Sub topic 15
TCPI: the efficiency still required
This chapter assumes you can already compute EV, AC, CPI, and EAC, as covered in the earlier chapters. It adds one more index, the to-complete performance index (TCPI). Where CPI looks backward, TCPI looks forward.
What TCPI answers
CPI tells you how efficiently you have spent money so far. TCPI answers a different question: at what cost efficiency must the remaining work be done to hit a chosen financial target?
- Work remaining, measured in budget terms, is the value still to be earned.
- Money available is the target minus what you have already spent.
- TCPI is the first divided by the second.
The general form is:
TCPI = (work remaining) / (funds remaining) = (BAC - EV) / (target - AC)The target is a choice you make, and two targets are common:
- BAC-based TCPI uses the original budget as the target:
(BAC - EV) / (BAC - AC). It asks whether you can still finish on budget. - EAC-based TCPI uses the latest forecast as the target:
(BAC - EV) / (EAC - AC). It asks whether you can hit the forecast you have already published.
Always state which target you used. A bare "TCPI = 1.27" is ambiguous.
Reading the value
TCPI is compared against 1.0 and against your current CPI.
| TCPI | Meaning |
|---|---|
| Below 1.0 | Each remaining budget unit of work may cost more than one currency unit and you still meet the target. The target is comfortable. |
| Exactly 1.0 | You must spend exactly as planned from here on. |
| Above 1.0 | You must be more efficient than the budget assumed. The target is harder. |
The comparison with CPI matters more than the comparison with 1.0. Suppose your CPI is 0.67 and TCPI is 1.27. You would have to nearly double your cost efficiency for the rest of the project. Efficiency rarely improves that sharply, so the BAC target is probably unrealistic.
Some organizations set a tolerance, for example treating a TCPI more than about 10% above the current CPI as a signal to re-forecast. Treat that as a local policy, not a universal rule.
Worked example
Use the status data from the earlier chapters: BAC 100,000, EV 30,000, AC 45,000.
- Work remaining is
BAC - EV = 70,000. - Funds left against the original budget are
BAC - AC = 55,000. - BAC-based TCPI is
70,000 / 55,000 ≈ 1.27.
The project has spent 45,000 and earned only 30,000. To finish within 100,000, every remaining currency unit must buy about 1.27 units of budgeted work.
Now apply the EAC targets from the forecasting chapter. EAC is 150,000 if the current CPI continues, 115,000 if the overrun was a one-off, and 170,000 if cost and schedule efficiency both drive the remaining work.
- Against EAC 150,000, TCPI is
70,000 / 105,000 ≈ 0.67. - Against EAC 115,000, TCPI is
70,000 / 70,000 = 1.00. - Against EAC 170,000, TCPI is
70,000 / 125,000 = 0.56.
def tcpi(bac, ev, ac, target=None):
"""To-complete performance index.
target defaults to BAC. Pass an EAC to get the EAC-based index.
Returns float('inf') if no funds remain but work does.
"""
if target is None:
target = bac
work_remaining = bac - ev
funds_remaining = target - ac
if work_remaining < 0:
raise ValueError("EV cannot exceed BAC")
if funds_remaining <= 0:
if work_remaining == 0:
return 1.0 # nothing left to do, nothing left to spend
return float("inf") # work remains but the target is already spent
return work_remaining / funds_remaining
bac, ev, ac = 100000, 30000, 45000
cpi = ev / ac
print(f"CPI: {cpi:.2f}")
print(f"TCPI (BAC): {tcpi(bac, ev, ac):.2f}")
print(f"TCPI (EAC 150000): {tcpi(bac, ev, ac, 150000):.2f}")
print(f"TCPI (EAC 115000): {tcpi(bac, ev, ac, 115000):.2f}")
print(f"TCPI (EAC 170000): {tcpi(bac, ev, ac, 170000):.2f}")Running it prints:
CPI: 0.67
TCPI (BAC): 1.27
TCPI (EAC 150000): 0.67
TCPI (EAC 115000): 1.00
TCPI (EAC 170000): 0.56A built-in consistency check
Look at the EAC 150,000 line. The EAC-based TCPI equals the CPI. That is not a coincidence. EAC 150,000 came from BAC / CPI, which assumes the remaining work runs at the current CPI. So the efficiency required to hit that forecast is, by construction, the efficiency you already have.
This gives you a quick sanity check:
- If you forecast with the "current CPI continues" formula, EAC-based TCPI should equal CPI. If it does not, there is an arithmetic error.
- If you forecast with the "one-off overrun" formula (
AC + BAC - EV), EAC-based TCPI is always 1.0. You are assuming that the remaining work will cost exactly its budget.
The last point is useful. A forecast of 115,000 requires perfect budget performance from a project that has so far delivered 0.67. TCPI makes that hidden assumption visible.
Choosing the target
The diagram shows a common way to decide which target to use.
Moving to a new target is a management decision, and the sponsor may need to approve the changed budget. TCPI gives you the evidence for that conversation. It does not make the decision.
Edge cases and failure modes
- Denominator near zero. As AC approaches the target,
target - ACshrinks and TCPI grows without bound. Late in a project, a small overspend can send TCPI to 3 or 5. The number is correct but fragile, so look at the underlying amounts as well. - AC at or above the target. If you have already spent the BAC and work remains, the BAC-based TCPI is undefined or negative. The code above returns infinity. The honest message is that the BAC is gone and you need a new target.
- Early in the project. With little work done, TCPI sits near 1.0 because both the numerator and denominator are close to their full values. It carries little information until a meaningful share of work is complete.
- Bad inputs. TCPI inherits every weakness of EV and AC. If percent complete is optimistic or actual costs are missing, EV is inflated or AC is understated, and TCPI looks more achievable than it is.
- Schedule is not covered. TCPI as defined here is a cost measure. It says nothing about whether the remaining work can be done by the deadline.
Summary of the formulas
| Measure | Formula | Question answered |
|---|---|---|
| TCPI (BAC) | (BAC − EV) / (BAC − AC) | Can we still finish on the original budget? |
| TCPI (EAC) | (BAC − EV) / (EAC − AC) | Can we hit our latest forecast? |
Exercise
A project has BAC 200,000, EV 80,000, AC 100,000. (a) Compute CPI and BAC-based TCPI. (b) The manager forecasts EAC with the formula AC + (BAC - EV). What is the EAC-based TCPI, and what does it tell you about the forecast?
Show answer
(a) CPI = 80,000 / 100,000 = 0.80. BAC-based TCPI = (200,000 - 80,000) / (200,000 - 100,000) = 120,000 / 100,000 = 1.20. The team must be 1.20 efficient against a track record of 0.80, so the BAC target looks unrealistic. (b) EAC = 100,000 + 120,000 = 220,000. EAC-based TCPI = 120,000 / (220,000 - 100,000) = 1.00. This forecast assumes the remaining work will cost exactly its budget, which is hard to believe given a CPI of 0.80, so the forecast is optimistic.
Exercise
Why does EAC-based TCPI equal CPI when EAC is calculated as BAC / CPI?
Show answer
EAC = BAC / CPI means EAC - AC = (BAC - EV) / CPI after substitution of the standard result, so TCPI = (BAC - EV) / (EAC - AC) = CPI. The forecast assumes the remaining work runs at the current CPI, so the efficiency required equals the efficiency already achieved.