Sub topic 9
Assigning Roles and Granting Authority
This chapter covers section 6 of the charter, "Project Manager Authority", and the roles that go with it. It assumes you know the common project roles (sponsor, project manager, team member) and have already identified stakeholders. You will learn how to assign roles so that every decision has an owner, and how to state what the project manager can decide without asking anyone.
Why roles and authority belong in the charter
A charter authorizes a project. Authorization is empty if nobody knows who may act on it. Most project conflicts about decisions trace back to one of three gaps:
- Nobody was named as responsible for a piece of work.
- Two people believed they owned the same decision.
- The project manager was held accountable for results but had no power to change the things that produce them.
The charter closes these gaps early, while the sponsor is still engaged and before any disagreement exists. A written statement of authority is also what you point to later when someone challenges a decision.
Roles versus people
A role is a set of responsibilities. A person fills it. Write the charter around roles first and then attach names. This keeps the charter useful when someone changes jobs, and it exposes roles with no one assigned.
| Role | Typical responsibility in the charter |
|---|---|
| Sponsor | Funds the project, owns the business case, removes obstacles outside the project manager's reach, approves the charter |
| Project manager | Plans and runs the project day to day, reports progress, escalates issues |
| Steering committee (if used) | Reviews progress at set points, decides on changes above the project manager's limits |
| Team members | Produce deliverables, estimate their own work, report problems early |
| Subject matter experts | Advise on a specific area, such as legal, security or finance |
| Customer or user representative | Confirms that deliverables meet real needs |
Not every project needs every role. A small project may have one sponsor, one project manager and four team members. What matters is that each responsibility the project needs has an owner.
Responsible, accountable and the difference
Two words are often mixed up.
- Responsible means doing the work.
- Accountable means answering for the result and having the final say.
Several people can be responsible for a task. Only one person should be accountable for it. If two people are accountable, in practice nobody is.
A RACI matrix records this. Its four letters are Responsible, Accountable, Consulted (asked for input before a decision) and Informed (told after a decision). A charter should hold only a small, high-level version, covering the main deliverables and decisions. The detailed matrix belongs in the project plan.
| Decision or deliverable | Sponsor | Project manager | Team lead | Finance |
|---|---|---|---|---|
| Approve charter | A | R | I | C |
| Select vendor | A | R | C | C |
| Accept database migration | I | A | R | I |
| Release held budget | A | C | I | R |
Check each row for exactly one A. Check each column for a person who is overloaded with R and A entries, since that person is a bottleneck.
Granting project manager authority
The authority statement is the part of the charter most often left vague. A sentence such as "The project manager is authorized to lead the project" does not settle any real question. Authority becomes useful when it names decision areas and limits.
Cover at least these areas:
- Resources. Can the project manager request, assign and release team members? Can they negotiate with functional managers for people's time?
- Budget. Can they move money between budget lines? Up to what amount or percentage without approval?
- Schedule. Can they move a task date? Can they move a milestone date? By how many days?
- Scope. Can they accept or reject a request for extra work? Who decides if the request is large?
- Procurement. Can they sign purchase orders? Up to what value?
- Escalation. Whom do they go to when they are blocked, and how quickly must that person respond?
Express limits as numbers or named approvers wherever you can. "Reallocate up to 5% of the budget between lines without approval; larger changes go to the sponsor" can be checked. "Reasonable budget flexibility" cannot.
Example authority section
## 6. Project Manager Authority
Dana Okafor is appointed project manager and may, without further approval:
- Assign and reassign tasks among the core team.
- Move budget between lines up to 5% of the total budget.
- Sign purchase orders up to $10,000.
- Move task dates that do not affect a milestone.
- Decline change requests estimated at under 2 days of effort.
Dana must obtain the sponsor's approval to:
- Change a milestone date by more than 5 working days.
- Add or remove a deliverable.
- Spend above the approved budget.
- Add external contractors.
If Dana and a functional manager disagree about team availability,
the issue is escalated to the sponsor, who responds within 3 working days.This example shows the pattern: a short list of what the project manager can do alone, a short list of what needs approval, and a named path for disagreements.
Authority must match accountability
If the project manager is accountable for delivery but cannot choose the people, spend the money or change the plan, the project is set up to fail. Compare what the charter holds the project manager responsible for with what it lets them decide.
| Accountable for | Needs at least this authority |
|---|---|
| Delivering on time | Authority to reorder tasks and request additional people |
| Staying within budget | Authority to reallocate within a limit and to refuse unfunded work |
| Quality of deliverables | Authority to reject work that fails acceptance criteria |
| Team performance | A voice in team selection and in feedback to line managers |
Many project managers work in a matrix organization, where team members report to a functional manager and not to the project manager. Here the charter does the work that a reporting line would otherwise do. It should state how much of each person's time is committed, who sets their priorities during the project, and who contributes to their performance review.
How decision flow works
Escalation should be a clear path, not a surprise. The diagram shows one typical flow for a decision that the project manager may or may not be allowed to make.
Notice that each branch ends with recording and informing. A decision nobody can find later is nearly as bad as no decision.
Edge cases and common problems
- Sponsor is too senior or too busy. A sponsor who cannot meet for weeks cannot unblock the project. Name a delegate and a maximum response time.
- Shared sponsorship. Two sponsors from different departments often give conflicting direction. Name one sponsor with final say, and make the other a key stakeholder or a steering committee member.
- Project manager appointed after the charter is drafted. Name the role and say who will appoint the person. Many organizations prefer to name the project manager before approval so that the person can help shape the charter.
- Authority silently exceeded. If a project manager routinely makes decisions above their limits and the sponsor tolerates it, the written limits stop meaning anything. Either enforce them or update the charter.
- Authority granted but not communicated. Functional managers who never saw the charter may ignore the project manager's requests. Send them the approved charter.
- Role overlap. A technical lead and a project manager may both believe they own schedule decisions. State who decides what, for example "the technical lead decides how to build it; the project manager decides when and with whom."
Review checklist
Before sending the roles and authority section for approval, check that:
- Every role in the stakeholder list has either a defined responsibility or is intentionally left out.
- Each major deliverable and decision has exactly one accountable person.
- Authority limits for the project manager use numbers or named approvers.
- The escalation path names people and response times.
- The sponsor has agreed to the limits, since they are the person giving up control.
- Functional managers who lend people to the project have seen the commitments in writing.
Exercise
A charter says "The project manager has authority over the budget." The project manager later wants to move $8,000 from training to equipment, from a total budget of $200,000. The sponsor objects and says the project manager overstepped. What is wrong with the charter, and how would you rewrite the sentence?
Show answer
The sentence gives no limits, so both sides can reasonably claim to be right. A better version sets a threshold and an approver: "The project manager may move up to 5% of the total budget ($10,000) between budget lines without approval. Larger moves require the sponsor's written approval." Under this wording the $8,000 move is within authority, and the dispute is settled by the charter.
Exercise
A RACI row for "Accept final deliverable" shows the sponsor, the project manager and the customer representative all marked A. What problem does this create, and what would you change?
Show answer
Three accountable people means no single person has the final say, so acceptance can stall or be disputed. Choose one accountable person, for example the sponsor or the customer representative, and mark the others as R, C or I. The project manager would normally be R for arranging the acceptance review, and the customer representative would be C.