Why SV and SPI Mislead Late in a Project, and Earned Schedule
Prerequisites and the basic limitation
Assume you know the work breakdown structure, the performance measurement baseline, planned value (PV), earned value (EV), and actual cost (AC). This chapter focuses on schedule interpretation rather than cost control.
Schedule variance (SV) and the schedule performance index (SPI) compare the budgeted value of completed work with the budgeted value that was planned by a status date:
- SV = EV − PV
- SPI = EV ÷ PV
A negative SV means less budgeted work is complete than planned. An SPI below 1.00 means progress is slower than planned.
These measures use money as a proxy for time. That works during much of the project, but it creates a serious problem near completion.
Why traditional schedule measures recover to zero
At project completion, all baseline work is complete. Therefore, EV equals the budget at completion (BAC), and PV also equals BAC:
- SV = BAC − BAC = 0
- SPI = BAC ÷ BAC = 1.00
This happens even if the project finished months late. The measures describe how much budgeted work was completed, not when the work was completed.
For example, a project planned to finish in month 12 might complete all its work in month 15. At month 15, EV and PV both equal the full budget. Traditional SV reports zero schedule variance, and SPI reports perfect schedule efficiency. The late finish has disappeared from the metric.
A cumulative S-curve makes this limitation easier to see:
Earned schedule measures time directly
Earned schedule (ES) translates the current EV into the point on the planned schedule where that amount of work should have been earned. It answers this question:
> On the baseline calendar, when was the current amount of earned value supposed to be reached?
Suppose the status date is month 8. The baseline shows PV of 55,000 at month 6 and 70,000 at month 7. If EV is 60,000, the project has earned the value planned for partway through month 6 and month 7:
ES = 6 + (60,000 − 55,000) ÷ (70,000 − 55,000) ES = 6.33 months
The time-based schedule variance is:
SV(t) = ES − actual time SV(t) = 6.33 − 8 = −1.67 months
The time-based schedule performance index is:
SPI(t) = ES ÷ actual time SPI(t) = 6.33 ÷ 8 = 0.79
Unlike traditional SV and SPI, earned schedule remains meaningful at completion. If the project finishes in month 15 against a planned month-12 finish, ES remains 12 months, so SV(t) is −3 months and SPI(t) is 0.80.
Applying earned schedule carefully
Use the baseline’s cumulative PV curve, not evenly spaced assumptions. Interpolate between adjacent periods when EV falls between two PV values. Also record the actual status date or elapsed project time consistently.
Earned schedule is a schedule indicator. It does not replace milestone analysis, critical-path review, or an updated forecast. A project can have an acceptable earned schedule while a key regulatory milestone remains at risk.
Exercise
A project is planned to finish in month 10 but actually finishes in month 12. What do traditional SV and SPI report at completion, and what does earned schedule report?
Show answer
Traditional SV is zero and SPI is 1.00 because EV and PV both equal BAC. Earned schedule is 10 months, so time-based schedule variance is −2 months and time-based SPI is 10 ÷ 12, or about 0.83.