Defining what is in scope and out of scope
This chapter assumes you know the common project roles (sponsor, project manager, team member) and have read the earlier chapters on the business case and measurable objectives. Scope is the third piece of the charter. It turns the objectives into a boundary that the team, the sponsor and other stakeholders can all point to.
What scope is, and what it is not
Project scope is the set of work the project will do, and the results it will produce, to meet its objectives. The charter states scope at a high level. It does not list every task. The detailed breakdown of work comes later, in the project plan.
Scope answers one question: "If someone asks us to do this, is it part of the project?" A good scope statement lets you answer in under a minute, without a meeting.
Two terms are easy to confuse:
- Product scope describes what the thing you deliver contains or can do, such as the features of a new platform.
- Project scope describes the work needed to deliver it, such as migration, training and testing.
In a charter you usually need both, stated briefly. The example later in this chapter mixes them on purpose, because sponsors think in both terms.
Why exclusions matter as much as inclusions
Most scope disputes do not come from things the charter says. They come from things it leaves unsaid. If the charter lists only inclusions, every unlisted request is arguable. A stakeholder can say, "That is obviously part of a migration," and you have no written reply.
Explicit exclusions do three jobs:
- They record decisions that were made on purpose, so nobody reopens them by accident.
- They give the project manager a reference when someone asks for extra work.
- They expose disagreement early. If a stakeholder reads the out-of-scope list and objects, you want that conversation before approval, not during delivery.
The skeleton in this tutorial uses a two-part structure for this reason.
## Scope
**In scope**
- Migrate the customer database to the new platform
- Train support staff on the new tools
**Out of scope**
- Redesign of the customer-facing website
- Migration of archived data older than 7 yearsNotice that each exclusion is something a reasonable person might assume is included. "Redesign of the website" sits next to a platform change, and "archived data" sits next to a database migration. Those are the exclusions worth writing down. An exclusion such as "Building a space station" adds nothing, because nobody expects it.
Deriving scope from objectives
Scope should come from the objectives, not from a brainstorm of everything the team could do. Take each objective and ask: what work is necessary to achieve it, and what work is merely related to it?
Consider this objective from the earlier chapter:
Reduce the median first-response time for support tickets from 8 hours to 2 hours by 30 June, without increasing headcount.Work that plausibly serves it includes a new ticket-routing tool, staff training and an auto-acknowledgement message. Work that is related but not required includes a customer satisfaction survey redesign or a new knowledge base. The second group is a candidate for the out-of-scope list, or for a later project.
A useful check runs in both directions:
- Every in-scope item should trace to an objective. If it does not, it may be scope creep waiting to happen, or the objective list may be incomplete.
- Every objective should have in-scope work behind it. If it does not, the objective cannot be met by this project as defined.
Writing scope items well
Each scope item should be specific enough that two people would agree on whether a piece of work matches it. Compare these:
| Weak item | Stronger item | Why it is better |
|---|---|---|
| Improve the database | Migrate the customer database to the new platform | Names an action and an object |
| Training | Train support staff on the new tools | Names who is trained and on what |
| Data migration | Migrate customer records created since 1 January 2018 | Sets a boundary on the data |
| Support for all regions | Support the UK and Ireland offices only | States the limit instead of implying none |
Three habits help:
- Use a verb and a noun. "Migrate the database" is clearer than "database migration," which can mean planning, doing or checking.
- Name the boundary. Dates, regions, systems, user groups and volumes make items testable.
- Avoid open-ended words. "Etc.," "and similar," "as needed," "full" and "complete" invite argument. If you need "all," define the set.
Handling the gray areas
Some items do not fit cleanly. You will meet these often.
Dependencies on other teams. Your project might need a network upgrade that another team owns. Do not list it as in scope if you do not control it. List it as an assumption or dependency, covered in a later chapter, and say who is responsible for it.
Ongoing work after delivery. Projects end. Operating the new system, maintaining it and paying for it afterward are usually not project work. State this: "Day-to-day operation after handover is out of scope and belongs to IT Operations."
Partial inclusion. Sometimes an item is in scope for one part only. Say so directly, for example: "Integration with the billing system: read-only access only. Write-back is out of scope."
Items you are unsure about. Do not hide uncertainty. Either decide before approval, or record the item as "to be decided by [name] by [date]." An unresolved item with an owner and a date is better than a vague phrase that hides it.
Scope, deliverables and success criteria
Scope, deliverables and success criteria are three separate sections, and each has its own job.
- Scope says what work and boundaries apply.
- Deliverables, covered in the next chapter, name the specific things the project hands over.
- Success criteria say how the results will be judged.
Keep the scope section from turning into a deliverables list. If you find yourself writing "a 20-page user guide," you have moved into deliverables. In scope, "Produce user documentation for support staff" is enough.
Using the scope statement during delivery
The scope section is most valuable after approval, when someone asks for something new. A simple routine keeps the answer consistent:
- Compare the request with the in-scope and out-of-scope lists.
- If it is clearly in scope, proceed.
- If it is clearly out of scope, say so and offer to record it for a future project.
- If it is neither, treat it as a change request. Estimate its effect on time, cost and risk, and send it to the person with authority to approve it, usually the sponsor.
The last step depends on the authority section of the charter. If the charter does not say who approves scope changes, the project manager ends up negotiating each request alone. A later chapter on reviewing and changing the charter covers that process in more detail.
Common errors
- Listing only inclusions. Leaves every unlisted request open to debate.
- Writing exclusions nobody would expect. Pads the list and hides the useful ones.
- Scope too broad for the objectives. Work that does not serve an objective adds cost and risk.
- Scope that quietly depends on things the project cannot control. Move these to assumptions and dependencies.
- Mixing scope with a task list. The charter should stay at a level where it changes rarely.
- Never showing the exclusions to stakeholders. If they first read the out-of-scope list during delivery, you will hear about it then.
Exercise
A charter for a customer database migration lists in scope: "Migrate the customer database" and "Train support staff." Midway through the project, the marketing director asks the team to also migrate five years of archived email campaign data. The sponsor wants to know whether this is in scope. What does the charter let you say, what is the weakness in the charter, and how would you rewrite the scope section to prevent the argument?
Show answer
The charter lets you say only that the archived campaign data is not named, so it is arguable. That is the weakness. The scope lists no exclusions and does not bound "the customer database," so a reasonable person could read the archive as part of it. Rewrite the section with a boundary and an exclusions list. In scope: "Migrate customer records in the production database created since 1 January 2018." Out of scope: "Migration of archived data older than 7 years" and "Migration of email campaign data held in the marketing system." Show this to the marketing director before approval. For the current request, treat it as a change request: estimate the time, cost and risk, and send it to the sponsor, who holds authority over scope changes.
Exercise
Take the objective "Reduce the median first-response time for support tickets from 8 hours to 2 hours by 30 June, without increasing headcount." List two work items you would put in scope and two you would put on the out-of-scope list. Give a one-line reason for each.
Show answer
Sample answer. In scope: (1) "Implement automatic ticket routing," because routing is a direct way to cut first-response time; (2) "Train support staff on the new routing tool," because the tool does not reduce response time if staff cannot use it. Out of scope: (1) "Redesign of the customer satisfaction survey," because it is related to support quality but does not affect first-response time and could be assumed part of a support improvement; (2) "Hiring additional support staff," because the objective forbids increasing headcount, so listing it as excluded settles a likely request. Any answer where each in-scope item traces to the objective and each exclusion is something a stakeholder might plausibly assume is acceptable.