Sub topic 11
Estimating Budget and Resources
This chapter covers section 8 of the charter, "Budget and Resources". It assumes you have read the earlier chapters on scope, deliverables and milestones, and that you know the roles of sponsor, project manager and team member. By the end you should be able to write a budget section that a sponsor can approve and that you can defend later.
What the charter needs from this section
A charter is written before detailed planning, so its budget is an estimate and not a final cost plan. The section answers three questions for the approver:
- How much money is the project asking for, and how accurate is that figure?
- Which people, equipment and services does the project need, and for how long?
- Where does the money come from, and who may spend it?
The budget depends on earlier sections. Scope and deliverables determine what work must be paid for. Milestones determine when the money and people are needed. The budget in turn feeds the risk section, because a tight budget is itself a risk.
Choosing an estimating approach
Early in a project you rarely have enough detail for a precise estimate. Three common techniques fit charter-level work.
| Technique | How it works | Best used when | Main weakness |
|---|---|---|---|
| Analogous | Start from the actual cost of a similar past project and adjust | A comparable project exists and its records are available | Past projects are never identical, so the adjustment is a judgment call |
| Parametric | Multiply a unit rate by a quantity, such as cost per user migrated | You have a reliable rate and can count the units | A poor rate or count produces a confident but wrong figure |
| Three-point | Estimate optimistic (O), most likely (M) and pessimistic (P) values, then average them | Uncertainty is high and you want to show a range | It takes more effort, and people tend to set O and P too close to M |
The three-point technique often uses the weighted formula (O + 4M + P) / 6. For example, if data migration could cost 20,000 at best, 30,000 most likely and 55,000 at worst, the estimate is (20,000 + 4 × 30,000 + 55,000) / 6, which is about 32,500. The result is higher than the most likely value because the downside is larger than the upside.
def three_point(optimistic, most_likely, pessimistic):
"""Return the weighted three-point estimate."""
return (optimistic + 4 * most_likely + pessimistic) / 6
print(round(three_point(20_000, 30_000, 55_000)))Running this prints 32500.
Stating accuracy as a range
A single number suggests more certainty than you have. At charter stage, estimates are commonly accurate only within a wide band. Some organizations use a rough order of magnitude of about -25% to +75%. Others use narrower bands. Use whatever band your organization's guidance sets, and state it in the charter.
## 8. Budget and Resources
**Estimated budget:** 180,000 (range 150,000 to 230,000), rough order of magnitude.
**Basis of estimate:** Analogous to the 2024 CRM upgrade (165,000), adjusted for 40% more users.
**Funding source:** Operations budget, cost center 4410.
**Estimate to be refined:** At the end of the planning phase.The sample states the figure, the range, the method and the date of refinement. Each line answers a question an approver is likely to ask.
Breaking the budget into categories
Even a high-level budget should show where the money goes. A short table is enough.
| Category | Estimate | Notes |
|---|---|---|
| Internal labor | 70,000 | 2.5 FTE for 6 months, at the internal loaded rate |
| External contractors | 55,000 | Data migration specialist, 11 weeks |
| Software and licences | 30,000 | First-year subscription |
| Training | 10,000 | Materials and trainer time for support staff |
| Contingency | 15,000 | About 9% of the subtotal |
| **Total** | **180,000** |
FTE means full-time equivalent: one person working full time. Two people each working half time make 1 FTE. A loaded rate includes salary plus overheads such as benefits and office space. Ask finance which rate to use, because projects are often mis-costed by using salary alone.
Contingency and management reserve
Money set aside for uncertainty comes in two forms, and the charter should say which it means.
- Contingency reserve covers identified risks and estimate uncertainty. The project manager usually controls it.
- Management reserve covers unknown problems that nobody has foreseen. The sponsor or a governance body usually controls it, and releasing it requires approval.
Do not hide padding inside individual line items. Hidden padding is hard to defend when someone questions the estimate, and it encourages teams to spend what they were given. State the reserve openly, with a percentage and a reason. Percentages vary with the novelty of the work. A familiar, repeatable project might carry 5 to 10%, and a novel one considerably more.
Listing resources, not just money
Resources are the people, equipment, facilities and services the project consumes. For each, record what is needed, how many, when, and whether it is confirmed.
| Resource | Quantity | Period | Status |
|---|---|---|---|
| Project manager | 1.0 FTE | Months 1 to 6 | Confirmed |
| Business analyst | 0.5 FTE | Months 1 to 3 | Requested |
| Developers | 2.0 FTE | Months 2 to 5 | Not yet agreed |
| Test environment | 1 | Months 3 to 6 | Requested |
The status column is the useful part. A resource that is "not yet agreed" is an assumption, and it belongs in the assumptions section too. Staff who work on the project part time while keeping their normal jobs are a frequent source of delay. Confirm the allocation with their line managers, not only with the individuals.
Edge cases
- Shared or borrowed staff. Their cost may not appear in the project budget if their department absorbs it. Say so, so the approver does not think the labor is free and does not discover later that it is unfunded.
- Operating costs after the project ends. Licences, support and hosting continue after delivery. Include a note on the ongoing yearly cost, or the project looks cheaper than the solution it creates.
- Capital and operating funds. Some organizations pay for these from different budgets. Check with finance which categories fall under which.
- Currency and inflation. For multi-year projects or foreign suppliers, state the exchange rate assumed and whether prices are fixed.
- Phased funding. The sponsor may release money in stages tied to milestones. If so, record the release points, because a delayed milestone then delays funding.
- Constrained budgets. If the sponsor sets a fixed amount before the estimate exists, compare it with your estimate. When the estimate is higher, report the gap and offer options such as reduced scope, a longer schedule or more funding. Do not quietly accept an unachievable number.
Connecting the budget to authority and risk
The budget section should say who may spend what. The project manager's authority section (section 6) normally sets a limit, such as approving purchases up to a fixed amount without the sponsor. Keep the two sections consistent. If section 6 allows spending up to 10,000 and section 8 lists a 55,000 contractor, the charter should say that the contract is approved by the sponsor as part of the charter itself.
Link budget uncertainty to the risk list. If the estimate depends on a single vendor quote, or on a licence price that may rise, list that as a high-level risk. The next section of the charter, assumptions and constraints, collects the conditions the estimate rests on. The risks chapter then turns the uncertain ones into risks.
A short checklist
- The total is given as a range with a stated basis of estimate.
- Costs are split into categories, including internal labor.
- Contingency is visible, with a percentage and a controller.
- Each resource shows quantity, period and confirmation status.
- Post-project running costs are noted.
- Funding source and spending limits match the authority section.
- A date is set to refine the estimate.
Exercise
A project manager estimates a migration task at 10,000 optimistic, 14,000 most likely and 26,000 pessimistic. Using the weighted three-point formula, what is the estimate? Then name one reason the charter should show it as a range and not as a single figure.
Show answer
(10,000 + 4 × 14,000 + 26,000) / 6 = 92,000 / 6, which is about 15,333. The charter should show a range because at charter stage the scope and rates are not yet detailed, so a single figure would imply a precision the estimate does not have. A range such as 12,000 to 26,000 also warns the approver that the cost could rise toward the pessimistic value.
Exercise
A charter lists "Developers, 2.0 FTE, months 2 to 5" with the status "not yet agreed". In which other charter section should this appear, and why?
Show answer
It belongs in the assumptions section. The schedule and cost rely on the developers being available, but nobody has committed them. Recording it as an assumption lets the team check it early, and it can also become a high-level risk if availability is doubtful.