Sub topic 17
Data Quality and Common Pitfalls in Earned Value Management
Assume you know basic project terms, work breakdown structures, budgets, milestones, percentages, and ratios. This chapter focuses on whether EVM data is trustworthy enough to support a decision.
The quality chain
Earned value management (EVM) depends on three values:
- Planned value (PV): the budgeted value of work scheduled by the status date.
- Earned value (EV): the budgeted value of work actually completed.
- Actual cost (AC): the cost recorded for the completed work.
A problem in any input can distort schedule variance, cost variance, SPI, CPI, and forecasts. For example, late invoices make AC too low. Optimistic progress reports make EV too high. An outdated baseline makes PV meaningless.
Common data problems
| Problem | What it distorts | Control |
|---|---|---|
| Work is marked complete without acceptance evidence | EV becomes too high | Require deliverables, tests, or approved milestones |
| Costs arrive after the reporting cutoff | AC becomes too low | Accrue committed or incurred costs using a documented rule |
| The baseline changes without approval | PV and BAC lose their reference point | Use formal change control and preserve prior versions |
| Shared costs are assigned inconsistently | AC cannot be compared across work packages | Define allocation rules before status reporting |
| Progress is reported as a guess | EV becomes subjective | Use objective completion rules |
| The same cost is recorded twice | AC and forecasts become inflated | Reconcile accounting and project-control records |
Progress is not effort
A team can spend many hours without earning much value. Conversely, a deliverable may be accepted after a small amount of final work. EVM should measure completed scope against the approved plan, not activity or optimism.
Choose a progress rule that fits the work:
- Fixed formula: earn 50% when work starts and 50% when it finishes.
- Weighted milestone: earn value when defined milestones are accepted.
- Percent complete: use only when completion can be assessed consistently.
- Units complete: earn value for verified units, such as tested components.
Do not mix rules casually. If one team reports “90% complete” based on effort and another reports it based on accepted output, their EV values do not have the same meaning.
A practical validation sequence
At each status date:
- Confirm that PV, EV, and AC use the same cutoff date.
- Reconcile the work-package total to the control-account and project totals.
- Check that EV does not exceed the budget for completed scope.
- Compare reported progress with evidence such as approvals, test results, or accepted products.
- Reconcile AC to the accounting ledger and investigate missing accruals.
- Record approved changes separately from performance variance.
- Review unusual jumps in EV, AC, CPI, or SPI against the previous period.
What EVM cannot prove
A good CPI does not prove that the product is useful or that quality is acceptable. A good SPI does not prove that the critical path is safe. EVM describes cost and schedule performance against a baseline. Combine it with scope, quality, risk, and dependency information.
Exercise
A work package has a budget of $20,000. The team reports 80% complete, but only 40% of its acceptance tests have passed. What should the project manager do before accepting the reported EV?
Show answer
Request objective completion evidence and apply the approved progress rule. If acceptance tests define completion, EV should reflect the verified 40% progress rather than the unsupported 80% estimate.