Sub topic 9
Schedule Variance and Cost Variance
Assume you know basic project vocabulary, can read a work breakdown structure, and understand percentages and simple arithmetic. This chapter uses earned value management (EVM) at a status date, which is the point in time when project data is measured.
Two questions at the status date
EVM separates two questions:
- Schedule variance (SV): Is the project delivering more or less work than planned?
- Cost variance (CV): Did the completed work cost more or less than its approved budget?
Both calculations use three values:
- Planned value (PV): The budgeted value of work scheduled to be complete by the status date.
- Earned value (EV): The budgeted value of work actually completed by the status date.
- Actual cost (AC): The amount actually spent for the completed work.
The values must cover the same scope and status date. PV, EV, and AC are usually expressed in currency, even when they measure schedule performance.
Calculating the variances
The formulas are:
| Measure | Formula | Meaning |
|---|---|---|
| Schedule variance | `SV = EV - PV` | Difference between completed and planned work |
| Cost variance | `CV = EV - AC` | Difference between budgeted and actual cost |
Interpret the signs as follows:
- A positive SV means more budgeted work was completed than planned.
- A negative SV means less budgeted work was completed than planned.
- A positive CV means the completed work cost less than its budget.
- A negative CV means the completed work cost more than its budget.
- A value of zero means the measure is exactly on its baseline.
For example, suppose a project has these values at its status date:
- PV = $40,000
- EV = $30,000
- AC = $45,000
Then:
SV = $30,000 - $40,000 = -$10,000CV = $30,000 - $45,000 = -$15,000
The project has completed $10,000 less work than planned. The work completed has cost $15,000 more than its approved budget.
pv = 40000
ev = 30000
ac = 45000
schedule_variance = ev - pv
cost_variance = ev - ac
print(f"SV: ${schedule_variance:,.0f}")
print(f"CV: ${cost_variance:,.0f}")A variance is not automatically a reason to change the plan. First investigate its cause. A negative cost variance might result from overtime, an incorrect estimate, a supplier price increase, or costs posted to the wrong work package.
Why the values must be comparable
EVM compares budgeted values, not raw task counts. Completing two small tasks is not necessarily equivalent to completing two large tasks. EV gives each task the budgeted weight defined in the performance measurement baseline.
Schedule variance is measured in money, so it does not directly mean “ten days late.” To express schedule efficiency as a ratio, use the schedule performance index:
SPI = EV / PV
Similarly, cost efficiency uses the cost performance index:
CPI = EV / AC
In the example, SPI is 0.75, and CPI is about 0.67. The project has earned 75% of the planned work and received about 67 cents of budgeted value for each dollar spent.
flowchart TD
PV["Planned value (PV)"] --> SV["SV = EV - PV"]
EV["Earned value (EV)"] --> SV
EV --> CV["CV = EV - AC"]
AC["Actual cost (AC)"] --> CV
SV --> Status["Interpret schedule status"]
CV --> StatusExercise
A project reports PV = $80,000, EV = $72,000, and AC = $68,000. What are SV and CV, and what do their signs mean?
Show answer
SV = $72,000 - $80,000 = -$8,000, so less work was completed than planned. CV = $72,000 - $68,000 = $4,000, so the completed work cost less than its budget.