Sub topic 12
Recording Assumptions and Constraints
Prerequisites and where this fits
This chapter assumes you have read the earlier chapters on scope, deliverables, milestones and budget. You should know what a sponsor and a project manager do, and you should have a draft scope statement in front of you. Assumptions and constraints are section 9 of the charter skeleton. They come after scope and budget because they describe the conditions under which those sections hold. They come before risks because many risks grow out of them.
Why this section exists
Every project plan rests on things nobody has checked yet. You expect a vendor to deliver on time. You expect the same people to be available for six months. You expect the budget to be released in the first quarter. If these expectations stay in people's heads, each person holds a slightly different version. When one of them fails, the team argues about who knew what.
Writing them down does three things:
- It makes hidden dependencies visible to the sponsor before approval.
- It gives the team a list to check as the project runs.
- It shows which parts of the plan are firm and which are provisional.
Assumptions versus constraints
The two are easy to confuse, so define them separately.
An assumption is something you treat as true for planning purposes, though you have not confirmed it. It might turn out false. Assumptions are about uncertain facts.
A constraint is a limit that is already imposed on the project. It is not up for debate within the project. Constraints are about fixed boundaries.
| Aspect | Assumption | Constraint |
|---|---|---|
| Status | Believed true, not verified | Known and imposed |
| Can it turn out wrong? | Yes | No, it is a given |
| Who controls it | Usually someone outside the team | Sponsor, regulator, contract or organization |
| Typical example | "The vendor API will be available by March." | "Go-live must happen before the 30 June audit." |
| What you do with it | Validate it, assign an owner, watch it | Plan around it |
A useful test: ask "Could this stop being true without anyone deciding to change it?" If yes, it is an assumption. If someone with authority would have to decide to change it, it is a constraint.
Kinds of constraints
Constraints usually fall into a few groups. Checking each group helps you avoid missing one.
- Time: a fixed launch date, a regulatory deadline, a blackout period such as a year-end freeze.
- Budget: a spending cap, or a rule that only operating funds, not capital funds, may be used.
- Resources: a fixed headcount, no contractors, shared specialists who are only available part time.
- Technology: the solution must run on the existing platform or use an approved tool.
- Legal and policy: data protection law, procurement rules, security standards.
- Quality: a required uptime, accuracy or certification level.
Notice that the scope constraint is already handled elsewhere. The "out of scope" list from the scope chapter limits the work, but it is a decision about content. Keep the constraints section for limits that come from outside the project's own choices.
Writing good assumptions
A weak assumption is vague and has no owner. A strong one names the thing, the date and the person who can confirm it.
Weak: "Resources will be available."
Strong: "The two database engineers from the platform team will work at least 50% on this project from 1 February to 30 April. Confirmation owner: Dana Reyes, platform team lead. To be confirmed by 15 January."
Each recorded assumption should carry:
- A clear statement that could be checked as true or false.
- An owner who is responsible for confirming it.
- A validation date after which it must be confirmed or escalated.
- An impact note saying what changes if it proves false.
You can keep this in a table inside the charter.
## 9. Assumptions and Constraints
### Assumptions
| ID | Assumption | Owner | Confirm by | If false |
|----|-----------|-------|------------|----------|
| A1 | Two platform engineers work at least 50% on the project from 1 Feb to 30 Apr | Dana Reyes | 15 Jan | Migration milestone slips by about 6 weeks |
| A2 | The vendor's export API is available in the test environment by 1 Mar | Priya Shah | 1 Feb | Data migration testing cannot start |
| A3 | Support staff can attend two half-day training sessions in May | Tom Okafor | 30 Mar | Training moves to June, after go-live |
### Constraints
| ID | Constraint | Source |
|----|-----------|--------|
| C1 | Go-live must occur before the 30 June audit | Compliance office |
| C2 | Total spending may not exceed the approved budget of 250,000 | Finance |
| C3 | Customer data must remain in the existing region | Data protection policy |Numbering the items (A1, C1) lets later documents refer to them without copying the text. The risk register, the change log and status reports can all say "A2 has failed."
How assumptions turn into risks
An assumption is a place where the plan could break. The next chapter covers high-level risks, and this is where the two connect. Go through each assumption and ask how likely it is to be false and how much damage that would do. If both answers are significant, move it into the risk list with a response plan.
The same applies to constraints in a different way. Constraints do not fail, but two of them can conflict. A fixed date, a fixed budget and a fixed scope may not fit together. If you notice that, raise it before approval. A charter that hides an impossible combination is a poor charter, because the sponsor will approve it believing it is achievable.
Common errors
- Listing facts as assumptions. "The company has 400 employees" is not an assumption if you can look it up. Check it and state it as background.
- Listing wishes as assumptions. "Stakeholders will be cooperative" cannot be verified and gives no action. Rewrite it as something specific, such as "The finance director will review invoices within three working days."
- Treating constraints as negotiable. If you write "The budget is limited" and then plan for more, you have either a false constraint or a hidden assumption. Decide which it is.
- No owners or dates. An assumption nobody is responsible for will never be checked.
- Writing the section once and forgetting it. The list is only useful if you revisit it at each milestone.
- Writing too many. Twenty-five generic items hide the five that matter. Keep those that would change a decision if they proved wrong.
Edge cases
An assumption already known to be false. If you discover it while drafting, do not record it. Change the plan, or raise it as an issue with the sponsor.
A constraint that you think is wrong. If a deadline seems arbitrary, you may ask the sponsor to justify or relax it, but record it as a constraint until someone with authority changes it. Disagreement is not a reason to omit it.
An assumption that the sponsor must confirm. Some assumptions, such as "funding will be released on 1 April", depend on the very person who approves the charter. Ask for confirmation as part of approval, and move the item from the assumptions list into the background section once confirmed.
Assumptions that depend on other projects. If your project needs another team's delivery, name that project and its expected date. It is both an assumption and a dependency, and the owner should be someone on the other project.
Changing an assumption mid-project. When an assumption fails, update the charter through the change process, not silently. The approval chapter and the change chapter cover how.
Checklist before moving on
- Every assumption is checkable, with an owner, a date and a stated effect if false.
- Every constraint has a named source.
- No item appears in both lists.
- The constraints are consistent with each other and with the scope, budget and milestones.
- The riskiest assumptions are carried into the risk section.
Exercise
A draft charter lists these items under "Assumptions": (1) "The project must finish by 15 September because of the product launch." (2) "The testing team will be available in July." (3) "Everyone will support the project." Classify each as an assumption or constraint, and rewrite any that are poorly written.
Show answer
Item 1 is a constraint. A fixed date imposed by the launch is a given, so move it to the constraints list with its source (the product launch plan). Item 2 is a genuine assumption, but it is weak. Rewrite it with an owner, a date and an effect, for example: "Two testers from the QA team are available full time from 1 to 31 July. Owner: QA lead. Confirm by 1 June. If false, system testing moves into August and the 15 September date is at risk." Item 3 is a wish, not a checkable assumption. Replace it with a specific one, such as "The heads of sales and support each assign one representative to the weekly review meeting," with an owner and a date, or drop it and handle support under stakeholder engagement.
Exercise
Your sponsor sets a fixed budget of 100,000, a fixed go-live date of 1 May, and a full scope that your estimate says needs 140,000 and until 1 July. How do you record this in the charter?
Show answer
Do not hide it. Record the budget and date as constraints with their sources. Then point out that the three limits (scope, budget, date) conflict, and raise this with the sponsor before approval. Offer options: reduce scope to what fits, raise the budget, move the date, or phase the delivery. Once the sponsor decides, update the scope, constraints and milestones so they agree. If the sponsor insists on all three, record the gap as a high-level risk and note the sponsor's decision in the approval record.