Sub topic 14
Estimate to Complete and Variance at Completion
Assume you know basic project management terms, can read a work breakdown structure, and are comfortable with percentages, ratios, and simple spreadsheet arithmetic. This chapter uses four earned value management measures:
- BAC, or budget at completion, is the total approved budget for the project.
- EV, or earned value, is the budgeted value of the work completed.
- AC, or actual cost, is what the completed work has cost so far.
- CPI, or cost performance index, is
EV / AC. It measures cost efficiency.
Estimate to complete and variance at completion turn the current status into a forecast.
The two forecast measures
Estimate to complete (ETC) is the expected cost of the remaining work. It answers:
> How much more money do we expect to spend?
Variance at completion (VAC) is the expected difference between the approved budget and the forecast final cost. It answers:
> When the project finishes, will the final cost be above or below the budget?
The basic relationships are:
EAC = AC + ETC
VAC = BAC - EACEAC, or estimate at completion, is the forecast total cost when the project is complete. A positive VAC means the forecast is below budget. A negative VAC means the forecast is above budget.
Calculating ETC from a current CPI
When current cost performance is expected to continue, use:
EAC = BAC / CPI
ETC = EAC - AC
VAC = BAC - EACFor example, suppose:
- BAC = $100,000
- EV = $30,000
- AC = $45,000
The CPI is:
CPI = EV / AC
CPI = 30,000 / 45,000
CPI = 0.67The forecast is:
EAC = 100,000 / 0.67 ≈ 150,000
ETC = 150,000 - 45,000 = 105,000
VAC = 100,000 - 150,000 = -50,000The project is forecast to finish at about $150,000, which is $50,000 over its approved budget. The forecast remaining cost is $105,000.
def forecast(bac, ev, ac):
if bac <= 0 or ev <= 0 or ac <= 0:
raise ValueError("BAC, EV, and AC must be positive")
cpi = ev / ac
eac = bac / cpi
etc = eac - ac
vac = bac - eac
return cpi, eac, etc, vac
cpi, eac, etc, vac = forecast(100_000, 30_000, 45_000)
print(f"CPI: {cpi:.2f}")
print(f"EAC: ${eac:,.0f}")
print(f"ETC: ${etc:,.0f}")
print(f"VAC: ${vac:,.0f}")Choosing the forecast assumption
The CPI formula assumes that the current cost efficiency will continue. That is useful when the overrun reflects a continuing problem, such as low productivity or underestimated labor effort. It is not automatically correct.
| Situation | EAC formula | Assumption |
|---|---|---|
| Current cost efficiency continues | `BAC / CPI` | Past cost performance predicts future performance |
| Past overrun was unusual | `AC + (BAC - EV)` | Remaining work will follow its original budget |
| Cost and schedule affect remaining work | `AC + (BAC - EV) / (CPI × SPI)` | Both cost and schedule inefficiency will continue |
The last formula uses SPI, the schedule performance index. Use it only when schedule delays are expected to create additional cost. Schedule efficiency should not be inserted into every forecast automatically.
Reading ETC and VAC together
A negative VAC identifies a projected overrun, but it does not explain its cause. Compare ETC with the remaining budget, BAC - EV. If ETC is higher than that remaining budget, the project must improve its future cost efficiency or obtain more funding.
Exercise
A project has BAC of $80,000, EV of $20,000, and AC of $25,000. If the current CPI continues, what are EAC, ETC, and VAC?
Show answer
CPI is 0.80. EAC is $100,000, ETC is $75,000, and VAC is -$20,000.