Sub topic 10
Setting High-Level Milestones
This chapter assumes you know what a project charter is, you have read the earlier chapters on objectives, scope and deliverables, and you know the usual project roles. Here you will learn how to write the milestones and timeline section of a charter, which is section 7 in the skeleton from the first chapter.
What a milestone is
A milestone is a point in the project that marks something finished or decided. It has a date but no duration. It is not a task, because nobody works "on" a milestone. People work on tasks, and a milestone is the event that tells you those tasks are done.
A charter lists only high-level milestones. Usually that means 4 to 10 for the whole project. The detailed schedule comes later in the project plan. The charter's job is to give the sponsor enough of a timeline to decide whether to approve the project, and to give the team dates they can be held to.
| Item | Example | Belongs in the charter? |
|---|---|---|
| Task | Write test scripts for the import tool | No. It goes in the project plan. |
| Milestone | Customer database migrated and verified | Yes |
| Phase gate | Sponsor approves go-live | Yes |
| Hard deadline | Contract with the old vendor ends on 31 October | Yes, as a constraint tied to a milestone |
Where milestones come from
Milestones should not be invented from a calendar. Derive them from the earlier sections of the charter.
- Start with the deliverables. Each major deliverable usually needs a milestone for when it is accepted, not when work on it begins.
- Add decision points. Examples are "budget released for phase 2" or "go-live approved."
- Add external dates. These include contract end dates, regulatory deadlines, financial year ends and fixed events such as a trade show.
- Add the success criteria check. If the objective says "by 30 June," a milestone must exist before that date to confirm the result.
This is why the concept graph places milestones after deliverables. A milestone with no deliverable or decision behind it is probably a task in disguise.
Writing a good milestone
A useful milestone has three properties.
- It is verifiable. Someone other than the owner can check whether it happened.
- It names an outcome, not an activity. "Training completed" is weaker than "All 40 support staff have passed the tool assessment."
- It has an owner and a target date. Even in a charter, one person should be answerable for each milestone.
Compare these two lines.
Weak: Start migration work in Q2.
Stronger: Customer database migrated to the new platform and reconciled
against the old system (owner: Data Lead, target: 15 May).The weak line describes activity and gives only a loose period. Nobody can say whether it has been met. The stronger line can be checked by comparing record counts.
Target dates versus fixed dates
At charter stage, you know little about the work, so most dates are estimates. Say so. Mark each date as one of two kinds.
- Fixed: it cannot move because of a contract, law or external event.
- Target: it is the current best estimate and can move through the change process.
Without this distinction, every date gets read as a promise, and the team is blamed when an estimate turns out wrong. Equally, a fixed date that is not labelled fixed may be treated as flexible until it is too late.
A common way to show uncertainty is a date range or a month rather than a day. "Pilot complete: June" is more honest at charter stage than "Pilot complete: 14 June" when the project has not yet been planned.
Working backward from a fixed date
If the project has a hard deadline, plan from the deadline backward. Place the final milestone first, then ask how long each earlier stage needs, and see whether the start date is realistic.
For example, suppose the old vendor contract ends on 31 October and the migration needs a month of parallel running. Then cutover must finish by about 30 September. Testing needs six weeks, so testing must begin by mid-August. If the charter is being signed in late July and build work is unfinished, the date is already at risk. That is a finding to record in the risk section and to raise with the sponsor before approval.
Including time for review and approval
A frequent omission is the time that other people need. Milestones often depend on reviews, sign-offs, procurement or access that the project team does not control. Allow for these explicitly.
- Add a review period before each acceptance milestone.
- Allow for known slow processes, such as security reviews or purchase orders.
- Check holiday periods and key people's leave.
If an approval takes the sponsor's committee three weeks to schedule, a milestone that assumes a one-week turnaround will slip. Record such dependencies as assumptions in section 9, linking them to the milestone.
Showing the timeline
A table is usually enough for the charter. Add a simple chart when the sequence matters or the sponsor prefers a visual.
| # | Milestone | Owner | Date | Type |
|---|---|---|---|---|
| 1 | Charter approved | Sponsor | 5 Jan | Fixed |
| 2 | Platform selected and contract signed | Project manager | Feb | Target |
| 3 | Customer database migrated and reconciled | Data lead | 15 May | Target |
| 4 | Support staff trained and assessed | Training lead | June | Target |
| 5 | Go-live approved | Sponsor | 15 June | Target |
| 6 | Old platform contract ends | Procurement | 31 Oct | Fixed |
The same information can be drawn as a timeline. The diagram below shows the order and rough spacing of the first five milestones.
Linking milestones to budget and success criteria
Milestones connect to the sections that follow and precede them.
- Budget: money is often released at milestones. If funding for phase 2 depends on milestone 3, say so. This makes the budget section and the milestone section agree.
- Success criteria: the final milestone should be the point at which the success criteria can be assessed. If the objective is a response-time target by 30 June, a milestone must come early enough to measure it, for example "Two weeks of ticket data collected: 14 June."
- Governance: milestones are natural points for a sponsor review. Say which ones are formal gates.
Common errors
- Too many milestones. A list of 30 items is a schedule, not a charter section. Cut it to the ones the sponsor needs to see.
- Milestones that are tasks. "Write requirements" is work. "Requirements approved" is a milestone.
- Dates that ignore dependencies. Check that no milestone falls before something it depends on.
- No distinction between fixed and target dates.
- Dates with no owner, so nobody answers when one slips.
- A timeline that contradicts the budget or the scope. If the scope needs six months of work and the timeline shows three, one of them is wrong.
- Treating the charter dates as final. The charter dates are an early estimate, and the project plan should refine them.
A short checklist
Before moving on, check each milestone against these questions.
- Does it mark an outcome or decision that someone can verify?
- Does it trace back to a deliverable, a decision, an external date or a success criterion?
- Does it have an owner?
- Is its date labelled fixed or target?
- Is the precision of the date appropriate for what is known?
- Does it allow time for reviews and approvals?
- Is it consistent with the scope, budget and risks?
Exercise
A draft charter lists this milestone: "Begin user training in May, date to be confirmed." Rewrite it as a better milestone, and name two things you should check before settling its date.
Show answer
A better version is: "All 40 support staff have completed training and passed the tool assessment (owner: Training lead, target: end of June, target date)." This names an outcome that someone else can verify, it has an owner, and it is labelled as a target date. Before settling the date, check that the training depends on a finished migration or a working platform, so it cannot fall before those milestones, and check for review or availability constraints such as staff leave, trainer availability or the time needed to run assessments.
Exercise
A project has a fixed date: a regulator requires a new reporting system to be live by 1 December. The system needs two weeks of parallel running, four weeks of testing and an approval from a committee that meets monthly. Starting from 1 December, work backward to find the latest dates for the main milestones, and say what you would do if the charter is being signed on 1 September and the build is estimated at three months.
Show answer
Working backward: go-live by 1 December, so parallel running starts by about 17 November. Testing (four weeks) must finish by then, so it starts by about 20 October. The build must be finished by 20 October, so with a three-month build, work would have to start about 20 July. The committee approval must also be scheduled before go-live, ideally with a margin of a month because it meets monthly. Since the charter is signed on 1 September, the build would only finish around 1 December, so the fixed date is already at risk. I would record this as a high-level risk, mark 1 December as a fixed date, and raise it with the sponsor before approval so they can decide whether to reduce scope, add resources or negotiate the deadline.