Sub topic 11
Reading the S-Curve of PV, EV, and AC
Assume you know the basics of a work breakdown structure, budgets, schedules, and simple ratios. This chapter shows how cumulative planned value (PV), earned value (EV), and actual cost (AC) reveal project status over time.
What the three curves show
An S-curve is a line chart that plots cumulative project values against time. The line often forms an S shape because projects usually spend and complete less work at the beginning, accelerate during execution, and slow down during closeout.
| Measure | Full name | Question it answers |
|---|---|---|
| PV | Planned value | How much budgeted work should be complete by this date? |
| EV | Earned value | How much budgeted work is actually complete by this date? |
| AC | Actual cost | How much money has the completed work actually cost? |
PV and EV use budgeted amounts. AC uses real recorded costs. Keeping these bases separate is essential. A project can spend $50,000 without earning $50,000 of budgeted value.
Reading the gaps between curves
At a status date, compare the vertical positions of the curves:
- If EV is below PV, less budgeted work is complete than planned. The project is behind schedule in earned-value terms.
- If AC is above EV, the completed work cost more than its budgeted value. The project is over budget.
- If EV is above PV, more work is complete than planned.
- If AC is below EV, the completed work cost less than its budgeted value.
For example, suppose the status date shows:
- PV = $40,000
- EV = $30,000
- AC = $45,000
EV is $10,000 below PV, so the project has completed less work than planned. AC is $15,000 above EV, so the completed work has cost more than its budgeted value.
These differences are cumulative. A gap can remain after a problem has been corrected because earlier schedule or cost performance is still included in the total.
A typical S-curve pattern
Early in a project, all three cumulative values should start near zero. During execution, the curves rise. At completion, PV and EV should converge at the budget at completion (BAC), assuming the approved scope and baseline remain unchanged.
AC may finish above or below BAC. If AC finishes above BAC, the project exceeded its planned budget. If the curves end at different times or values, check whether the project is actually complete, whether costs are missing, or whether the baseline changed.
Limits of the visual
An S-curve shows when a difference exists, but not why it exists. A low EV may result from delayed materials, unapproved work, poor estimating, or optimistic progress rules. A high AC may reflect a legitimate scope change rather than poor cost control.
Use the chart to identify where to investigate. Then inspect control accounts, work packages, progress evidence, commitments, and cost transactions. Also remember that schedule variance in money units does not directly state how many days late the project is.
Exercise
At the status date, PV is $80,000, EV is $70,000, and AC is $65,000. What does the curve relationship indicate?
Show answer
EV below PV indicates the project is behind plan in earned-value terms. AC below EV indicates the completed work cost less than its budgeted value. The project is behind schedule but under budget for the work completed.