Sub topic 7
Earned Value: The Budgeted Cost of Work Performed
This chapter assumes you know basic project management terms, including work breakdown structure, task estimates, milestones, and a performance baseline. You should also be comfortable with percentages and simple ratios.
What earned value measures
Earned value (EV) is the budgeted cost of the work that is actually complete. It answers this question:
> How much of the approved budget has the completed work earned?
EV does not mean the money spent. Actual cost (AC) measures that. EV also does not mean the work planned by a certain date. Planned value (PV) measures that.
For example, a work package has a budget of $50,000. If the team has completed 40% of its scope, its EV is:
\[ EV = \$50{,}000 \times 0.40 = \$20{,}000 \]
The team may have spent $25,000 to produce that work. In that case, EV is still $20,000 and AC is $25,000. Comparing the two reveals a cost problem.
How EV fits with PV and AC
At a status date, the three measures describe different facts:
| Measure | Full name | Question answered |
|---|---|---|
| PV | Planned value | How much budgeted work should be complete? |
| EV | Earned value | How much budgeted work is actually complete? |
| AC | Actual cost | How much did the completed work cost? |
These values must use the same scope, budget currency, and status date. EV comes from the performance measurement baseline, not from invoices alone.
Choosing a progress rule
A project team must define how much budget a work package earns as it progresses. The rule should be agreed before status reporting begins.
Fixed-formula rule
A fixed-formula rule gives credit in predefined steps. The common 0/100 rule earns no value until the work is complete, then earns 100%. A 50/50 rule earns half at start and half at completion.
These rules are simple and reduce optimistic progress claims. They work best for short, clearly bounded work packages.
Weighted milestones
A work package earns value when it passes specified milestones. Each milestone has a weight, and the weights total 100%.
For example, design might earn 30% after requirements approval, 40% after the draft review, and 30% after final approval. If the first two milestones are complete, EV equals 70% of the package budget.
Percent complete
With a reliable physical measure, EV is the budget multiplied by the verified percentage complete:
work_packages = [
{"name": "Design", "budget": 20_000, "percent_complete": 1.00},
{"name": "Build", "budget": 50_000, "percent_complete": 0.40},
{"name": "Test", "budget": 30_000, "percent_complete": 0.00},
]
bac = sum(item["budget"] for item in work_packages)
ev = sum(item["budget"] * item["percent_complete"]
for item in work_packages)
print(f"BAC: ${bac:,.0f}") # BAC: $100,000
print(f"EV: ${ev:,.0f}") # EV: $40,000The method is valid only when “40% complete” represents completed scope, not time elapsed or money spent. Spending 40% of a budget does not prove that 40% of the work is complete.
Checking earned value
To validate EV, ask:
- What observable deliverable or milestone proves the work is complete?
- Which measurement rule applies to this work package?
- Is the reported progress based on output rather than elapsed time?
- Are the package budget and status date consistent with the baseline?
Exercise
A work package has a budget of $24,000. It uses a 50/50 rule, and the work has started but is not complete. What are its EV and remaining unearned budget?
Show answer
EV is $12,000. The remaining unearned budget is $12,000, because the package earns the other half only when it is complete.