Sub topic 13
Forecasting the Estimate at Completion
Assume you know basic project vocabulary, work breakdown structures, planned value (PV), earned value (EV), actual cost (AC), and the cost performance index (CPI). This chapter uses those values to forecast the project’s final cost.
What estimate at completion means
The estimate at completion (EAC) is the forecasted total cost of the project when all planned work is finished. It combines:
- AC: money already spent.
- ETC: the estimated cost of the remaining work.
- EAC: AC plus ETC.
The simplest relationship is:
EAC = AC + ETC
The correct ETC depends on what you believe will happen during the remaining work. EVM provides several formulas because project conditions differ.
Choose a formula based on the situation
| Situation | Formula | Main assumption |
|---|---|---|
| Current cost efficiency continues | `EAC = BAC / CPI` | Future work will have the same cost efficiency as completed work |
| Past variance was unusual | `EAC = AC + (BAC - EV)` | Remaining work will meet its original budget |
| Cost and schedule affect remaining cost | `EAC = AC + (BAC - EV) / (CPI × SPI)` | Both cost and schedule inefficiency will continue |
| A fresh estimate is available | `EAC = AC + bottom-up ETC` | The team has re-estimated all remaining work |
Here, BAC is the budget at completion. The quantity BAC - EV is the budgeted value of work that remains.
Worked forecast
Suppose a project has these status values:
- BAC = 100,000
- PV = 40,000
- EV = 30,000
- AC = 45,000
The cost performance index is:
CPI = EV / AC = 30,000 / 45,000 = 0.67
If the current cost efficiency continues:
EAC = BAC / CPI = 100,000 / 0.67 ≈ 150,000
This forecast says the project may finish about 50,000 over its original budget.
If the current overrun was caused by a one-time event, use:
EAC = AC + (BAC - EV)
EAC = 45,000 + (100,000 - 30,000) = 115,000
If schedule delays will also increase the cost of remaining work, use:
EAC = AC + (BAC - EV) / (CPI × SPI)
With SPI = EV / PV = 0.75, this gives an EAC of about 170,000.
bac, pv, ev, ac = 100000, 40000, 30000, 45000
cpi = ev / ac
spi = ev / pv
eac_typical = bac / cpi
eac_one_time = ac + (bac - ev)
eac_cost_and_schedule = ac + (bac - ev) / (cpi * spi)
print(f"Current CPI continues: {eac_typical:,.0f}")
print(f"Past overrun was one-time: {eac_one_time:,.0f}")
print(f"Cost and schedule effects continue: {eac_cost_and_schedule:,.0f}")Interpret the forecast, not just the number
The formulas are conditional forecasts. They do not discover the future automatically. Ask:
- Was the cost variance caused by a recurring process problem?
- Was it caused by a one-time purchase or incident?
- Are schedule delays creating overtime, rework, or escalation?
- Has the scope changed since the baseline?
- Are AC and EV complete and recorded against the same work?
A bottom-up ETC is often better when circumstances have changed. The team estimates each remaining work package, adds those estimates, and calculates EAC = AC + ETC. This method takes more effort but can reflect known corrective actions or changed conditions.
Exercise
BAC is 80,000, EV is 24,000, and AC is 30,000. If the current CPI continues, what is the EAC?
Show answer
CPI is 24,000 / 30,000 = 0.80. EAC is 80,000 / 0.80 = 100,000.