Charter, Business Case, Project Plan and Statement of Work
This chapter assumes you know what a project charter is for (the previous chapter) and that you are familiar with the roles of sponsor, project manager and team member. It separates the charter from three documents that people often confuse with it. After reading, you should be able to say which document answers which question, and which one to reach for when a dispute starts.
Why the confusion happens
Four documents touch the same project and share vocabulary: objectives, scope, budget, risks, timeline. A reader who sees "scope" in all four may conclude they are interchangeable. They are not. Each one exists for a different reader, is written at a different time, and answers a different question.
| Document | Core question | Main reader | Typical timing |
|---|---|---|---|
| Business case | Should we invest in this at all? | Executives who fund work | Before the project is approved |
| Project charter | Is this project authorized, and within what boundaries? | Sponsor, project manager, team, key stakeholders | At approval, before detailed planning |
| Statement of work (SOW) | What exactly will a supplier deliver, and on what terms? | Buyer and supplier | When work is contracted |
| Project plan | How will we deliver it, step by step? | Project team and project manager | After the charter, then updated throughout |
The business case: the reason to spend money
A business case argues that an investment is worthwhile. It compares options, usually including "do nothing", and weighs costs against benefits. It contains financial analysis such as cost, expected benefit, payback period or return on investment.
The business case is the input to the decision. The charter is the output of that decision. A charter does not repeat the full analysis. It carries a short justification (a few sentences or a short paragraph) and points to the business case for the evidence.
A common error is to paste the whole business case into the charter. This makes the charter long, and nobody reads it. Another error is the opposite: writing a charter with no justification and no link to a business case. The team then cannot tell why the project matters when they must make trade-offs.
The project charter: authorization and boundaries
The charter is short, often one to three pages. It does three jobs:
- It authorizes the project and names the project manager.
- It sets boundaries: objectives, scope, high-level budget, timeline and risks.
- It gives the project manager authority to use resources.
The charter stays at a high level on purpose. It says that a migration will finish by the third quarter within a stated budget. It does not say who does which task in which week.
The charter is signed by the sponsor, and often by other senior stakeholders. Its main reader is the group that must agree on what the project is. Months later, when someone asks for extra work, the charter is the reference people return to.
The project plan: how the work gets done
The project plan is a set of documents, not one page. Depending on the project it may include the schedule, work breakdown, resource plan, communication plan, risk register and quality plan. It is detailed and changes often.
The relationship is one of refinement. The charter says "launch by 30 September". The plan breaks that into tasks, owners, dependencies and dates that add up to that launch. If the plan shows the launch is impossible without more money or time, the plan does not quietly override the charter. The difference goes back to the sponsor as a change request (covered in a later chapter).
Common error: starting the plan before the charter is approved, then discovering that stakeholders disagree on scope. All the detailed work must be redone.
The statement of work: what a supplier owes
A statement of work describes the work a supplier will perform for a buyer. It is part of a contract or agreement. It typically lists the deliverables, the standards they must meet, the schedule, the payment terms and the acceptance process.
The SOW has legal weight, while the charter usually does not. A charter is an internal authorization. A SOW binds two parties, so it uses precise language that a lawyer or procurement officer can enforce.
The two documents connect in a specific way. The charter's scope and deliverables guide what the project needs to buy. Those needs then become the SOW. Not every project has a SOW. A project run entirely by internal staff may have none. Large projects may have several, one per supplier.
A mismatch is a real risk. If the SOW promises the supplier will deliver things the charter lists as out of scope, the project has paid for unauthorized work. Check each SOW against the charter before signing.
How the documents flow
The documents usually appear in this order, though real projects can overlap them.
A worked comparison
Suppose a company wants to replace its customer database.
- Business case: "Maintenance of the old system costs 400,000 a year and causes outages. A new platform costs 900,000 once and 150,000 a year. Payback is under four years." It compares three options.
- Charter: "Migrate the customer database to the new platform by 30 September within a budget of 900,000. Out of scope: website redesign. Priya Rao is project manager with authority to approve spending up to 20,000 without further sign-off."
- Statement of work: "The vendor will migrate 12 million records, run two rehearsal migrations, and fix defects found in acceptance testing for 30 days. Payment: 30% on signing, 50% on successful rehearsal, 20% on acceptance."
- Project plan: "Week 3: data mapping complete. Week 6: first rehearsal. Weeks 7 to 8: fix defects." It includes task owners and dependencies.
Notice that each document uses the same facts at a different level of detail. The figure 900,000 appears in the business case and the charter. It must match.
Keeping the documents consistent
Because they overlap, the documents can drift apart. Three habits reduce this:
- Treat the charter as the controlling reference for scope and authority. When another document disagrees, resolve the difference deliberately.
- State a figure in one place and refer to it elsewhere where possible.
- When the charter changes through approved change control, check the plan and any SOW for needed updates.
Which document answers which question
| Situation | Go to |
|---|---|
| An executive asks why we are doing this at all | Business case |
| A colleague asks you to add a feature | Charter scope section |
| You need to know who may approve a purchase | Charter authority section |
| A supplier says a task was not included in their price | Statement of work |
| The team asks what to work on next week | Project plan |
Exercise
A vendor's draft statement of work includes training for 500 staff. The signed charter lists staff training as out of scope for this project. What should the project manager do, and why?
Show answer
Do not sign the SOW as drafted. The SOW would commit money to work the charter does not authorize. Either remove the training from the SOW, or take a change request to the sponsor to bring training into scope (with any budget and schedule effects) and update the charter before the SOW is signed.
Exercise
Your project plan shows the project needs 1.1 million, but the charter budget is 900,000. Which document do you change first, and who must agree?
Show answer
Neither changes silently. The plan reveals a gap against the charter, so raise a change request to the sponsor. Options are to increase the budget, reduce scope or accept different trade-offs. Only after the sponsor approves a revised charter should the plan be baselined to the new figure.