Budget at Completion: the Total of the Plan
Prerequisites and purpose
This chapter assumes you know basic project terms such as scope, schedule, milestone, budget, and work breakdown structure (WBS). You should also be comfortable with percentages and simple arithmetic.
Budget at completion (BAC) is the total approved budget for the project’s planned work. It answers one question:
> How much did we plan to spend for the authorized project scope?
BAC is a baseline value. It does not change merely because the project is late or over budget. Changes require approved scope or baseline-control decisions.
How BAC is built
A project team divides the approved scope into a WBS. The WBS is organized into control accounts, which group related work for management and reporting. Each control account contains work packages or planning packages with assigned budgets.
The performance measurement baseline (PMB) combines the authorized scope, schedule, and time-phased budget. BAC is the total budget in that baseline.
\[ BAC = \sum \text{budgeted work packages} + \text{other authorized baseline budgets} \]
For example:
| Work package | Budget |
|---|---|
| Design | $20,000 |
| Build | $50,000 |
| Test | $30,000 |
| **BAC** | **$100,000** |
The sum is $100,000, so the project’s BAC is $100,000. This value is also the final cumulative planned value (PV) when the complete baseline is represented.
What BAC includes and excludes
BAC includes the approved budgets for the work needed to deliver the project scope. It can include undistributed budget while the team assigns budget to detailed work. It excludes management reserve because management reserve is held outside the performance measurement baseline for unknown-unknowns and is not part of the budget for planned work.
A change request may increase or decrease BAC if it changes authorized scope and the approved baseline. A cost overrun does not increase BAC. Instead, the overrun appears later through cost variance and forecasts such as estimate at completion (EAC).
| Event | Effect on BAC |
|---|---|
| Actual spending exceeds the work package budget | No automatic change |
| Approved scope change adds budget | BAC may increase |
| Work finishes below budget | BAC remains unchanged |
| Management reserve is allocated through approved control | Baseline and BAC may change |
> callout note > Keep BAC separate from the current forecast. BAC describes the approved plan. EAC describes what the project is now expected to cost.
BAC provides the denominator for several EVM measures. For example, variance at completion is calculated as VAC = BAC - EAC. If BAC is $100,000 and EAC is $150,000, VAC is negative $50,000, indicating a forecast overrun against the approved plan.
Exercise
A project has three authorized work packages budgeted at $12,000, $28,000, and $60,000. Actual cost is already $45,000. What are BAC and the effect of actual cost on BAC?
Show answer
BAC is $100,000. Actual cost does not change BAC; it is reported separately as AC and compared with earned value.