Sub topic 8
Actual Cost: What the Work Really Cost
Prerequisites
This chapter assumes you know basic project management terms, work breakdown structures, budgets, milestones, percentages, and ratios. You should also know that earned value management (EVM) compares planned value, earned value, and actual cost at the same status date.
What actual cost means
Actual cost (AC) is the cost incurred for the work performed by a specific status date. It answers this question:
> How much did the completed work really cost?
AC can include:
- Labor charged to the work package
- Materials and equipment
- Subcontractor invoices
- Allocated overhead
- Approved expenses
- Other costs recorded by the organization's accounting system
AC is not necessarily the amount paid in cash. A supplier invoice may be recorded as an accrued cost before payment. Conversely, a purchase order may represent a commitment but not an actual cost yet. Your organization's accounting rules determine when a cost enters AC.
Aligning AC with earned value
AC is useful only when it matches the same scope and time period as earned value (EV). Suppose a work package has a budget of $50,000 and is 40% complete. Its earned value is:
\[ EV = \$50{,}000 \times 0.40 = \$20{,}000 \]
If the project has recorded $24,000 of labor and materials for that work by the status date, then:
\[ AC = \$24{,}000 \]
The cost variance is:
\[ CV = EV - AC = \$20{,}000 - \$24{,}000 = -\$4{,}000 \]
The negative result means the completed work cost $4,000 more than its budgeted value. The cost performance index (CPI) is:
\[ CPI = \frac{EV}{AC} = \frac{20{,}000}{24{,}000} \approx 0.83 \]
A CPI below 1.00 indicates that the project is getting less than one dollar of budgeted work for each dollar spent.
| Value | Amount | Meaning |
|---|---|---|
| Budget for work package | $50,000 | Total authorized budget |
| Earned value | $20,000 | Budgeted value of completed work |
| Actual cost | $24,000 | Cost recorded for completed work |
| Cost variance | -$4,000 | Over budget for the work performed |
How AC enters the EVM process
Project controls staff usually collect AC from timesheets, invoices, payroll records, expense reports, and accounting journals. They then assign each cost to the correct control account and work package. The accounting data must be cut off at the same status date used for PV and EV.
earned_value = 20_000
actual_cost = 24_000
cost_variance = earned_value - actual_cost
cpi = earned_value / actual_cost
print(f"CV: ${cost_variance:,.0f}")
print(f"CPI: {cpi:.2f}")Common data problems
AC can be misleading when:
- Timesheets are submitted late.
- Invoices are recorded in a different accounting period.
- Costs are assigned to the wrong control account.
- Overhead is omitted or applied inconsistently.
- Commitments are reported as costs before they are incurred.
- Labor is recorded, but the related work is not yet complete.
A low AC may look favorable while hiding missing invoices or unreported labor. Before interpreting CPI, check whether the accounting data is complete and whether the cost allocation rules are consistent.
Exercise
A work package has an earned value of $36,000 and an actual cost of $30,000. What are its cost variance and CPI, and what do they indicate?
Show answer
CV = $36,000 - $30,000 = $6,000. CPI = $36,000 / $30,000 = 1.20. The positive variance and CPI above 1.00 indicate that the completed work cost less than its budgeted value.