Sub topic 17
Data quality and common pitfalls
This chapter assumes you can compute PV, EV, AC, the variances and the indices (SV, CV, SPI, CPI), and that you know the EAC formulas. It covers the ways good formulas produce bad answers. Every EVM measure is a ratio or difference of three numbers. If one of those numbers is wrong, the result looks exact and still misleads.
Where bad numbers come from
Each of the three inputs has its own typical failure.
| Input | Typical failure | Effect on the metrics |
|---|---|---|
| PV | Baseline is stale, or changed without approval | SV and SPI compare against a plan nobody follows |
| EV | Progress is reported optimistically or by gut feel | SPI and CPI look better than reality |
| AC | Costs are missing, late, or booked to the wrong account | CPI looks better than reality, EAC is too low |
EV and AC are measured by different people with different systems. Progress comes from team leads. Costs come from finance or timesheets. The two often use different cut-off dates and different account structures. Many problems in this chapter are mismatches between them.
Optimistic progress reporting
EV equals budget times the fraction complete, so any inflation in the fraction goes straight into EV. Two patterns are common.
The 90% syndrome. A work package reaches "90% complete" quickly and then stays there for weeks. Estimates of percent complete are easy to give and hard to check. People report effort spent, not value produced.
Front-loaded credit. A package is credited for work that has started but not been verified. A common example is counting "code written" as done before testing.
The defenses are in how you set the measurement rule, not in checking people more often:
- Use objective rules where you can. Fixed-formula (0/100 or 50/50) and weighted-milestone rules need a checkable event, not an opinion.
- Reserve percent-complete for short packages. Keep work packages within a reporting period or two, so a wrong estimate cannot hide for long.
- Define milestones by acceptance. "Review passed" is checkable. "Mostly finished" is not.
- Require evidence of completion, such as a deliverable, a test result, or a sign-off.
Incomplete actual cost
AC must include all cost that the budget was meant to cover, up to the status date. Common gaps:
- Supplier invoices that arrive after the cut-off, so the cost is real but not yet booked.
- Labor that is booked a period late, because timesheets are approved after month end.
- Costs booked to a different project, a shared overhead account, or a department that the project report does not read.
- Committed costs, such as purchase orders for goods already delivered, that are not yet invoiced.
The effect is a CPI that is too high. Here is a small example. EV is 30,000, finance reports AC of 30,000, but 12,000 of delivered work has not been invoiced.
ev = 30000
ac_reported = 30000
uninvoiced = 12000 # delivered but not yet booked
bac = 100000
ac_true = ac_reported + uninvoiced
cpi_reported = ev / ac_reported
cpi_true = ev / ac_true
print(f"Reported CPI: {cpi_reported:.2f}") # 1.00
print(f"True CPI: {cpi_true:.2f}") # 0.71
print(f"EAC reported: {bac / cpi_reported:,.0f}") # 100,000
print(f"EAC true: {bac / cpi_true:,.0f}") # 140,000A missing 12,000 turns an on-budget forecast into a 40,000 overrun. The fix is to accrue costs: record the cost when the work is done, not when the invoice arrives. If accruals are not possible, at least estimate unbooked cost for the status report and mark it as an estimate.
Mismatched timing and scope
Even when each number is correct, they may not describe the same thing.
- Different status dates. PV is calculated to the end of the month, EV to the last progress meeting, AC to the last payroll run. Pick one status date and make every input follow it.
- Different scope. If AC includes cost of work that has no matching PV or EV (for example, an unapproved change), CPI drops for a reason unrelated to performance. Keep each input tied to the same work packages and the same control accounts.
- Different cost types. PV may be budgeted in labor hours or at standard rates, while AC is at actual rates. Convert to one currency and one basis.
- Different baselines. After a change, PV may use the new baseline while EV still credits work against the old budget.
Baseline problems
The metrics are only as meaningful as the baseline.
Rebaselining to hide variance. Resetting the baseline whenever the project falls behind erases SV and CV and returns the indices to 1.0. Rebaseline only through approved change control, and keep a record of the original baseline so cumulative variance can still be reported.
Unrealistic baselines. If the plan was padded or built with no sound estimate, the indices measure the quality of the estimate, not of execution. A CPI of 1.2 might mean the team is efficient, or that the budget was generous.
Unscheduled work. Work that is not in the WBS has no PV and no EV, but it still generates AC. It worsens CPI and the project can look like it is performing badly when it is doing extra work. Control scope with change requests so extra work gets its own budget.
Misreading the metrics
- Treating SV as a time measure. SV is in currency, and it falls toward zero as the project nears the end, even for a late project. Use it with caution late in the project and consider earned schedule instead.
- Ignoring the critical path. SPI aggregates all work. A project can show SPI near 1.0 because non-critical work is ahead while critical work is late. EVM does not replace schedule analysis.
- Using one data point. A single period's CPI is noisy. Look at the cumulative CPI and the trend over several periods. Cumulative CPI tends to stabilize early, so a poor value is unlikely to recover.
- Averaging indices across unlike work. Rolling up packages with very different risk can hide a failing one. Check the control accounts underneath the total.
- Forecasting with one formula. The EAC formula must match the assumption about the future. Applying
BAC / CPIwhen the overrun was a one-time event gives an inflated forecast, andAC + (BAC - EV)when the problem is systemic gives one that is too low.
A basic sanity check
Automated checks catch many data errors before anyone interprets the metrics. This function flags values that cannot be right.
def check_status(bac, pv, ev, ac, prior_ev=0, prior_ac=0):
"""Return a list of data-quality issues for one status snapshot."""
issues = []
if not 0 <= pv <= bac:
issues.append("PV is outside 0..BAC")
if not 0 <= ev <= bac:
issues.append("EV is outside 0..BAC")
if ev < prior_ev:
issues.append("EV decreased since the last period")
if ac < prior_ac:
issues.append("AC decreased since the last period")
if ac == 0 and ev > 0:
issues.append("Progress claimed with no cost booked: actuals may be missing")
if ev == 0 and ac > 0:
issues.append("Cost booked with no progress credited")
return issues
problems = check_status(bac=100000, pv=40000, ev=30000, ac=0,
prior_ev=20000, prior_ac=25000)
for p in problems:
print(p)
# AC decreased since the last period
# Progress claimed with no cost booked: actuals may be missingA check like this does not prove the data is right. It only catches impossible values. EV can fall legitimately when work is rejected and reopened, so treat that warning as a prompt to ask, not as an error.
A short review routine
- Confirm that all three inputs use the same status date and the same set of work packages.
- Check that AC includes accruals and committed costs for delivered work.
- Review the progress rule for each large package, and ask for evidence for any package that has stayed near the same percentage for several periods.
- Confirm that the baseline changed only through approved change control.
- Run the sanity checks, then compute the metrics, and read cumulative trends rather than a single period.
- Choose the EAC formula that matches your assumption about future performance, and state the assumption.
Exercise
At a status date, EV is 48,000 and finance reports AC of 40,000, so CPI is 1.20. You learn that a supplier delivered 10,000 of materials used in the work but has not yet invoiced. What is the corrected CPI, and what does the correction tell you about the project?
Show answer
True AC is 40,000 + 10,000 = 50,000, so CPI = 48,000 / 50,000 = 0.96. The project appeared 20% under budget but is actually slightly over budget. The error came from unbooked cost, so the fix is to accrue costs for delivered work instead of waiting for invoices.
Exercise
A work package with a budget of 20,000 has been reported at 90% complete for four consecutive periods. Name two changes to the measurement approach that would reduce the risk of overstated EV.
Show answer
Any two of these: split the package into shorter packages so progress is checked more often; replace percent-complete with a weighted-milestone or fixed-formula rule tied to checkable events such as acceptance or sign-off; require evidence of completion before credit is given.