Sub topic 6
Deciding How Much Work Counts as Done
Assume you know how to read a work breakdown structure, identify a work package, and use a time-phased budget. The difficult part of earned value management is often not the arithmetic. It is deciding when a work package has earned its budgeted value.
Earned value (EV) is the budgeted value of completed work. It is not the amount paid and not the percentage of calendar time that has passed. Each work package needs a progress rule agreed before work begins.
Choose a progress measurement rule
Common rules include:
| Method | How EV is earned | Best use |
|---|---|---|
| 0/100 | Earns nothing until the package is complete | Short, clearly verifiable tasks |
| 50/50 | Earns 50% at start and 50% at completion | Short tasks where partial progress is hard to measure |
| Weighted milestones | Earns fixed portions when defined milestones are accepted | Design, construction, and staged deliverables |
| Percent complete | Earns the budget multiplied by an approved completion percentage | Long tasks with measurable ongoing output |
The rule should measure delivered work, not effort alone. A team spending 80% of its hours does not prove that 80% of the deliverable is complete.
Fixed-formula methods
A fixed-formula method gives a package a predetermined amount of EV at specific events.
With the 50/50 rule, a $10,000 package earns $5,000 when work starts and the remaining $5,000 when it finishes. The rule is simple, but it can overstate progress if a package starts long before it produces useful output.
The 0/100 rule avoids that early credit. The same $10,000 package earns $0 until acceptance, then earns $10,000. This is conservative and works well for small tasks with a clear completion test.
Weighted milestones
Weighted milestones divide a package into observable stages. Suppose a $30,000 design package has these approved weights:
- Requirements approved: 20%
- Detailed design complete: 50%
- Design review accepted: 30%
If the first two milestones are complete, EV is:
$30,000 × (0.20 + 0.50) = $21,000
Milestones must describe outputs or decisions that can be checked. “The team worked on the design” is not a milestone.
Percent-complete reporting
For a package with a $20,000 budget and an approved completion estimate of 40%:
EV = $20,000 × 0.40 = $8,000
Use objective evidence where possible, such as tested features, accepted drawings, or completed units. Avoid averaging several subjective opinions without defining how the percentage is determined. Also record the status date so that the same progress is not claimed in multiple reporting periods.
Exercise
A $40,000 work package uses weighted milestones of 25%, 35%, and 40%. The first two milestones are accepted. What is its earned value?
Show answer
$40,000 × (0.25 + 0.35) = $24,000.