Work Packages and Control Accounts: Where the Numbers Live
Assume you know basic project terms such as scope, schedule, budget, milestone, and work breakdown structure (WBS). You should also be comfortable with percentages and simple arithmetic. This chapter shows how a WBS becomes a structure for measuring earned value management (EVM).
From the WBS to measurable work
A work breakdown structure divides the project scope into smaller deliverables. The lowest useful level for planning and measurement is often a work package. A work package is a defined piece of work with:
- A clear deliverable
- An owner
- A planned start and finish
- A budget
- A method for measuring progress
- A time-phased plan showing when the budget will be used
For example, a website project might have a work package called “Create product catalog.” Its budget could be $30,000, scheduled across April and May.
Several related work packages form a control account. A control account is a management point where scope, schedule, budget, progress, and actual cost are compared. A control account manager is responsible for the results inside that account.
Control accounts and work packages
The control account is high enough for management reporting but detailed enough to identify problems. The work package is low enough for the team to plan and measure specific work.
| Level | Main purpose | Typical information |
|---|---|---|
| Control account | Manage and report a group of related work | Owner, total budget, schedule, variances |
| Work package | Plan and measure defined work | Budget, dates, progress rule, actual cost |
| Planning package | Hold future work not yet detailed | High-level budget and expected timing |
A planning package is budgeted future work that has not yet been divided into detailed work packages. It should not hide current work that the team could already define. As the project approaches that work, the planning package should be converted into detailed work packages through a controlled baseline update.
Building the performance measurement baseline
The performance measurement baseline (PMB) is the approved, time-phased plan used to compare actual performance. It combines the project’s authorized scope, schedule, and budget.
To build it:
- Decompose the approved scope into WBS elements.
- Assign related work packages to control accounts.
- Estimate the budget for each work package.
- Schedule each package across specific time periods.
- Choose a progress measurement rule.
- Add the time-phased budgets to create planned value (PV).
The sum of all work package budgets is the budget at completion (BAC). A package budget is not earned merely because money was spent. Earned value (EV) depends on how much of the defined work is complete, using the agreed measurement rule.
For instance, a $20,000 design package using a 50/50 rule earns $10,000 when it starts and the remaining $10,000 when it finishes. The rule prevents a team from declaring arbitrary progress.
Common errors
A control account should not mix unrelated deliverables merely to simplify reporting. Doing so can hide an overrun in one area behind savings in another. Another error is placing all budget in a control account without assigning it to work packages or planning packages. That budget cannot produce credible progress data.
Actual cost must also be assigned to the same structure. If labor, invoices, or materials are recorded late or against the wrong control account, cost variance will be misleading.
Exercise
A control account contains three work packages with budgets of $10,000, $15,000, and $25,000. What is the control account budget, and what must be added before it can support time-based PV reporting?
Show answer
The budget is $50,000. Each work package needs planned dates and a time-phased budget. The account also needs agreed progress rules and a method for recording actual cost.