Sub topic 3
Stating why the project exists
This chapter covers the business justification section of a project charter. It assumes you know what a charter is, how it differs from a business case, and the usual project roles such as sponsor and project manager. By the end, you should be able to write a justification that a sponsor can approve and a team can use to make decisions later.
What the justification section does
The business justification answers one question: why is the organization spending money and people's time on this project instead of something else? Every other section depends on the answer. Objectives, scope and success criteria all exist to serve the reason stated here.
The charter's justification is a summary. The full business case, if one exists, holds the detailed financial model and the options analysis. The charter takes its conclusions and states them in a few paragraphs, with a reference to the business case for readers who want the evidence.
A good justification does three jobs:
- It lets the approver decide whether the project deserves resources.
- It gives the team a test for ambiguous choices. When two options are both reasonable, the team picks the one that better serves the stated reason.
- It lets a later reviewer judge whether the project is still worth continuing if circumstances change.
The parts of a justification
A justification that works in practice has five parts. You can write them as short labelled paragraphs or as one flowing section.
| Part | Question it answers | Example |
|---|---|---|
| Problem or opportunity | What is wrong, or what could be gained? | Support tickets wait too long for a first reply. |
| Evidence | How do we know? | Median first response is 8 hours. Survey scores for responsiveness fell 12 points in a year. |
| Impact of inaction | What happens if we do nothing? | Churn among enterprise customers continues at the current rate. |
| Proposed response | What are we choosing to do, at the level of approach? | Adopt a new ticketing platform and retrain staff. |
| Expected benefit | What do we gain, and roughly what does it cost? | Lower churn and fewer escalations, for a budget in the range stated in section 8. |
The charter's later sections carry the detail. The justification only needs enough of the proposed response to make the benefit believable.
Problem statements versus solution statements
The most common weakness in this section is describing a solution instead of a problem. "Implement a new CRM" is a solution. It tells the reader what will be bought, but not why. If the CRM turns out to be a poor fit, nobody can tell whether the project failed or whether a different approach would have met the real need.
State the problem in terms of its effect on the organization, and then state the response.
| Weak (solution as reason) | Stronger (problem as reason) |
|---|---|
| We need to implement a new CRM. | Sales staff spend about a quarter of their week re-entering data across three systems, and forecasts are unreliable because the records disagree. A single customer system is the proposed response. |
| We must move to the cloud. | The data centre lease ends in March and renewing costs more than the projected cost of hosting externally. |
| Launch a mobile app. | Forty percent of orders now start on phones, and the mobile website converts at half the rate of the desktop site. |
The stronger versions contain a number, a cause or a deadline. They can be checked, and they can be disproved, which is the point.
Using evidence
Evidence turns an opinion into a justification. Useful sources include:
- Operational data, such as ticket volumes, error rates, cycle times and costs.
- Customer or staff feedback, such as survey results and complaint counts.
- External pressure, such as a regulation with a compliance date, a contract requirement or a competitor's move.
- Strategic documents, such as a company plan that names this area as a priority.
Name the source and the date of each figure. "Customers are unhappy" is an impression. "The March survey scored responsiveness at 58, down from 70 the previous year" is a fact that a reader can verify.
If the evidence is thin, say so. A sentence such as "No baseline measurement exists yet. Collecting one is the first task in the project" is more useful than a confident claim that cannot be supported. Hidden gaps in evidence tend to surface later as disputes about whether the project worked.
Linking the justification to strategy
Approvers compare projects against each other. A justification that connects the work to an organizational goal gives them a reason to rank it above competing requests. Cite the specific goal, for example "supports the company objective to retain 95% of enterprise accounts this year", rather than a generic phrase such as "aligns with our strategy".
Be careful not to stretch the link. If a project only loosely relates to a strategic goal, a forced connection will be noticed and will weaken trust in the rest of the document.
Quantifying benefits honestly
Benefits fall into two groups. Tangible benefits have a money value, such as cost savings, added revenue or avoided penalties. Intangible benefits, such as better staff morale or stronger brand reputation, matter but are harder to price.
Guidelines for stating them:
- Give ranges when the figure is an estimate, and say how you got it.
- Separate one-off benefits from recurring ones. A saving of 20,000 per year is not the same as a single saving of 20,000.
- Include the main costs alongside the benefits, or point to the section that does.
- List intangible benefits without inventing a price for them. A rough number with no basis invites argument.
- Describe the benefit as an effect on the organization. "Staff will have a new tool" is a feature, not a benefit.
Here is a short justification for a customer support project that applies these guidelines.
## 1. Purpose and Justification
**Problem.** The median first response to a support ticket is 8 hours
(ticketing report, October). The responsiveness score in the annual customer
survey fell from 70 to 58 over the same year.
**Impact of inaction.** Enterprise customers who rated responsiveness below 60
cancelled at twice the rate of other customers last year. At the current rate,
we expect to lose an estimated 400,000 to 600,000 in annual recurring revenue
(finance estimate, based on last year's cancellations).
**Proposed response.** Replace the current ticketing tool with a platform that
supports automatic routing, and train support staff to use it.
**Expected benefit.** Faster first responses, lower cancellations among
enterprise customers, and fewer escalations to engineering. The estimated
one-off cost is in section 8. No increase in support headcount is planned.
**Strategic link.** Supports the company goal to retain 95% of enterprise
accounts this year.
**Evidence gap.** Escalation rates are not tracked today. Establishing a
baseline is the first task in the project.Edge cases
Mandatory projects. Some projects exist because a law, a contract or a security finding requires them. The justification is then the obligation itself: state the requirement, its source and its deadline, and the consequence of missing it. You do not need a benefit estimate, but you should still compare the cost with the penalty for non-compliance, because it affects how much to spend.
Projects with uncertain benefits. Research or pilot projects may not have a reliable benefit figure. State the question the project will answer and what decision the answer will support. The justification then becomes the value of the information, not a forecast of savings.
Inherited projects. If a project was started before you wrote the charter, resist copying the original reasons without checking them. Conditions may have changed. Confirm with the sponsor that the stated reason still holds.
Several competing reasons. Different stakeholders may want the project for different reasons. List the main one first and mark the others as secondary. If the reasons conflict, for example one group wants lower cost and another wants more features, resolve this with the sponsor before the charter is approved. Otherwise the conflict will reappear as a dispute over scope.
Checking your draft
Before you submit the section, ask these questions:
- Could someone outside the project understand the problem without any background?
- Is each figure tied to a source and a date?
- Does the section describe a problem or opportunity, not only a product or activity?
- Does it say what happens if the organization does nothing?
- Would the sponsor sign it knowing that others will read it later to judge the project?
Exercise
A draft charter says: "The purpose of this project is to implement a new HR portal, which will modernize our processes and improve employee satisfaction." Name two weaknesses and rewrite the first sentence so that it states a problem with evidence.
Show answer
First, the sentence names a solution (an HR portal) instead of a problem. Second, "modernize" and "improve satisfaction" give no evidence, source or number, so no one can verify them. A stronger rewrite: "HR staff spend about 15 hours a week answering leave and payslip questions by email, and the staff survey rated HR responsiveness at 54 out of 100 (survey, June). A self-service portal is proposed to cut these requests." Any rewrite is acceptable if it states a measured problem, cites a source, and leaves the solution as the proposed response.
Exercise
Your project is required by a new data protection regulation that takes effect on 1 January. What should the justification contain, and what do you still need to check even though no benefit estimate is needed?
Show answer
It should state the regulation, the date it takes effect, what it requires of the organization, and the consequence of missing the date, such as fines or loss of contracts. You should still compare the project cost with the penalty for non-compliance, and check whether the regulation allows more than one way to comply, because that affects the scope and budget you propose.