The Performance Measurement Baseline
Assume you know basic project terms such as scope, schedule, budget, milestones, and work breakdown structure (WBS). You should also be comfortable with percentages and simple spreadsheet arithmetic.
What the baseline contains
The performance measurement baseline (PMB) is the approved, time-phased plan used to measure project performance. It connects three views of the same commitment:
- Scope: the work the project promises to deliver.
- Schedule: when that work is planned.
- Cost: the budget assigned to that work.
“Time-phased” means that the budget is distributed across calendar periods instead of being shown only as one total. For example, a project might have a total budget of $100,000, with $20,000 planned for January, $50,000 for February, and $30,000 for March.
The PMB is not simply the latest estimate. It is the approved reference point against which progress and spending are compared. A team should not change it merely because the project is performing poorly. Approved scope or schedule changes can update the baseline through formal change control.
From WBS to control accounts
A WBS decomposes the project into manageable deliverables. A control account is a management control point where scope, schedule, and budget are brought together. A control account manager is responsible for planning and reporting the work at that point.
Each control account contains one or more work packages. A work package is a small, measurable unit of planned work. It has a defined result, an owner, planned dates, and a budget. Work packages should be small enough that the team can objectively judge their progress.
Some future work may be too far away to detail. That work can be held in a planning package, which is a temporary planning placeholder. As the work approaches, the team should break it into detailed work packages without changing the approved total budget unless a controlled change is authorized.
| Baseline element | Main question it answers |
|---|---|
| Scope and WBS | What work is included? |
| Schedule | When is the work planned? |
| Time-phased budget | How much budget is assigned to each period? |
Building and maintaining the baseline
A practical baseline-building sequence is:
- Confirm the approved scope and WBS.
- Assign each work package to a control account and owner.
- Estimate the budget for each work package.
- Place each budget into the periods when the work is planned.
- Check that the schedule, budget, and scope agree.
- Approve the result and record the baseline version.
The sum of the time-phased budgets is the budget at completion (BAC). Later, the project team uses the baseline to calculate planned value, which is the budgeted value of work scheduled by a specific status date.
# A simple time-phased baseline
monthly_budget = {
"January": 20_000,
"February": 50_000,
"March": 30_000,
}
bac = sum(monthly_budget.values())
cumulative_plan = {}
running_total = 0
for month, budget in monthly_budget.items():
running_total += budget
cumulative_plan[month] = running_total
print(f"BAC: ${bac:,.0f}")
print(cumulative_plan)Exercise
A customer approves an additional deliverable with a $12,000 budget. Should the project manager silently add the budget to next month's baseline?
Show answer
No. The approved scope change should go through change control. After approval, update the affected WBS, schedule, work packages, and time-phased baseline, then record the new baseline version.