Getting the Charter Approved
This chapter assumes you have drafted the main sections of a charter: business justification, objectives, scope, deliverables, success criteria, stakeholders, roles, milestones, budget, assumptions, constraints and risks. It also assumes you know the usual project roles, such as sponsor, project manager and team member. Here you will learn how a charter moves from draft to approved, who signs it, and what approval does and does not mean.
Why approval matters
A charter that nobody has signed is a proposal. A signed charter is an authorization. Approval does three things:
- It commits the sponsor to provide the funding, people and decisions the charter lists.
- It gives the project manager the authority written in the roles section.
- It creates a fixed reference. When someone later asks for extra work, the team can point to the approved scope instead of relying on memory.
Approval also marks a change in how the project is run. Before approval, anyone can reshape the draft. After approval, changes follow the change process described in the next chapter.
Who approves
The approver is the person who holds the authority and the money the project needs. In most organizations this is the sponsor, the executive who pays for the project and is accountable for its business result. Some organizations route charters to a steering committee or portfolio board, especially when the budget is large or the project crosses departments.
Choose approvers by asking what the charter commits:
| What the charter commits | Who must agree |
|---|---|
| Money | Sponsor or budget holder |
| People from other teams | The managers of those people |
| Authority over decisions | Sponsor, or the governing board |
| Changes to a shared system | The owner of that system |
| Compliance or legal obligations | Legal or compliance representative |
A common failure is a charter signed by the sponsor alone, which promises the time of staff whose managers never agreed. Those managers later refuse to release people, and the project stalls with a valid signature on file. Resource commitments need a signature from whoever controls the resource.
The project manager normally signs too, as a sign that they accept the role and the terms. In the skeleton charter, this is the approval table at the end:
## 11. Approval
| Name | Role | Signature | Date |
|------|------|-----------|------|
| A. Rivera | Sponsor | | |
| J. Chen | Project Manager | | |
| M. Okafor | Head of Support (resource owner) | | |Keep the list short. Each extra signer adds delay, and a signature from someone with no stake in the project adds nothing.
The approval process
Approval is a sequence, not a single event. Most of the effort happens before anyone signs.
1. Pre-review informally
Do not send a charter cold to the sponsor. Walk the main points through with the sponsor and with the people most affected, one at a time. Ask each of them two questions: "Is anything here wrong?" and "Is anything missing?" Objections are cheap to fix in a conversation and expensive to fix in a formal meeting. By the time the document is formally submitted, nobody who matters should be surprised by it.
2. Check readiness
Before submitting, read the charter as the approver would. Confirm that:
- The objectives are measurable, with a baseline, target, deadline and limit.
- The scope lists exclusions as well as inclusions.
- Every deliverable can be tied to at least one success criterion.
- The budget and milestone figures are labeled as estimates, with a stated level of confidence.
- The authority granted to the project manager is stated in concrete terms, such as a spending limit or the right to assign team tasks.
3. Submit and review
Submit the charter through the channel your organization uses: a review meeting, a circulated document with a response deadline, or a workflow tool. Give reviewers a date by which silence counts as no objection only if your governance rules say so. Otherwise, silence is not approval. Chase answers until you have an explicit yes or an explicit list of concerns.
4. Decide
There are three possible outcomes:
- Approve. The approvers sign. The charter becomes the baseline.
- Approve with conditions. The approvers sign on the condition that specific items are resolved, such as confirming a vendor quote. Write the conditions and their due dates into the charter or an attached note, and name an owner for each.
- Revise or reject. The charter goes back for rework, or the project is declined. Record the reason. A rejection is a legitimate result of governance: the organization decided the project was not worth its cost.
5. Baseline and distribute
After signing, store the approved version in a known location, mark it with a version number and date, and send it to everyone named in it. A baseline is the approved version that later changes are measured against. If people keep working from an older draft, approval has achieved little.
What approval does not mean
Approval of a charter authorizes the project to start and plan in detail. It does not mean that every number is final. The budget and dates in a charter are high-level estimates made with limited information. Many organizations treat charter approval as permission to begin planning, followed by a second approval of the detailed plan and budget.
State this in the charter. A line such as "Budget estimate accurate to within -10% / +25%; to be confirmed in the project plan" prevents the sponsor from reading the figure as a fixed promise. It also protects the project manager from being held to a number that was never meant to be exact.
Edge cases
The sponsor is unavailable. Do not accept a signature from an assistant, or a verbal yes with no record, unless the governance rules allow delegation. If the sponsor delegates, get the delegation in writing and note it on the approval page.
An approver wants changes after signing. Treat it as a change request, not an edit. Altering a signed document without a record destroys the purpose of a baseline.
Approvers disagree. Do not average the positions or quietly pick one. Escalate to whoever has authority over both parties, or ask the sponsor to rule. The disagreement is a governance issue, and the charter should not be signed until it is settled or the dispute is recorded openly.
The project has already started. Teams sometimes begin work on an urgent project before the charter is signed. This is common and risky. Work done without approval has no agreed scope or budget. Get the charter signed as quickly as possible, and record any spending already incurred.
Electronic or wet signatures. Either is acceptable if your organization accepts it. What matters is that the record shows who approved, in what role and on what date.
Quick checklist before sign-off
- Every person who commits money, people or authority has been consulted.
- The approval table names each signer and their role.
- Estimates are labeled as estimates.
- Open conditions have owners and due dates.
- The final version has a version number and a storage location.
- Distribution is planned.
Exercise
A charter commits two engineers from the infrastructure team for six months. The sponsor, who works in a different department, has signed it. Two weeks later the infrastructure manager says the engineers are not available. What went wrong in the approval process, and what should have been done?
Show answer
The approval list left out the resource owner. The sponsor can commit budget but cannot commit people who report to another manager. Before the charter was submitted, the project manager should have identified the infrastructure manager as a person whose resources the charter commits, held a pre-review with them, and added them to the approval table. If the infrastructure manager could not agree, the conflict should have been escalated to someone with authority over both departments before the charter was baselined.
Exercise
A reviewer replies, "Looks fine, but the budget seems tight." The approval deadline is tomorrow. List two reasonable ways to proceed, and explain why simply treating the reply as a yes is a weak choice.
Show answer
Option one: ask the reviewer what range they expect and revise or caveat the budget estimate before submission. Option two: obtain approval with a condition, such as "budget to be confirmed in the detailed plan by a stated date", with a named owner. Treating the reply as a yes is weak because the reviewer raised a concern but gave no explicit approval. If the budget proves too small, the reviewer can say they never agreed, and the project has no record that the concern was addressed.