Sub topic 6
Naming the Deliverables
This chapter assumes you know what a charter is, have written a business case and measurable objectives, and have drawn a scope boundary with in-scope and out-of-scope lists. Deliverables come next in the charter. They turn the scope statement into a list of things someone can hand over, inspect and accept.
What a deliverable is
A deliverable is a tangible or verifiable product, result or capability that the project hands over. You can point to it, and someone can check whether it exists and meets its requirements.
Three terms are often confused:
| Term | What it describes | Example |
|---|---|---|
| Activity | Work the team does | Migrate customer records |
| Deliverable | A product the work produces | Customer database running on the new platform |
| Outcome | A change in the business after delivery | Support staff resolve tickets faster |
Objectives describe outcomes. Scope describes the boundary. Deliverables sit between them: they are what the team builds so that the outcomes can happen. If you list only activities, no one can say when you are done. If you list only outcomes, you promise results the team does not fully control.
Where deliverables fit in the charter
Scope says what is included. Deliverables make that inclusion concrete. Every in-scope item should map to at least one deliverable, and every deliverable should trace to an in-scope item. Checking this in both directions catches two problems early. A scope item with no deliverable is a promise nobody will fulfill. A deliverable with no scope item is work the sponsor may not know they are paying for.
Writing a deliverable entry
At charter level, keep each entry short. You are not writing a full specification. For each deliverable, record:
- A name that is a noun phrase, such as "Migrated customer database" and not "Migrating the database".
- A one- or two-sentence description of what it is and what it contains.
- An acceptance condition: how someone will decide it is done.
- An owner or accepting party, usually a role and not a person.
- The milestone or target date it belongs to.
The acceptance condition is the part most charters skip. Without it, "done" becomes a negotiation at the end of the project. The next chapter develops success criteria in detail. Here, you only need a short, checkable statement per deliverable.
Here is a deliverables section for the migration project used in the scope example:
## 4. Deliverables
| ID | Deliverable | Description | Acceptance condition | Accepts | Milestone |
|----|-------------|-------------|----------------------|---------|-----------|
| D1 | Migration plan | Sequence, cutover window and rollback steps | Approved by IT operations lead | IT operations lead | M1 |
| D2 | Migrated customer database | All active customer records on the new platform | Record counts match source; 50 sampled records match field by field | Head of customer support | M3 |
| D3 | Trained support staff | Staff able to use the new tools in daily work | 90% of staff pass the practical assessment | Head of customer support | M4 |
| D4 | Support runbook | Procedures for common tasks and incidents | Reviewed and signed off by two senior agents | Support team lead | M4 |
| D5 | Project closure report | Results against objectives and lessons learned | Accepted by the sponsor | Sponsor | M5 |Each row can be read on its own. A reader who sees D2 knows what will exist, how it will be judged, and who decides.
Choosing the right level of detail
A charter is written early, when much is unknown. Deliverables at this stage should be specific enough to review and general enough to survive discovery. A useful test: could two reasonable people read the entry and disagree about whether the project has delivered it? If yes, tighten it. Could the entry be invalidated by a normal design decision? If yes, loosen it.
- Too vague: "New system". Which parts? Used by whom? Live or in test?
- Too detailed: "Admin screen with blue header and 12 filter fields". This belongs in requirements, not a charter.
- About right: "Customer database running on the new platform in production, covering all active accounts".
A rule of thumb is five to fifteen deliverables for a typical project. If you have forty, you are probably listing work packages. If you have two, check whether supporting items such as training, documentation and handover are hiding inside them.
Common categories to check
Teams reliably forget the same kinds of deliverables. Before you finalize the list, scan these categories:
- Primary products: the system, report, building or service the project exists to produce.
- Transition items: training, user guides, runbooks, and handover to operations.
- Data and migration items: converted data, reconciliation reports.
- Governance items: the project plan, status reports, the closure report.
- Evidence items: test results, compliance certificates, audit sign-offs.
Governance items are real deliverables, but be selective. Listing every status report clutters the charter. List the ones the sponsor expects to receive and accept, such as the project plan and closure report.
Edge cases
Interim and final deliverables. A project may deliver in stages, such as a pilot and then a full rollout. List each stage as its own deliverable with its own acceptance condition, or state clearly that the pilot is a milestone and not a deliverable. If you leave this unclear, partial delivery can be argued as either success or failure.
Third-party deliverables. If a vendor produces part of the work, list the item and name the vendor-facing owner on your side. Add the dependency to the assumptions section, because your delivery now depends on someone else's schedule. Do not hide vendor items inside a larger deliverable.
Deliverables that depend on decisions not yet made. If you do not know whether the project will produce a custom integration or buy a connector, write the deliverable at the level you can defend ("Integration between billing and the new platform") and record the open choice as an assumption or risk.
Deliverables outside the project's control. "Customers adopt the new portal" is an outcome. The project can deliver the portal, a communication campaign and training. It cannot deliver adoption. Put adoption in the objectives, and list the things the project controls as deliverables.
Excluded deliverables. When a stakeholder expects something you are not building, add it to the out-of-scope list and, where useful, note it next to the deliverables table. This gives the team a reference when someone asks for extra work.
Testing your list
Run these checks on the draft:
- Every deliverable is a noun, and you could hand it to someone.
- Every deliverable has an acceptance condition and an accepting role.
- Every in-scope item maps to a deliverable, and every deliverable maps to an in-scope item.
- Together, the deliverables are enough to meet the objectives. If every deliverable is accepted and an objective still cannot be met, something is missing.
- No deliverable sits in the out-of-scope list.
The fourth check is the most valuable. It finds gaps that individual reviews miss, such as a new tool with no training deliverable when the objective depends on staff using it.
Summary of working rules
- Name products, not activities or outcomes.
- Give each deliverable a checkable acceptance condition and an accepting role.
- Keep the level high enough for a charter and specific enough to settle arguments.
- Check the list against scope and objectives in both directions.
- Include transition and governance items that sponsors actually expect.
Exercise
A draft charter for an office-move project lists these deliverables: "Plan the move", "Staff are happy in the new office", and "Furniture installed on floors 3 and 4, with each desk matching the seating plan". Which entries are valid deliverables, and how would you fix the others?
Show answer
Only the third is a valid deliverable, because it is a verifiable product with an implied check against the seating plan. "Plan the move" is an activity. Rewrite it as a noun with an acceptance condition, such as "Move plan approved by the facilities manager". "Staff are happy in the new office" is an outcome the project cannot fully control. Move it to the objectives with a measure, such as a survey score, and list controllable deliverables instead, such as the new-office orientation guide and the completed seating arrangement.
Exercise
Your charter lists the deliverable "Migrated customer database". The sponsor says it is done once the data is copied. The head of support says it is done once agents can look up customers. How should the charter prevent this disagreement?
Show answer
Add an acceptance condition and an accepting role to the deliverable. For example: "All active customer records on the new platform; record counts match the source; 50 sampled records match field by field; accepted by the head of customer support." If agent lookup matters, add a separate check or deliverable for it. The entry then defines "done" before work starts.