SPI and CPI: Efficiency as a Ratio
This chapter assumes you know the basics of a work breakdown structure, a time-phased budget, and the three EVM measures: planned value (PV), earned value (EV), and actual cost (AC). All three values must use the same status date and comparable budget units.
What the ratios measure
A variance gives a difference in money. An index gives a ratio that is easier to compare across work packages or reporting periods.
The schedule performance index (SPI) answers:
> How much budgeted work did the project complete compared with how much work it planned to complete?
The formula is:
SPI = EV / PV
The cost performance index (CPI) answers:
> How much budgeted work did the project complete for each unit of actual cost?
The formula is:
CPI = EV / AC
Because both formulas divide comparable values, the result has no currency unit.
| Index | Formula | Meaning |
|---|---|---|
| SPI | EV / PV | Schedule efficiency |
| CPI | EV / AC | Cost efficiency |
| 1.00 | Equal numerator and denominator | Performance matches the baseline |
| Greater than 1.00 | EV exceeds the comparison value | Favorable performance |
| Less than 1.00 | EV is below the comparison value | Unfavorable performance |
An SPI of 0.80 means the project has earned 80% of the budgeted work it planned to earn by the status date. A CPI of 0.80 means the project has earned 80 cents of budgeted work for every dollar spent.
Worked example
Suppose the status report contains these values:
- PV = 40,000
- EV = 30,000
- AC = 45,000
Then:
- SPI = 30,000 / 40,000 = 0.75
- CPI = 30,000 / 45,000 = 0.67
The project is completing work more slowly than planned. It is also spending more than the budgeted value of the work completed.
pv = 40_000
ev = 30_000
ac = 45_000
spi = ev / pv
cpi = ev / ac
print(f"SPI: {spi:.2f}")
print(f"CPI: {cpi:.2f}")The ratios do not explain the cause. An SPI below 1.00 might result from a late approval, a missing dependency, or an unrealistic schedule. A CPI below 1.00 might result from rework, inaccurate estimates, or costs posted late. Investigate the work package data before choosing corrective action.
Interpreting trends and thresholds
A single index is a signal, not a complete diagnosis. Compare the current SPI and CPI with:
- The approved performance measurement baseline
- Previous reporting periods
- Control-account and work-package results
- Agreed management thresholds
For example, a CPI that improves from 0.70 to 0.90 shows better efficiency, but the project is still under the 1.00 baseline target. A stable CPI of 0.95 may be acceptable for one project and unacceptable for another. The project’s control thresholds and forecast assumptions determine the response.
A visual reading of the ratios
Common errors
Do not calculate SPI from calendar dates alone. SPI uses budgeted work, so progress must be measured with an approved earning rule. Do not treat CPI as a profit margin. CPI describes performance against the project budget, not revenue or business value. Also, do not compare ratios from projects with different definitions of completion without checking their measurement rules.
Exercise
A project has PV = 60,000, EV = 54,000, and AC = 48,000. What are SPI and CPI, and what do they indicate?
Show answer
SPI = 54,000 / 60,000 = 0.90, so progress is behind the baseline plan. CPI = 54,000 / 48,000 = 1.125, or about 1.13, so cost efficiency is favorable: the project earns about $1.13 of budgeted work per dollar spent.