Sub topic 15
TCPI: the efficiency still required
Assume you know how to calculate planned value (PV), earned value (EV), actual cost (AC), budget at completion (BAC), and cost performance index (CPI). This chapter uses those values to judge whether a target is still realistic.
What TCPI measures
The to-complete performance index (TCPI) is the cost efficiency required for the remaining work. It answers this question:
> How efficiently must the remaining budgeted work be completed to reach a chosen cost target?
A TCPI of 1.00 means the remaining work must deliver one dollar of budgeted value for every dollar spent. A TCPI of 1.20 means the project must deliver $1.20 of budgeted value for each remaining dollar of cost.
Two targets are common:
| Target | Formula | Meaning |
|---|---|---|
| BAC | `(BAC - EV) / (BAC - AC)` | Efficiency needed to finish within the original budget |
| EAC | `(BAC - EV) / (EAC - AC)` | Efficiency needed to finish within the current forecast |
The numerator is the budgeted value of the remaining work. The denominator is the money available to perform that work.
TCPI against the original budget
Suppose a project has these status values:
- BAC = $100,000
- EV = $30,000
- AC = $45,000
- EAC = $150,000
The remaining budgeted work is $70,000. If the original BAC remains the target, only $55,000 remains available because $45,000 has already been spent.
\[ TCPI_{BAC} = \frac{100{,}000 - 30{,}000}{100{,}000 - 45{,}000} = \frac{70{,}000}{55{,}000} \approx 1.27 \]
The project must achieve a CPI of about 1.27 for the remaining work. Its current CPI is:
\[ CPI = \frac{EV}{AC} = \frac{30{,}000}{45{,}000} \approx 0.67 \]
Moving from 0.67 to 1.27 requires a major improvement. The original budget is therefore unlikely unless the team can explain a credible change in conditions.
TCPI against the forecast
If management accepts an EAC of $150,000, the remaining work has $105,000 available:
\[ TCPI_{EAC} = \frac{100{,}000 - 30{,}000}{150{,}000 - 45{,}000} = \frac{70{,}000}{105{,}000} \approx 0.67 \]
This target requires roughly the same efficiency as the current CPI. It is more realistic under the assumption that current cost performance continues.
def tcpi(bac, ev, ac, target):
remaining_value = bac - ev
remaining_budget = target - ac
if remaining_budget <= 0:
raise ValueError("The target leaves no positive budget for remaining work")
return remaining_value / remaining_budget
bac, ev, ac = 100_000, 30_000, 45_000
print(f"TCPI to BAC: {tcpi(bac, ev, ac, bac):.2f}")
print(f"TCPI to EAC: {tcpi(bac, ev, ac, 150_000):.2f}")How to judge the result
- If TCPI is close to the current CPI, the target may be achievable without a major change.
- If TCPI is much higher, investigate scope, estimates, productivity, and remaining risks.
- If the denominator is zero or negative, the target is mathematically unavailable or already exceeded.
- TCPI is an indicator, not a promise. It does not prove that the remaining work can be completed at the required efficiency.
Exercise
A project has BAC = $80,000, EV = $20,000, and AC = $30,000. What is the TCPI to BAC, and what does it mean?
Show answer
TCPI = (80,000 - 20,000) / (80,000 - 30,000) = 60,000 / 50,000 = 1.20. The remaining work must achieve a CPI of 1.20 to finish within the original budget.