Sub topic 15
Reviewing the Charter and Handling Changes
This chapter assumes you can already draft a charter's main sections: the business case, objectives, scope, deliverables, success criteria, stakeholders, authority, milestones, budget, assumptions, constraints and risks. It also assumes your charter has been approved, or is about to be. Here you will learn how to review a charter before approval, when to revisit it afterward, and how to change it without losing control of the project.
Why the charter needs a review and change routine
An approved charter is a reference point. People will quote it when they disagree about scope, budget or who decides what. If it never changes while the project does, it becomes wrong. People then stop trusting it, and it stops settling disputes.
If it changes informally, through an email here or a hallway agreement there, it stops being a baseline. Nobody can say which version is real.
The routine in this chapter keeps the charter both stable and accurate. Review it before approval to catch weaknesses. After approval, change it only through a visible, recorded process.
Reviewing a draft before approval
Review a draft in two passes, and use different people for each.
Pass 1: Consistency review
The author or a peer checks that the sections agree with each other. Charter sections depend on one another, so an error in one often shows up as a contradiction in another. Check these links:
| Check | What to look for |
|---|---|
| Objectives to justification | Each objective supports a reason given in the business case. |
| Objectives to success criteria | Each objective has a criterion that can be measured. |
| Scope to deliverables | Every deliverable is in scope, and nothing in scope lacks a deliverable. |
| Deliverables to milestones | Each deliverable appears at a milestone with a date or period. |
| Milestones to budget | The budget covers the work implied by the timeline. |
| Assumptions to risks | Each fragile assumption has a matching risk, or a reason it does not. |
| Authority to constraints | The project manager's authority does not conflict with a stated constraint, such as a spending limit. |
A typical failure: the scope says "migrate the customer database", but no deliverable names the migrated database and no milestone covers it. Each section reads fine alone. Together they leave a gap that someone will find during execution.
Pass 2: Sponsor and stakeholder review
Give the draft to the sponsor and the key stakeholders. Ask each reader a specific question, because "Any comments?" usually gets none. For example:
- Sponsor: "Is this the outcome you are funding, and is the authority listed enough for the project manager to act?"
- Finance contact: "Can you commit to this budget range and funding source?"
- Operational owner: "Can your team supply the people named, in the months stated?"
- Anyone listed under out of scope: "Do you accept these exclusions?"
The last question matters most. Surprise about exclusions is a common cause of later scope disputes. It is much cheaper to find that disagreement before approval.
A review checklist
Use a short checklist so reviews are consistent across projects. Keep it in a document that reviewers can copy:
# Charter Review Checklist
- [ ] The purpose can be stated in two sentences.
- [ ] Each objective has a metric, baseline, target and deadline.
- [ ] Out-of-scope items are listed, not only in-scope items.
- [ ] Every deliverable has an acceptance criterion.
- [ ] Each stakeholder group has a named person or role.
- [ ] The project manager's authority (spend, staffing, schedule) is stated with limits.
- [ ] Milestones are dated or have a date range.
- [ ] Budget states its estimate range and what it excludes.
- [ ] Every assumption says who will confirm it and by when.
- [ ] Top risks have an owner.
- [ ] The approval block names who signs and in what role.Record the outcome of each review: who reviewed, which version, what was changed. A short note is enough, and it helps if someone later asks why a decision was made.
Versioning the charter
Give the charter a version number and a change log from the first draft. A common convention is 0.x for drafts and 1.0 for the approved version. Later approved changes become 1.1, 1.2 and so on. Use a whole-number increase, such as 2.0, for a change that alters the project's purpose, objectives or scope boundary.
Place a change log at the top or end of the document:
## Document History
| Version | Date | Author | Change | Approved by |
|---------|------|--------|--------|-------------|
| 0.3 | 2026-03-02 | A. Rivera | Added exclusions after sponsor review | n/a (draft) |
| 1.0 | 2026-03-10 | A. Rivera | Approved baseline | J. Okafor (Sponsor) |
| 1.1 | 2026-06-18 | A. Rivera | Moved milestone M3 from 30 Sept to 31 Oct; budget unchanged | J. Okafor (Sponsor) |Store the charter in one place that everyone can read and only a few can edit. Superseded versions should stay available but be clearly marked, so nobody works from an old copy.
When the charter should be revisited
Do not revise on a whim, and do not wait until the project is in trouble. Two kinds of trigger apply.
Scheduled reviews. Choose them when the project is chartered. A common pattern is to check the charter at each stage gate or major milestone, or quarterly for long projects. At each check, ask whether the business case still holds, whether the assumptions are still true, and whether the risks have changed.
Event-driven reviews. Revisit the charter when something happens that touches its content:
- The sponsor changes, or the sponsor's priorities change.
- An assumption turns out to be false.
- A constraint changes, such as a budget cut or a new regulation.
- A risk occurs and its effect reaches the objectives, scope, budget or dates.
- Stakeholders request work that falls under out of scope.
- A key resource named in the charter becomes unavailable.
Not every event requires a charter change. A delay of two weeks inside a milestone window that the charter already allows is a matter for the project plan, not for the charter. The test is whether the change would make a statement in the charter untrue, or would exceed the authority the charter gives the project manager.
The change process
A change to an approved charter follows the same path as any controlled change: request, assess, decide, record, communicate.
Assess the impact first
Before the sponsor decides, the project manager should describe the effect on each of the main constraints: scope, schedule, budget, quality and risk. A change request that says "add the mobile app" is not decidable. One that says "add the mobile app: +10 weeks, +£80,000, two new risks, and the out-of-scope item 'mobile access' moves into scope" can be decided in one meeting.
Decide at the right level
The charter's authority section determines who can approve what. A typical split:
- The project manager approves changes that stay inside stated tolerances, such as a small shift within a milestone window.
- The sponsor approves changes that move a milestone date, increase the budget beyond the tolerance, or alter scope.
- A steering group or higher authority approves changes to the purpose, the business case, or anything that affects other projects.
If the charter does not state these thresholds, add them at the next revision. Missing thresholds are a frequent source of conflict, because every change then becomes a negotiation about who may decide.
Keep a change log separate from the document history
The document history records changes to the charter itself. A change request log records every request, including those that were rejected or handled inside the plan. The second log is useful evidence when a stakeholder says their request was ignored.
Common errors in review and change
- Reviewing only for wording. Readers fix grammar and miss the contradiction between scope and budget. Use the consistency table above.
- Silent updates. Editing an approved charter without a version change or approval means readers cannot tell which text was authorized.
- Treating the charter as unchangeable. Refusing all changes forces people to work around the document. A charter that is out of date is worse than one that has been updated properly.
- Revising for every small shift. Frequent revisions suggest the charter holds too much detail. Move detail into the project plan and keep the charter high-level.
- Approving changes without impact assessment. A yes given without cost and schedule figures tends to be reversed later.
- Forgetting to tell people. An approved change that stakeholders never hear about creates the same disputes it was meant to prevent. Send a short notice with the new version number and a summary of what changed.
Exercise
Your approved charter (version 1.0) lists "Integration with the payroll system" as out of scope. Midway through the project, the HR director asks you to add it. You estimate it would add 6 weeks and £45,000. The charter allows you to approve schedule changes of up to 2 weeks and no budget increases. What do you do, and what does the charter look like afterward if the request is approved?
Show answer
The request exceeds the project manager's authority on both schedule (6 weeks against a 2-week limit) and budget (any increase needs approval). Log it, write an impact assessment covering scope, schedule, budget, quality and risk, and submit it to the sponsor. If the sponsor approves, update the charter: move payroll integration from out of scope to in scope, add the related deliverable, adjust the milestone dates and budget, and add any new risks. Record the change in the document history as a new version (for example 1.1, or 2.0 if the sponsor treats it as a change to the scope boundary), with the approver named. Then notify stakeholders of the new version and what changed.
Exercise
Name three charter consistency checks you can run during review, and give one example of a contradiction each would catch.
Show answer
Any three of the following. Scope to deliverables: the scope includes staff training but no deliverable covers it. Deliverables to milestones: a deliverable has no milestone, so no date applies to it. Milestones to budget: the timeline needs a contractor for four months but the budget funds two. Assumptions to risks: the plan assumes a vendor delivers by March, but no risk covers vendor delay. Authority to constraints: the project manager may hire freely, yet a constraint fixes headcount.