cumulative PV of [10000, 20000, 35000, 55000, 80000, 100000]. The last value of the curve equals BAC.
Where BAC Appears in the Formulas
BAC is the fixed reference point for the whole set of measures.
| Measure | Formula | What BAC does |
|---|---|---|
| Percent complete | EV / BAC | Turns earned value into a share of the whole project |
| Percent spent | AC / BAC | Shows how much of the budget has been consumed |
| EAC (typical) | BAC / CPI | Scales the original budget by cost efficiency |
| VAC | BAC - EAC | Compares the plan with the forecast |
| TCPI | (BAC - EV) / (BAC - AC) | Sets the work remaining and the budget remaining |
Percent complete and percent spent are worth comparing side by side. Suppose EV is 30,000, AC is 45,000, and BAC is 100,000. The project is 30% complete but has spent 45% of the budget, so the overspend is visible without computing any index.
bac, ev, ac = 100000, 30000, 45000
percent_complete = ev / bac
percent_spent = ac / bac
print(f"Complete: {percent_complete:.0%}") # Complete: 30%
print(f"Spent: {percent_spent:.0%}") # Spent: 45%Changing BAC: Approved Changes and Rebaselining
BAC is meant to stay stable. That stability is what makes variances meaningful. It changes in only two ways.
- An approved scope change. When a change request adds or removes work, the budget for that work is added to or removed from BAC. The PV, and later the EV, for the new work are added at the same time.
- A formal rebaseline. When the baseline is so far from reality that the variances no longer guide decisions, management may approve a new baseline. This is rare, and the history of variances before the rebaseline should be kept.
The following changes do not alter BAC:
- An overrun on existing work. This raises EAC, not BAC.
- Moving money between work packages without a scope change. This changes the phasing and the control account split, but the total is unchanged.
- Spending contingency or management reserve. These are tracked separately, and draws from them are approved against the reserve.
The next example shows how an approved change moves the forecast. The status is the same as before, but a change adds 12,000 of budgeted work.
ev, ac = 30000, 45000
cpi = ev / ac
bac_original = 100000
approved_change = 12000
bac_new = bac_original + approved_change
print(round(bac_original / cpi)) # 150000
print(round(bac_new / cpi)) # 168000This sketch is simplified. In a real change, the EV and PV for the new work are added to the baseline too, and any of the new work already completed raises EV. Here the added work is assumed to be unstarted.
Common Errors
- Treating BAC as the forecast. If you report "we will finish at 100,000" because that is the BAC, you ignore the performance data. Use EAC for the expectation.
- Including management reserve in BAC. Then VAC and TCPI look better than they should, because the extra budget is not actually assigned to work.
- A PV curve that does not end at BAC. This points to a phasing error or a missing work package.
- Changing BAC without a change record. Auditors and stakeholders cannot trace why variances shifted.
- Mixing currencies or units. BAC, PV, EV, and AC must use the same currency and, for labor-hour tracking, the same unit.
Exercise
A project has control account budgets of 60,000, 90,000, and 50,000. Senior management holds a separate management reserve of 15,000. After 40,000 of work (by budgeted value) is completed, what are BAC and the percent complete?
Show answer
BAC is 60,000 + 90,000 + 50,000 = 200,000. The management reserve is not part of BAC. Percent complete is EV / BAC = 40,000 / 200,000 = 20%.
Exercise
A project's BAC is 500,000. EV is 200,000 and AC is 250,000. An approved change adds 50,000 of unstarted work. What is the new BAC, and what is the new percent complete?
Show answer
The new BAC is 500,000 + 50,000 = 550,000. EV is unchanged because none of the new work is done, so percent complete is 200,000 / 550,000, about 36.4%. It falls from 40% because the denominator grew.