Why Earned Value: Measuring Progress in Money Terms
Prerequisites
This chapter assumes that you know basic project management terms such as scope, schedule, budget, milestone, and work breakdown structure (WBS). You should also be comfortable with percentages, ratios, and simple arithmetic.
The problem with reporting progress
A status report that says “the project is 50% complete” leaves important questions unanswered:
- Was 50% of the planned work supposed to be complete by now?
- Is the completed work worth half of the project budget?
- How much did the completed work actually cost?
Earned value management (EVM) answers these questions with three related measures. Each measure uses money as a common unit, even when the work itself consists of different tasks.
| Measure | Question it answers |
|---|---|
| Planned value (PV) | How much budgeted work should be complete by the status date? |
| Earned value (EV) | How much budgeted work is actually complete? |
| Actual cost (AC) | How much did the completed work actually cost? |
The values are cumulative through a selected status date, such as the end of a reporting week.
The three values
Planned value is the authorized budget for work scheduled to be completed by a specific date. It comes from the approved, time-phased plan. “Time-phased” means that the budget is distributed across the dates when the work is planned to occur.
Earned value is the budget assigned to the work that has actually been completed. It does not mean the amount invoiced or the amount paid. It measures the budgeted worth of completed work.
Actual cost is the recorded cost of the work performed. Depending on the organization, it may include labor, materials, equipment, subcontractors, and allocated overhead.
Consider a project with a total budget of $100,000. By the end of week four, the plan says that $40,000 of work should be complete. The team has completed work whose approved budget is $30,000, and the accounting records show that the work cost $45,000.
- PV = $40,000
- EV = $30,000
- AC = $45,000
The project is behind the planned amount of work because EV is lower than PV. It is also spending more than planned for the work completed because AC is higher than EV.
Why use money as the common unit?
A project may contain design, construction, testing, and training. Percent complete alone cannot compare these activities reliably. Completing 50% of a small task is not equivalent to completing 50% of a high-value task.
EVM weights progress by the approved budget of each work package. If a $20,000 work package is fully complete, it contributes $20,000 of EV. If a $50,000 work package is 40% complete under an approved measurement rule, it contributes $20,000 of EV.
This approach connects scope, schedule, and cost. It also creates a basis for forecasting. However, money is only a measurement unit. EVM does not prove that the delivered work meets quality requirements, satisfies the customer, or creates business value.
Exercise
A project has PV of $60,000, EV of $50,000, and AC of $55,000 at the status date. What does each comparison indicate?
Show answer
EV is $10,000 below PV, so less budgeted work is complete than planned. AC is $5,000 above EV, so the completed work cost more than its approved budget.