Sub topic 13
Listing High-Level Risks
This chapter assumes you have read the earlier chapters on scope, deliverables, milestones, budget and resources, and assumptions and constraints. You should know what a project charter is and who signs it. The risk section draws on all of those, so a weak earlier section will show up here as vague or missing risks.
What a charter risk section is for
A risk is an uncertain event or condition that, if it happens, affects at least one project objective. It has a cause, an event and an effect. An issue is different: it has already happened and needs action now.
A charter risk section is short. It gives the sponsor and approvers a view of the main threats at the moment they decide to authorize the project. It does not replace the risk register, the detailed log of every risk that the project manager builds during planning. The charter lists perhaps five to ten risks. The register may hold fifty.
The section has three jobs:
- It tells approvers what they are agreeing to. Approval with no visible risks means approval based on an incomplete picture.
- It shows whether the project is viable. A project whose top risks are all severe and unmanageable may need to be reshaped or declined.
- It gives the project manager a starting list for the risk register, and a record that the sponsor knew about these risks when authorizing the work.
Where high-level risks come from
Do not brainstorm risks from a blank page. The earlier charter sections already contain most of them. The concept graph for this tutorial reflects this: risks depend on assumptions and constraints, and on budget and resources.
| Charter section | What to ask | Example risk |
|---|---|---|
| Assumptions | What if this assumption is false? | The vendor may not deliver the new platform by March, so migration cannot start. |
| Constraints | Which fixed limit is tightest? | The fixed budget leaves no room for the extra licenses a larger user count would need. |
| Scope | Which boundary is most likely to be pushed? | Stakeholders may request the website redesign, which is out of scope. |
| Milestones | Which date depends on something outside the team? | The legal review is scheduled by another department and may slip. |
| Budget and resources | Which people or funds are not yet secured? | The data engineer is shared with another project and may be unavailable. |
| Stakeholders | Who could block or withdraw support? | The support director has not yet agreed to release staff for training. |
Each unverified assumption is a candidate risk. If you wrote "the new platform will be ready by March" as an assumption, the matching risk is "the platform is not ready by March." Writing both is not duplication. The assumption states what you are planning around, and the risk states what happens if you are wrong and what you will do about it.
Two other sources are worth checking. Lessons learned from similar past projects often name risks that no one thinks of in the abstract. People who did the work before, such as operations staff or the team that ran the last migration, usually know where it went wrong.
Writing a risk statement
A useful risk statement has three parts: a cause, an uncertain event, and an effect on an objective. A common template is "Because of <cause>, <event> may occur, leading to <effect>."
Compare these:
| Weak | Better |
|---|---|
| Data problems | Because customer records come from three systems with different formats, duplicate or corrupt records may be found during migration, delaying go-live by up to four weeks. |
| Budget risk | Because vendor pricing is quoted in euros and our budget is in dollars, a currency change of more than 5% may raise platform costs beyond the approved budget. |
| Staff issues | Because two of the five trainers also support the current system, they may be unavailable during cutover, reducing training coverage. |
The weak versions name a topic. The better versions name something that can be assessed, assigned and monitored. They also tie the risk to a specific objective or milestone, which is what lets the sponsor judge its importance.
Avoid writing a risk that is really a missing task ("no test plan exists") or a certainty ("the deadline is tight"). If it will definitely happen, treat it as an issue or a constraint.
Rating risks at a high level
At charter stage you rarely have data for numeric probabilities. A simple three-level scale for probability and for impact is enough. Define each level in the charter so that readers rate the same way.
| Level | Probability | Impact on schedule or budget |
|---|---|---|
| Low | Unlikely, below about 20% | Less than 5% variance |
| Medium | Possible, about 20% to 50% | 5% to 15% variance |
| High | Likely, above about 50% | More than 15% variance, or an objective is missed |
Combine the two ratings to get a priority. A high-probability, high-impact risk is a top priority. A low-probability, low-impact risk may not belong in the charter at all.
Keep the scale simple. A five-by-five scoring matrix at this stage suggests precision you do not have. The ratings are judgments, and the goal is to rank risks, not to calculate them.
Adding an initial response and an owner
A risk list without responses only tells readers to worry. For each top risk, record a first response and a name.
The standard response types are:
- Avoid: change the plan so the risk cannot occur, for example by dropping a dependent feature.
- Mitigate: reduce the probability or impact, for example by running a pilot migration before the full one.
- Transfer: shift the impact to another party, for example through a fixed-price contract or insurance.
- Accept: do nothing now, and optionally set aside contingency time or money.
Owners at this stage are usually named roles or people who can act on the risk. The owner is not necessarily the person who will fix it. The owner watches for warning signs and raises the alarm.
A compact charter table looks like this:
## 10. High-Level Risks
| ID | Risk | Prob. | Impact | Response | Owner |
|----|------|-------|--------|----------|-------|
| R1 | Because the vendor has not confirmed its delivery date, the platform may arrive after March, delaying migration by up to 6 weeks. | Medium | High | Mitigate: add a delivery-date clause with penalties to the contract. | Procurement lead |
| R2 | Because customer records come from three systems, duplicates may delay go-live by up to 4 weeks. | High | Medium | Mitigate: run a pilot migration on 10% of records in month 2. | Technical lead |
| R3 | Stakeholders may request the website redesign, which is out of scope, expanding the work. | Medium | Medium | Avoid: apply the change process in Section 6. | Project manager |Notice that R3 links back to the scope section and the project manager's authority. Risks, scope and governance reinforce each other.
Edge cases and common errors
- Threats only. Risks can also be positive. An opportunity is an uncertain event that would benefit the project, such as a vendor releasing a feature early. Many charters include a short "opportunities" line. Do so only if you will act on it.
- Risks that belong to someone else. A risk to the organization's strategy, such as a competitor's move, may be the reason for the business case rather than a project risk. Decide whether the project can influence it.
- A single mega-risk. "The project may fail" is not a risk. Break it into causes you can respond to.
- Hiding risks to win approval. A charter with no high-rated risks on a complex project loses credibility. Approvers often read a clean risk section as a sign of weak analysis.
- Treating the list as final. The charter records risks known at authorization. The project manager must carry them into the risk register and review them regularly. A major new risk, such as a loss of funding, can also be grounds to revisit the charter, as covered in the chapter on reviewing and changing it.
- Contingency without a source. If a response says "use contingency," check that the budget section actually holds contingency, and say how much.
Checking the section before approval
Before sending the charter for signature, check these points:
- Every unverified assumption in the charter has a matching risk, or a stated reason why it does not.
- Each risk names a cause, an event and an effect on an objective, milestone or budget line.
- Probability and impact use the scale defined in the charter.
- Each top risk has a response type and an owner.
- The list is short enough to read in a few minutes.
Exercise
A charter assumes that "the finance team will provide a part-time analyst for four months." Write a high-level risk statement for this assumption using the cause, event and effect pattern. Then rate it on the three-level scale, and name one response type with an owner.
Show answer
Sample answer: "Because the analyst is also assigned to year-end reporting, the finance team may withdraw the analyst in months 3 and 4, leaving the budget forecasts incomplete and delaying the final cost milestone by about three weeks." Rating: Medium probability, Medium impact. Response: Mitigate by agreeing a written allocation with the finance director and naming a backup analyst. Owner: the project manager, or the sponsor if the agreement needs senior authority. Any answer is acceptable if it has a cause, an event and an effect tied to the schedule or budget, and uses defined ratings, one of the four response types and a named owner.
Exercise
A draft charter lists these risks: "Budget," "The deadline is tight," and "A key supplier may go out of business, leaving no source for a critical part and halting production for at least two months." Which items need rewriting, and why?
Show answer
"Budget" is a topic, not a risk, because it has no cause, event or effect. "The deadline is tight" is a condition that already exists, so it belongs under constraints, or it should be rewritten as a specific uncertain event that threatens the date. The third item is acceptable, because it names an event, a consequence and a size of impact. It could be improved by adding a cause, such as the supplier's financial condition.