Why SPI drifts toward 1.0 as a project ends
This chapter assumes you can compute planned value (PV), earned value (EV) and the Schedule Performance Index (SPI = EV / PV) from earlier chapters. It also assumes you know that PV is cumulative and that budget at completion (BAC) is the final value of the PV curve. Here you will see why SPI becomes unreliable late in a project, and how to spot the problem in your own reports.
The mechanism: PV stops growing, EV keeps climbing
PV is cumulative. It rises along the baseline until the planned finish date, where it reaches BAC. After that date, PV stays at BAC, because the plan contains no more work.
EV also rises toward BAC, because it is the value of the work actually completed. A project that is behind schedule reaches BAC later than planned, but it still reaches it. The sequence is:
- Before the planned finish, EV is below PV, so SPI is below 1.0.
- After the planned finish, PV is fixed at BAC. SPI is now EV / BAC, which is the fraction of the project done.
- When the work is finished, EV = BAC = PV, so SPI = 1.0 and SV = 0.
This holds however late the project was. A project that finishes a year after its planned date reports SPI = 1.0 on the day it completes. The index measures progress against the plan's value curve. It does not measure lateness, and the two stop agreeing when the curve flattens.
The same effect appears before the planned finish, on a smaller scale. Near the end of the baseline the PV curve is flat or shallow, so each period adds little to PV. EV keeps catching up on the work it missed, and SPI rises toward 1.0 even though the delay has not shrunk.
A worked example
Take a six-period project with BAC = 100,000. The cumulative PV at the end of each period is 10,000, 25,000, 40,000, 60,000, 80,000 and 100,000.
The team is steadily one period behind. At the end of each period, its EV equals the PV the plan expected one period earlier, apart from period 1, where EV is 5,000. It needs a seventh period to finish.
| Period | PV | EV | SPI (EV / PV) | SV (EV − PV) |
|---|---|---|---|---|
| 1 | 10,000 | 5,000 | 0.500 | −5,000 |
| 2 | 25,000 | 10,000 | 0.400 | −15,000 |
| 3 | 40,000 | 25,000 | 0.625 | −15,000 |
| 4 | 60,000 | 40,000 | 0.667 | −20,000 |
| 5 | 80,000 | 60,000 | 0.750 | −20,000 |
| 6 | 100,000 | 80,000 | 0.800 | −20,000 |
| 7 | 100,000 | 100,000 | 1.000 | 0 |
The delay is one period at every status date after the first, yet SPI climbs from 0.400 to 1.000. In period 7 the report shows SV = 0 and SPI = 1.0 for a project that finished a full period late. A reader who looks only at the final row would conclude the project was on schedule.
Seeing the drift in code
The earned schedule (ES) method from the previous chapter asks a different question. It finds the time at which the plan expected the current EV, instead of dividing values. The code below computes both indices for the example.
cum_pv = [10_000, 25_000, 40_000, 60_000, 80_000, 100_000]
ev_by_period = [5_000, 10_000, 25_000, 40_000, 60_000, 80_000, 100_000]
def pv_at(period):
"""Cumulative PV at the end of a period; it stays at BAC after the plan ends."""
return cum_pv[min(period, len(cum_pv)) - 1]
def earned_schedule(ev):
"""Periods of planned progress earned so far, by linear interpolation."""
prev = 0.0
for i, pv in enumerate(cum_pv):
if ev <= pv:
return i + (ev - prev) / (pv - prev)
prev = pv
return float(len(cum_pv))
print("period SPI SPI(t)")
for period, ev in enumerate(ev_by_period, start=1):
spi = ev / pv_at(period)
spi_t = earned_schedule(ev) / period
print(f"{period:>6} {spi:.3f} {spi_t:.3f}")Running it prints:
period SPI SPI(t)
1 0.500 0.500
2 0.400 0.500
3 0.625 0.667
4 0.667 0.750
5 0.750 0.800
6 0.800 0.833
7 1.000 0.857The SPI column ends at 1.000. The SPI(t) column ends at 0.857, which is the planned duration of 6 periods divided by the actual duration of 7. Both indices rise over time, but only SPI(t) still reports that the project is late.
Why SPI(t) does not drift
SPI(t) compares two durations: the planned time at which this much value should have been earned, and the actual time. Neither side depends on how flat the PV curve is, because the interpolation in the ES calculation already accounts for the slope. Once the project is complete, ES is capped at the planned duration, and the actual duration keeps growing as the project overruns. The ratio then falls below 1.0 and stays there, which is the correct signal.
You can also forecast from it. Dividing the planned duration by SPI(t) gives an estimated total duration. In period 6 this is 6 / 0.833 = 7.2 periods, close to the real finish of 7. The cost-based SPI cannot give you a usable date forecast at that point.
Other limits of SPI to remember
- SPI counts all work equally. A late task off the critical path lowers SPI without delaying the finish. A late critical task can be hidden by early non-critical work that pushes SPI up. SPI cannot tell these apart.
- SPI is in money, not time. An SPI of 0.8 does not mean "20% late in calendar terms". The distance in time depends on how steep the PV curve is at that point.
- SPI is weakest in the last third. Many practitioners treat SPI as unreliable once the project is roughly two-thirds through its planned duration, and certainly after the planned finish date. This is a rule of thumb, not a standard.
- CPI does not have this problem. AC is real spending, which keeps growing as work continues, so CPI = EV / AC keeps reflecting overruns. You can use CPI to the end of the project. An SPI-based forecast formula such as BAC / (CPI × SPI) inherits the drift, so avoid it late in the project.
Decision criteria: what to use when
| Situation | Use | Reason |
|---|---|---|
| Early or middle of the project | SPI and SV | The PV curve is steep, so the drift is small and the cost-based figures are adequate. |
| Last third of the baseline, or any time after the planned finish | SPI(t) and ES | They keep measuring time directly. |
| You need to know whether the finish date will move | Critical path analysis, with SPI(t) as a cross-check | SPI mixes critical and non-critical work. |
| Cost forecast at any stage | CPI-based EAC | AC does not flatten at the end. |
Common mistakes
- Reading a rising SPI as recovery. Check whether the schedule gap, measured in time, is actually shrinking.
- Closing the schedule variance to zero in the final report without noting the actual finish date.
- Applying a threshold such as "SPI below 0.9 is a red flag" in the last phase. A late project can sit above any threshold you pick.
- Skipping the baseline finish date. EV compared against a stale PV curve gives meaningless indices, so update PV only through formal re-baselining.
Exercise
A project has BAC = 200,000 and a planned duration of 10 periods. It completes in period 13. In period 13, what are SPI and SV, and what does that tell you about the project's lateness? Which measure would show the delay, and what value would SPI(t) take at completion?
Show answer
At completion EV = BAC = 200,000 and PV = BAC = 200,000, because PV stays at BAC after period 10. So SPI = 200,000 / 200,000 = 1.0 and SV = 0. These figures say nothing about the three-period delay. SPI(t) would show it. ES at completion is capped at the planned duration of 10 periods, and the actual time is 13, so SPI(t) = 10 / 13 ≈ 0.769. The simple comparison of the actual finish (period 13) with the baseline finish (period 10) also shows a 3-period slip.
Exercise
In the six-period example, the project is at period 5 with EV = 60,000 and PV = 80,000. Calculate SPI, then ES and SPI(t). Use the interpolation described in the chapter, with cumulative PV values 10,000, 25,000, 40,000, 60,000, 80,000, 100,000. Then forecast the total duration as planned duration divided by SPI(t).
Show answer
SPI = 60,000 / 80,000 = 0.750. EV of 60,000 equals the cumulative PV at the end of period 4, so ES = 4.0. SPI(t) = 4.0 / 5 = 0.800. The forecast duration is 6 / 0.800 = 7.5 periods, which is close to the actual finish at 7 periods and is a more useful date signal than SPI.