Sub topic 4
Planned value: the budgeted cost of work scheduled
This chapter assumes you know what a work breakdown structure (WBS) and a baseline schedule are. It also assumes you can do percentage and ratio arithmetic. By the end you should be able to build planned value (PV) from a schedule, read it at any status date, and avoid the usual mistakes when using it.
What planned value answers
Planned value is the approved budget for the work that was scheduled to be finished by a given date. It answers one question: how much work should be done by now, measured in budget money?
PV is not spending and not progress. It describes the plan only. Nothing that happens on the project changes it, unless the baseline is formally changed. This makes it the yardstick for the other two measures:
| Measure | Question it answers | Depends on |
|---|---|---|
| Planned value (PV) | How much work was scheduled by now? | Baseline budget and schedule |
| Earned value (EV) | How much work is actually done? | Budget and measured progress |
| Actual cost (AC) | What did the done work cost? | Accounting records |
Other sources call PV the budgeted cost of work scheduled (BCWS). The two names mean the same thing.
How PV is built
PV comes from three inputs that already exist in a well-formed baseline:
- A budget for each work package, taken from the cost estimate.
- A schedule for each work package: its start and finish dates, or the periods in which it is planned.
- A spreading rule that says how the budget falls across those periods.
You put each work package's budget into the periods when its work is scheduled. This is called time-phasing. Then you add up all work packages for each period. The running total of the period values is the cumulative PV.
Cumulative PV starts at zero and never decreases. In the last period it equals the budget at completion (BAC), which the next chapter covers. That gives you a useful check: if your cumulative PV does not end at the sum of all work package budgets, the time-phasing has lost or duplicated money.
Spreading rules
The spreading rule is a modelling choice. It should match how the work really consumes budget.
- Linear (even) spread. The budget is divided equally across the work package's duration. This is the default and fits steady effort.
- Start-loaded or finish-loaded. All or most of the budget lands at the start or the end. This fits a purchase that is paid when ordered, or a deliverable that is only recognized when accepted.
- Resource-loaded. The spread follows the planned hours or costs of the resources assigned, period by period. This is the most accurate rule when you have a resource-loaded schedule.
- Milestone-based. The budget lands on planned milestone dates. This is common for fixed-price work.
Use the same rule in your plan that you will later use to measure EV. If PV is spread evenly but EV is credited only at completion, the two will disagree for reasons that have nothing to do with performance.
A worked example
Use the three work packages from the running example. The status date is the end of month 3.
| Work package | Budget | Scheduled months | Even spread per month |
|---|---|---|---|
| Design | 20,000 | 1 to 2 | 10,000 |
| Build | 50,000 | 2 to 6 | 10,000 |
| Test | 30,000 | 6 to 8 | 10,000 |
The script below time-phases the budgets and prints period and cumulative PV.
from itertools import accumulate
work_packages = [
{"name": "Design", "budget": 20000, "start": 1, "finish": 2},
{"name": "Build", "budget": 50000, "start": 2, "finish": 6},
{"name": "Test", "budget": 30000, "start": 6, "finish": 8},
]
def pv_by_period(packages, periods):
"""Spread each budget evenly over its scheduled periods (inclusive)."""
pv = [0.0] * periods
for wp in packages:
length = wp["finish"] - wp["start"] + 1
per_period = wp["budget"] / length
for period in range(wp["start"], wp["finish"] + 1):
pv[period - 1] += per_period
return pv
periods = 8
monthly = pv_by_period(work_packages, periods)
cumulative = list(accumulate(monthly))
for month, (m, c) in enumerate(zip(monthly, cumulative), start=1):
print(f"Month {month}: period PV {m:,.0f}, cumulative PV {c:,.0f}")
print("PV at end of month 3:", f"{cumulative[2]:,.0f}")
print("Total equals BAC:", cumulative[-1] == sum(wp["budget"] for wp in work_packages))The output ends with a cumulative PV of 40,000 at the end of month 3. That is Design's full 20,000, plus two months of Build at 10,000 each. The final value is 100,000, which equals the sum of the budgets, so the check prints True.
Month 2 and month 6 have period PV of 20,000 because two work packages overlap. Cumulative PV therefore rises faster in those months. Plotted over the whole project, cumulative PV usually forms an S shape, because effort is light at the start and end and heavy in the middle. Later chapters read that curve.
PV at a status date
At any status date, PV is the cumulative value up to and including that period. You also need to handle dates that fall inside a period.
- If you report at period ends, read the cumulative value directly.
- If you report mid-period, take the cumulative PV of the previous period and add the fraction of the current period's PV that has elapsed. Use the same fraction rule that you used in the spread. With an even spread this is simple proration, with a back-loaded spread it is not.
- Use the same status date for PV, EV, and AC. Mixing a PV from the 15th with an AC from the 31st makes every variance wrong.
Common errors
Treating PV as a forecast. PV is the plan. If the schedule changes because of delays, PV does not move. Moving it would hide the slip that SV is meant to expose.
Changing PV without a baseline change. PV changes only through approved change control, such as a scope change or a re-baseline. Quietly rewriting dates to match reality destroys the comparison.
Spreading budget by calendar rather than by work. A work package that is scheduled across a holiday shutdown should not receive budget for the shutdown days. Spread over working periods.
Including management reserve. Management reserve sits outside the performance baseline. It is not part of PV. Contingency reserve is a related case. Whether it is inside the baseline depends on your organization's rules, so check before including it.
Ignoring dependencies when dates move. If a predecessor slips and the successor's baseline dates are not updated through change control, PV is still correct as a baseline. The slip will show as a negative SV. Do not "fix" it by editing PV.
Forgetting that PV is in budget currency. PV uses budgeted rates, not today's rates. If actual rates differ, that difference belongs in AC and cost variance, not in PV.
Limits of PV
PV only tells you what was supposed to happen. On its own it cannot say whether the project is ahead or behind. You need EV for that, and the difference between EV and PV gives schedule variance. PV also counts work in money, not in time, which is why SV and SPI can mislead late in a project. The earned schedule chapter returns to this.
Exercise
Using the table in this chapter, what is cumulative PV at the end of month 6? Show which work packages contribute.
Show answer
80,000. Design is fully scheduled by month 2, so it contributes 20,000. Build runs through month 6, so it contributes its full 50,000. Test starts in month 6 and has one of its three months scheduled, so it contributes 10,000. The sum is 20,000 + 50,000 + 10,000 = 80,000.
Exercise
A project manager sees that the Build work package is two months late. She changes its baseline dates to the new finish so that SV returns to zero. What is wrong with this, and what should happen instead?
Show answer
PV is the approved plan, and editing it without change control erases the evidence of the delay. SV should stay negative until the work catches up or a formal re-baseline is approved. Any date change should go through change control, with the reason documented.