Common Mistakes and How to Avoid Them
This chapter assumes you have read the earlier chapters and can describe each charter section: business case, objectives, scope, deliverables, success criteria, stakeholders, authority, milestones, budget, assumptions, constraints, risks and approval. It also assumes you know the usual project roles, such as sponsor, project manager and team member. Here you will learn to review a draft charter and find the weaknesses that cause trouble later.
Why Review for Mistakes
A charter rarely fails because it is missing a section. It fails because a section is present but does not do its job. A vague objective cannot be checked. A scope list with no exclusions cannot settle an argument. A signature from the wrong person gives no real authority.
Most charter mistakes fall into three groups:
- Vague language: the text sounds reasonable but cannot be tested.
- Missing links: sections do not agree with each other.
- Weak governance: the right people have not committed to the document.
The sections below cover each mistake with its symptom, its cause and a fix.
Mistakes in the Justification and Objectives
Describing the solution instead of the problem
A common opening line is "Implement a new CRM system." That names an activity and says nothing about why the organization needs it. When the sponsor's budget is cut, nobody can argue that the project still matters.
Fix: State the problem or opportunity first, with its cost or value. Then name the project as the response. For example: "Sales staff lose about five hours a week re-entering data across three tools. A single CRM would recover that time."
Objectives that cannot be measured
"Improve customer support response times" is a wish. Nobody can say on the last day whether it was achieved. The earlier chapter on objectives gave the pattern: a metric, a baseline, a target, a deadline and a limit.
Vague: Improve customer support response times.
Measurable: Reduce the median first-response time for support tickets from 8 hours to 2 hours by 30 June, without increasing headcount.Fix: For each objective, check that you can answer five questions. What is measured? What is it now? What must it become? By when? Within what limit? If one answer is missing, the objective is not finished.
Confusing objectives with deliverables
"Deliver a training course" is a deliverable. "Reduce onboarding errors by 40%" is an objective. A project can deliver every item and still miss its objectives, and the charter should make that possible to see.
Fix: Keep the two in separate sections. Each deliverable should link to at least one objective. If a deliverable supports no objective, question whether it belongs.
Mistakes in Scope and Deliverables
Listing only what is in scope
A scope section with only inclusions leaves everything else open. Stakeholders fill the silence with their own expectations. Later, a request for a redesigned website seems reasonable because nothing said it was excluded.
Fix: List exclusions next to inclusions, and name the items people are most likely to assume.
## Scope
**In scope**
- Migrate the customer database to the new platform
- Train support staff on the new tools
**Out of scope**
- Redesign of the customer-facing website
- Migration of archived data older than 7 yearsScope written at the wrong size
Scope that is too broad ("improve the customer experience") cannot be planned. Scope that is too detailed ("button colors on the login page") belongs in the project plan and forces a charter revision whenever a detail changes.
Fix: Describe scope at the level of capabilities and major deliverables. A useful test: if a normal change in how the team works would force you to edit the line, it is too detailed.
Vague deliverables
"Documentation" and "a report" leave the team and the sponsor imagining different things.
Fix: Name each deliverable with its form and, where it matters, its acceptance condition. Write "A user guide of the migrated platform, reviewed and accepted by the support lead" rather than "documentation".
Mistakes in Success Criteria
Success defined as finishing on time and on budget
Schedule and budget matter, but a project can meet both and still produce something nobody uses.
Fix: Include criteria for outcomes (the objectives were met), outputs (the deliverables were accepted) and constraints (time and cost). Name who judges each one.
No one is named as the judge
A criterion such as "users are satisfied" has no value unless someone decides how satisfaction is measured and who accepts the result.
Fix: For each criterion, state the measure, the threshold and the person or role who confirms it.
Mistakes with People and Authority
Missing stakeholders
Teams often list the sponsor and the team and forget the groups affected by the result. Examples are the operations staff who must run the new system, the security team who must approve it, or customers who must change their habits. These groups surface late and raise objections when changes are expensive.
Fix: Walk through the people who pay for, build, use, support, regulate or are disrupted by the project. Ask each of them, "Who else will be affected?"
Roles without authority
A charter that names a project manager but gives no authority leaves that person responsible for results with no power to act. Typical symptoms are the manager waiting for approval to borrow a team member, or being unable to approve small spending.
Fix: State the project manager's authority in concrete terms: spending limits, who can be assigned and reassigned, which decisions can be made alone, and which must go to the sponsor.
| Weak statement | Stronger statement |
|---|---|
| The project manager leads the project. | The project manager may approve spending up to 5,000 per item within the approved budget and may reassign team tasks without sponsor approval. |
| The sponsor supports the project. | The sponsor resolves escalated issues within five working days and approves any change to scope, budget or deadline. |
A sponsor in name only
If the sponsor signs the charter but has no time, budget control or standing to settle disputes, the project has nobody who can protect it.
Fix: Confirm during review that the sponsor controls the budget or can credibly obtain it, and that the sponsor has agreed to the time commitment the role requires.
Mistakes in Planning Details
Milestones that are really tasks
"Write code" is an activity. "Pilot release accepted by the support team" is a milestone, because it is an event you can check.
Fix: Phrase each milestone as a result with a date, and tie it to a deliverable.
Budgets with no basis
A single number with no explanation cannot be defended when someone challenges it, and a round figure copied from another project is likely to be wrong.
Fix: State how the estimate was formed, such as comparison with a similar project or a rough breakdown by labor and purchases. Give a range if the uncertainty is large, and say what the range depends on.
Hidden assumptions and ignored constraints
An assumption such as "the vendor will deliver the licenses by March" is a risk that nobody has looked at. A constraint such as a fixed regulatory deadline is a hard boundary, and teams sometimes write it as a preference.
Fix: Write assumptions as testable statements with an owner and a date by which each will be confirmed. Write constraints as limits the project cannot change. Then check each assumption: if it were false, what would happen? If the answer is serious, add it to the risks.
Risks that are generic
"Delays may occur" fits every project and helps none. A list of risks with no owner is a list of worries.
Fix: Keep the list short, specific and high-level. For each risk, state the cause, the effect and an owner. Detailed analysis goes in the risk register.
Mistakes in Approval and Maintenance
Treating the signature as a formality
When the document is circulated for signatures with no discussion, people sign without reading. Later they say they never agreed to the scope.
Fix: Hold a short review meeting before signing. Ask each approver to state in their own words what the project will and will not do.
Approval by the wrong people
A charter signed only by the project manager authorizes nothing. A charter signed by someone without authority over the budget or resources has the same problem.
Fix: Identify who controls the money, the people and the business area the project affects. Those roles should sign.
Never reopening the charter
Conditions change, and a charter that never changes will drift away from the real project. The opposite error is editing the charter casually, so that nobody knows which version is current.
Fix: Define what triggers a revision, such as a change in objectives, scope, budget, key milestones or sponsor. Make changes through a recorded approval step, and keep version numbers and dates.
A Review Checklist
Use this list when you review a draft.
- Does the business case state a problem and its cost or value?
- Does every objective have a metric, baseline, target, deadline and limit?
- Does the scope list exclusions as well as inclusions?
- Does each deliverable link to an objective and have an acceptance condition?
- Are success criteria judged by named people?
- Are all affected groups identified as stakeholders?
- Does the project manager have written authority?
- Are milestones events that can be checked?
- Does the budget explain how it was estimated?
- Do assumptions have owners and confirmation dates?
- Are risks specific, with owners?
- Did the approvers discuss the document, and do they have the authority to sign?
Reviewing in this order follows the dependencies between sections. If an objective is weak, the scope, deliverables and success criteria built on it will be weak too, so fix upstream sections first.
Summary of Fixes
| Mistake | Main fix |
|---|---|
| Solution stated as the purpose | Describe the problem and its cost first |
| Unmeasurable objectives | Use metric, baseline, target, deadline and limit |
| No exclusions | List out-of-scope items next to in-scope items |
| Success means on time and on budget | Add outcome and output criteria with named judges |
| No authority for the project manager | Write concrete limits and decision rights |
| Generic risks | Give cause, effect and owner |
| Signature as formality | Hold a review discussion before signing |
Exercise
A draft charter has this objective: "Improve staff productivity by rolling out the new scheduling tool." Name two problems with it and rewrite it so it can be checked. Assume staff currently spend 6 hours a week on scheduling and the project ends on 31 March.
Show answer
The first problem is that "improve productivity" has no metric, baseline, target or deadline. The second is that "rolling out the tool" is a deliverable, not an objective, so the sentence mixes the two. A better version is: "Reduce the average time staff spend on scheduling from 6 hours to 2 hours per week by 31 March, without adding staff." The rollout of the tool moves to the deliverables section.
Exercise
A charter is signed by the project manager and the team leads. The sponsor was on leave and the finance director was not asked. List two risks this creates and how to correct them.
Show answer
First, the document does not authorize the project or the budget, because nobody who controls the money has agreed to it. Second, the project has no one with standing to resolve escalated disputes. To correct this, identify the sponsor and the budget holder, hold a short review with them, and obtain their signatures before work continues. The review should include a statement from each approver of what the project will and will not do.