Sub topic 4
Planned Value: The Budgeted Cost of Work Scheduled
This chapter assumes you know basic project management terms such as scope, task, milestone, budget, and work breakdown structure (WBS). You should also be comfortable with percentages and simple spreadsheet arithmetic.
What planned value answers
Planned value (PV) is the budgeted cost of the work that the project plan says should be complete by a specific date. It answers this question:
> According to the approved plan, how much budgeted work should we have completed by now?
PV does not describe what the team actually completed or what the work actually cost. Those are measured separately. PV is a time-based value taken from the performance measurement baseline, which is the approved plan for scope, schedule, and budget.
The unit is usually money, such as dollars or euros. However, PV is a measure of budgeted work, not a cash payment.
Time-phasing the budget
A project budget becomes useful for performance measurement when it is distributed across time. This process is called time-phasing. Each work package receives a budget and a planned period in which the work will occur.
For example, a project may have this baseline:
| Work package | Total budget | Planned timing |
|---|---|---|
| Design | $20,000 | Month 1 |
| Build | $50,000 | Months 2–3 |
| Test | $30,000 | Month 4 |
The total budget is the budget at completion (BAC):
\[ BAC = 20{,}000 + 50{,}000 + 30{,}000 = 100{,}000 \]
If the status date is at the end of Month 2, the plan may say that all design and half of the build work should be complete. The planned value is therefore:
\[ PV = 20{,}000 + (0.5 \times 50{,}000) = 45{,}000 \]
The $45,000 does not claim that the team completed $45,000 of work. It says that the approved schedule assigned $45,000 of budgeted work to the period ending at the status date.
Cumulative and period PV
Project controls often show both period PV and cumulative PV.
- Period PV is the budgeted work planned for one reporting period.
- Cumulative PV is the total planned value from the project start through the status date.
Cumulative PV should rise over time until it reaches BAC at project completion. A plan with no work scheduled in a period has zero period PV, but its cumulative PV remains unchanged.
# Planned value by month for three work packages
monthly_pv = {
"Month 1": 20_000, # Design
"Month 2": 25_000, # First half of Build
"Month 3": 25_000, # Second half of Build
"Month 4": 30_000, # Test
}
cumulative_pv = 0
for month, period_pv in monthly_pv.items():
cumulative_pv += period_pv
print(f"{month}: period PV=${period_pv:,.0f}, "
f"cumulative PV=${cumulative_pv:,.0f}")Reading PV on a project curve
A cumulative PV curve is often called the planned-value line on an S-curve. The curve may be flat early in the project, rise rapidly during execution, and flatten near completion. The shape reflects the timing of the budget, not necessarily the amount of money paid in each period.
At each status date, PV provides the schedule-side reference for later comparisons. Earned value compares the budgeted worth of work actually completed with PV. Actual cost compares the real spending with the budgeted worth of completed work. Those comparisons only make sense when the PV baseline is current, detailed, and consistently time-phased.
Exercise
A project has a $40,000 design package planned entirely for Month 1 and a $60,000 build package planned evenly across Months 2–4. What is the cumulative PV at the end of Month 3?
Show answer
$80,000. The plan includes all $40,000 of design plus two-thirds of the $60,000 build budget: $40,000 + (2/3 × $60,000) = $80,000.