Sub topic 12
Interpreting Status: The Four Common Cases
Assume you already know how a work breakdown structure, performance measurement baseline, planned value (PV), earned value (EV), and actual cost (AC) are recorded. This chapter uses the standard formulas:
- Schedule variance:
SV = EV - PV - Cost variance:
CV = EV - AC - Schedule performance index:
SPI = EV / PV - Cost performance index:
CPI = EV / AC
A positive variance is favorable. A negative variance is unfavorable. An index above 1.00 is favorable, while an index below 1.00 is unfavorable.
The four status combinations
Schedule status comes from comparing EV with PV. Cost status comes from comparing EV with AC. Combining those two results gives four common cases.
| Schedule status | Cost status | Meaning |
|---|---|---|
| Ahead of schedule | Under budget | More budgeted work is complete than planned, and it cost less than its budgeted value |
| Ahead of schedule | Over budget | More work is complete than planned, but the project paid too much for it |
| Behind schedule | Under budget | Less work is complete than planned, but completed work cost less than its budgeted value |
| Behind schedule | Over budget | Less work is complete than planned, and completed work cost more than its budgeted value |
The first case is usually favorable, but check whether early progress came from completing inexpensive tasks while expensive work remains. The second case may indicate that overtime, extra staff, or rushed procurement created schedule gains at a high cost. The third case may reflect delayed work, postponed spending, or a temporary lack of resources. The fourth case needs the fastest investigation because both dimensions are unfavorable.
A worked status example
Suppose a project has these results at the status date:
- PV: $40,000
- EV: $30,000
- AC: $45,000
Then:
SV = 30,000 - 40,000 = -10,000CV = 30,000 - 45,000 = -15,000SPI = 30,000 / 40,000 = 0.75CPI = 30,000 / 45,000 = 0.67
The project is behind schedule because only $30,000 of budgeted work is complete against $40,000 planned. It is also over budget because that completed work cost $45,000. An SPI of 0.75 means the project achieved about 75% of the planned progress rate. A CPI of 0.67 means each dollar spent produced about 67 cents of budgeted work.
Reading the pattern over time
One status point is less useful than a trend. Plot cumulative PV, EV, and AC at regular reporting dates.
Look for persistent movement rather than reacting to a small change. Define warning thresholds before reporting begins, such as SPI or CPI below 0.90. Then investigate the cause at the control-account level. Ask whether the problem comes from incorrect estimates, late work, productivity, supplier costs, or missing actual-cost data.
Exercise
A project has PV of $80,000, EV of $72,000, and AC of $68,000. Which of the four cases applies?
Show answer
It is behind schedule and under budget. SV is -$8,000, CV is $4,000, SPI is 0.90, and CPI is about 1.06.