Sub topic 4
Writing Measurable Objectives
This chapter assumes you know the basic project roles (sponsor, project manager, team member) and that you have already written, or at least understand, the business justification for your project. Objectives come directly after the justification in the charter. They turn the reason for the project into statements the team can be held to.
What an objective is
An objective is a statement of a result the project must achieve. It is not a task, and it is not a deliverable. A deliverable is something you hand over, such as a migrated database. An objective says what must be true because you handed it over, such as "support staff resolve tickets faster."
The business justification explains why the project exists. Objectives say what changed outcome will count as the justification being met. Later sections (scope, deliverables, success criteria) depend on them. If an objective is vague, every one of those sections inherits the vagueness.
Why vague objectives cause trouble
"Improve customer support response times" sounds reasonable. It fails in practice for four reasons:
- Nobody can say how much improvement is enough, so the sponsor and the team may disagree at the end.
- No baseline is stated, so no one can tell whether a change happened.
- No deadline is stated, so "improve" can continue indefinitely.
- No limit is stated, so the team may reach the goal by spending money the sponsor never agreed to.
A measurable objective removes these gaps. It names a metric, a baseline, a target, a deadline and a limit.
Vague: Improve customer support response times.
Measurable: Reduce the median first-response time for support tickets from 8 hours to 2 hours by 30 June, without increasing headcount.The measurable version contains all five parts:
| Part | In the example |
|---|---|
| Metric | Median first-response time for support tickets |
| Baseline | 8 hours |
| Target | 2 hours |
| Deadline | 30 June |
| Limit | No increase in headcount |
The SMART check
SMART is a common checklist for objectives. It stands for Specific, Measurable, Achievable, Relevant and Time-bound. Use it as a review tool after drafting, not as a template to fill in.
- Specific: one clear outcome, with a named metric.
- Measurable: someone can obtain the number, from a named source.
- Achievable: the target is reachable with the stated budget, time and people.
- Relevant: the objective supports the business justification.
- Time-bound: a date or period is attached.
The checklist has one weakness. An objective can pass every letter and still be worthless if the metric is wrong. The next section covers that.
Choosing the metric
The metric is the most consequential decision in an objective. Three questions help.
- Does the metric reflect the outcome the sponsor cares about? Ticket volume closed per day may rise while customers are less satisfied.
- Can the data actually be collected? If your ticket system does not record first-response time, the objective cannot be checked without extra work.
- Can the team game the metric? If you measure "tickets closed," people may close tickets without solving them.
Prefer a metric that already exists in a system the sponsor trusts. If you must create a new measurement, add the work to create it to the project, and say so in the charter.
Median, mean and percentile
When a metric is a time or a cost, state which statistic you mean. The mean is pulled up by a few extreme cases. The median is the middle value and ignores them. A percentile such as the 90th shows how bad the slow cases are. In the example, "median" means half of tickets get a first response within 2 hours, but says nothing about the slowest tickets. If those matter, add a second objective, for example "90th percentile first-response time under 8 hours."
Leading and lagging measures
A lagging measure shows the final result, such as customer retention after a year. A leading measure predicts it earlier, such as response time in the first month. Charter objectives are often lagging, but the project may end before they can be observed. In that case, choose a leading measure that can be read before the project closes, and name the lagging one as a follow-up the sponsor will track after closure.
Baseline and target
A baseline is the current value of the metric. Without it, "reduce by 50%" has no meaning. Record where the baseline came from and the period it covers, for example "median across January to March, from the ticketing system."
If you do not have a baseline when writing the charter, do not invent one. Write a placeholder objective and make measuring the baseline an early activity:
Objective 2 (target to be confirmed): Reduce the median first-response time for support tickets by at least 50% from the baseline, by 30 June. The baseline will be measured and agreed with the sponsor by 15 February.A target should be grounded in something: a benchmark, a contract requirement, a past project, or the sponsor's stated need. A target chosen because it sounds good invites argument later.
The limit
The limit is the constraint that stops the objective from being achieved at any cost. It is often a budget, a headcount, a quality floor or a regulation. In the example, "without increasing headcount" rules out hiring more staff as the solution. Without such a limit, a team could meet the target in ways the sponsor would reject.
How many objectives
Keep the count small. Three to five objectives is typical for a project that needs a charter. More than that usually means some items are tasks or deliverables in disguise, or that the project is really several projects. When objectives compete, for example faster delivery and lower cost, say which has priority. Otherwise the team will have to guess when they conflict.
From objective to the rest of the charter
Scope is tested against objectives: if work does not help meet an objective, it is a candidate for the out-of-scope list. Deliverables are tested the same way: each should contribute to at least one objective. Success criteria then describe how the objectives will be judged as met.
Worked example
A company plans to move its customer database to a new platform. A first draft of objectives reads:
- Migrate the database.
- Train staff.
- Make the system better.
The first two are tasks. The third cannot be checked. A revised version:
- Reduce the median time to retrieve a customer record from 12 seconds to under 3 seconds by 30 September, measured in the support console's monthly report.
- Reach at least 90% of support staff passing the new-tool assessment by 31 August.
- Complete the migration with no loss of active customer records, verified by a record-count reconciliation, within the approved budget.
Each objective now has a metric and a way to check it. The third uses a limit (no loss, approved budget) instead of an improvement figure, which is appropriate for an outcome that must be preserved rather than improved.
Common errors
- Writing activities ("Implement a new CRM") instead of outcomes. Ask what will be different once it is done.
- Stating a target without a baseline or a deadline.
- Using a metric nobody collects.
- Setting a target the budget cannot support.
- Listing objectives that conflict, with no priority.
- Using words like "improve," "enhance" or "better" with no number.
Exercises
Exercise
Rewrite this objective so it is measurable: "Make the onboarding process faster for new employees." Assume the current process takes 10 working days and the sponsor wants it done by the end of the year with no new hires in HR. State which parts you have supplied and which you would need to confirm.
Show answer
Example: "Reduce the average time from a new employee's start date to full system access from 10 working days to 3 working days by 31 December, without adding HR staff." Parts supplied: metric (time to full system access), baseline (10 days, given), target (3 days), deadline (31 December, from the sponsor), limit (no new HR hires). To confirm: the target of 3 days, since it was not given and needs a grounding such as a benchmark or the sponsor's need, and how and where the time is measured, since the data source was not stated. Whether "average" or "median" is intended should also be agreed.
Exercise
A project team proposes the objective "Close 500 support tickets per week." Give two reasons this metric might not reflect the sponsor's real goal of better customer service, and suggest a better one.
Show answer
First, the team can close tickets without solving the customer's problem, so the number rises while satisfaction falls. Second, the volume of incoming tickets varies, so closing 500 may be easy or hard depending on demand and says nothing about quality. A better metric is one tied to the outcome, such as "Raise the share of tickets resolved at first contact from 60% to 80% by 30 June" or a customer satisfaction score from a post-ticket survey, with a baseline and deadline.