Sub topic 8
Identifying Stakeholders
What this chapter assumes
You already know the common project roles (sponsor, project manager, team member). You have seen why a charter exists and how to write its purpose, objectives, scope and deliverables. This chapter covers the charter's stakeholder section, which is chapter 8 of 16 in the tutorial and sits between success criteria and the assignment of roles and authority.
What a stakeholder is
A stakeholder is any person, group or organization that can affect the project, is affected by it, or believes it is affected. The third case matters. A team that wrongly fears losing work can still slow a project down.
Stakeholders fall into two broad groups:
- Internal stakeholders work in your organization, such as the sponsor, the team, finance, legal, IT operations and the departments that will use the result.
- External stakeholders sit outside it, such as customers, suppliers, regulators, contractors and the public.
Keep this distinction separate from the project team. The team is the subset of stakeholders who do the work. Most stakeholders never attend a project meeting.
Why the charter lists stakeholders
The charter is written early, when changing direction is cheap. Naming stakeholders then has three effects:
- It exposes missing voices before the scope is fixed. A requirement that nobody owns is usually a requirement nobody asked for.
- It tells the sponsor who must be consulted before approval.
- It gives later disputes a reference. If a department says it was never involved, the charter shows whether it was identified and what role it had.
The charter holds a high-level list. The detailed analysis and communication schedule belong in the stakeholder register and communication plan, which you build after approval.
How to find stakeholders
No single method finds everyone. Combine several.
- Read the business case and objectives. For each objective, ask who benefits, who pays, and who must change behavior.
- Walk through each deliverable. Ask who will build it, review it, approve it, operate it and use it.
- Follow the process. Trace the work the project changes from start to finish and note every team it passes through.
- Check the usual hidden groups: legal, security, procurement, finance, HR, internal audit, and the help desk that will take the calls after launch.
- Ask the sponsor and early stakeholders, "Who else should I talk to?" Repeat until no new names appear.
- Look at past projects of the same kind and see who joined late and why.
Example
The charter's example scope includes migrating the customer database to a new platform and training support staff. Working through it gives this list:
| Stakeholder | Type | Connection to the project |
|---|---|---|
| Director of Customer Operations | Internal | Sponsor, funds the work |
| Support team leads | Internal | Users of the new tools, attend training |
| IT infrastructure team | Internal | Hosts and runs the new platform |
| Information security officer | Internal | Must approve data handling |
| Finance business partner | Internal | Tracks budget |
| Platform vendor | External | Supplies the product and migration support |
| Customers | External | Affected by downtime during migration |
| Data protection regulator | External | Sets rules on customer data |
Notice that the information security officer and the regulator appear only because the team followed the data. Asking only "who is on the project?" would have missed both.
Analyzing stakeholders
A name list does not say how much attention each person needs. A common technique is a power and interest grid. For each stakeholder, judge two things: how much influence they have over the project, and how much the project matters to them.
| Influence | Interest | Typical approach |
|---|---|---|
| High | High | Manage closely. Involve them in decisions. |
| High | Low | Keep satisfied. Brief them on key points and avoid surprises. |
| Low | High | Keep informed. Share progress and ask for feedback. |
| Low | Low | Monitor. Minimal effort, but reassess later. |
Treat the grid as a starting judgment. Positions change. A low-interest regulator becomes high-interest the moment a data incident occurs.
Recording expectations
For each key stakeholder, add one line about what they expect or require. This is where hidden conflicts appear.
## 5. Stakeholders and Roles
| Stakeholder | Role in project | Main expectation |
|-------------|-----------------|------------------|
| Director of Customer Operations | Sponsor | Median first-response time falls to 2 hours by 30 June |
| Support team leads | Users, trainees | Training during quiet hours, no loss of ticket history |
| IT infrastructure team | Platform host | Early notice of capacity needs |
| Information security officer | Approver (data handling) | Review of access controls before migration |
| Customers | Affected party | No loss of service during cut-over |Look for expectations that cannot all be true. If the sponsor wants the migration finished by 30 June and the IT team needs a six-week freeze before that date, you have found a conflict while it is still cheap to resolve. Raise it with the sponsor before approval, and either adjust the charter or record it as a risk.
Common errors
- Listing only the team. This produces a charter that ignores users, approvers and the groups who run the result.
- Using vague groups. "Management" or "the business" cannot be contacted. Name a role or a person, such as "Head of Finance".
- Confusing sponsor and stakeholder. The sponsor is one stakeholder with specific duties. Everyone else is not a sponsor just because they are interested.
- Naming people who have since left or moved. Check that each named person still holds the role.
- Treating the list as finished. New stakeholders appear as the project moves into new phases, so plan to revisit the list.
- Assuming silence means support. A stakeholder who does not respond has not agreed. Record who has been consulted and who has not.
Checking your list
Before moving on, test the stakeholder section with these questions:
- Does every deliverable have at least one person who will use it and one who will accept it?
- Does every objective have someone who cares whether it is met?
- Is each name a role or person that exists today?
- Have the high-influence stakeholders seen their entry and agreed it is accurate?
- Are there conflicting expectations, and has each been resolved or logged as a risk?
The next chapter takes the stakeholders you have named and gives each a defined role, then sets out the project manager's authority.
Exercise
A charter for an office relocation lists these stakeholders: "Project team", "Management" and "Employees". Name two problems with this list and describe how you would improve it.
Show answer
The groups are too vague to contact or hold to account, and the list omits stakeholders who can block the project. Replace "Management" with named roles, such as the Chief Operating Officer (sponsor) and the Head of Facilities. Split "Employees" into groups with different needs, such as staff who will commute farther and staff with accessibility requirements. Add missing groups found by following the deliverables and process: the landlord, the IT team that moves equipment, the building authority that issues occupancy approval, and the movers. Give each a role and a main expectation.
Exercise
A regulator has low interest in your project today but high influence. Which grid quadrant applies, what approach do you take, and what event could change the approach?
Show answer
The quadrant is high influence, low interest, so you keep the regulator satisfied: brief them at key points and avoid surprises. A data breach, a change in the law, or a change to how the project handles regulated data would raise their interest and move them to manage closely.